The ISOLDE consolidation project Mats Lindroos The ISOLDE

  • Slides: 18
Download presentation
The ISOLDE consolidation project Mats Lindroos

The ISOLDE consolidation project Mats Lindroos

The ISOLDE facility Mats Lindroos

The ISOLDE facility Mats Lindroos

Objectives for the consolidation project • To bring the level of radiation safety to

Objectives for the consolidation project • To bring the level of radiation safety to a level compatible with European legislation • To consolidate the facility so that the required number of shifts per year are assured. Mats Lindroos

Project organization • Project leader: Mats Lindroos • Budget and time frames established by

Project organization • Project leader: Mats Lindroos • Budget and time frames established by project leader for all activities • 13 sub-projects each lead by a sub-project leader • Sub-project leaders work independently within given frames and reports to project leader at monthly project meeting Mats Lindroos

Sub-projects Radiation-safety improvements • 2. 1 Building 179 and 838 as class A radioactive

Sub-projects Radiation-safety improvements • 2. 1 Building 179 and 838 as class A radioactive laboratory – Project leaders: Erich Kugler and Richard Catherall • 2. 2 Building 170 as class C lab with special area for work with open radioactive sources (and modifications to buildings 507, 115 and 601) – Project leaders: Erich Kugler and Uwe Georg • 2. 3 Renovation of target manipulation robot – Project leader: Richard Catherall Mats Lindroos

Sub-project Consolidation (1) • 3. 1 New front-ends for the ISOLDE facility – Project

Sub-project Consolidation (1) • 3. 1 New front-ends for the ISOLDE facility – Project leader front-end 4: Stefano Marzari – Project leaders new generation: (Jan Borburgh and) Stefano Marzari • Guarantee running of the facility • Ease and cost of maintenance (lower personal dose) Mats Lindroos

Sub-project Consolidation (2) • 3. 2 Improvements of target manufacturing facilities – Project leader:

Sub-project Consolidation (2) • 3. 2 Improvements of target manufacturing facilities – Project leader: Jacques Lettry • Guarantee target production • Increase beam quality (REX) Mats Lindroos

Sub-project Consolidation (3) • 3. 3 High resolution separator – Project leader: Tim Giles

Sub-project Consolidation (3) • 3. 3 High resolution separator – Project leader: Tim Giles • High resolution mode – For the high resolution mode we need to: • A better theoretical understanding of the full system • Add control for higher order correction elements • New instrumentation • Beam cooler? Mats Lindroos

Sub-project Consolidation (4) • 3. 4 Improvements of LASER ion source – Project leader:

Sub-project Consolidation (4) • 3. 4 Improvements of LASER ion source – Project leader: New 5 th EIC • Enable routine operation and lowering operation costs Mats Lindroos

RILIS elements Mats Lindroos

RILIS elements Mats Lindroos

Sub-projects Consolidation (5) • 3. 5 Improvements of secondary beam transport system – Project

Sub-projects Consolidation (5) • 3. 5 Improvements of secondary beam transport system – Project leader: Uwe Georg • Reduce setting up-time for experiments (stable beam) • 3. 6 Consolidation of ISOLDE control system – Project leader: Frank Locci and Giuseppe Mornacchi • Integration into PS control structure (DB, piquet, spare parts…) Mats Lindroos

Sub-projects Consolidation (6) • 3. 9 ISOLDE Power supplies – Project leader: Jean-Pierre Royer

Sub-projects Consolidation (6) • 3. 9 ISOLDE Power supplies – Project leader: Jean-Pierre Royer • Integrate maintenance in the PS power group’s structures • 3. 10 ISOLDE instrumentation – Project leader: Uli Raich and Gerrit Jan Focker • Integrate maintenance in PS beam diagnostics group’s structure Mats Lindroos

Sub-projects Consolidation (7) • The 2 last projects were not originally part of the

Sub-projects Consolidation (7) • The 2 last projects were not originally part of the consolidation – Equipment operational but NOT maintainable – Total lack of spares – An additional budget request for 2002 -3 will be sent to the director of accelerators ASAP. Mats Lindroos

Requested budget Mats Lindroos

Requested budget Mats Lindroos

Budget All costs in k. CHF Mats Lindroos

Budget All costs in k. CHF Mats Lindroos

Time plan Mats Lindroos

Time plan Mats Lindroos

Manpower • 15 human-years in total needed (5 per year) – Focus on consolidation

Manpower • 15 human-years in total needed (5 per year) – Focus on consolidation and safety for existing staff rather then development and research – Request for: • CERN visitors programmes • ISAC-ISOLDE collaboration? – Advancement is likely to be manpower limited Mats Lindroos

Dedicated to the ISOLDE users Mats Lindroos

Dedicated to the ISOLDE users Mats Lindroos