THE COMPACT LINEAR COLLIDER (CLIC) STUDY J. P. Delahaye for The Compact LInear Collider

THE COMPACT LINEAR COLLIDER (CLIC) STUDY J. P. Delahaye for The Compact LInear Collider Study Team http: //clic-study. web. cern. ch/CLIC-Study/ J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 1

Outline • CLIC work program and organisation towards feasibility demonstration by 2010 • Progress

Outline • CLIC work program and organisation towards feasibility demonstration by 2010 • Progress from last meeting of the Collaboration Board • Looking into the future after 2010 • Expanding CLIC/CTF 3 Collaboration • Conclusion J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 2

CLIC Chart 09 CLIC/CTF 3 Collab. Board M. Calvetti/LNF CLIC Advisory Committee T. Raubenheimer/SLAC

CLIC Chart 09 CLIC/CTF 3 Collab. Board M. Calvetti/LNF CLIC Advisory Committee T. Raubenheimer/SLAC CLIC Steering Committee J. P. Delahaye Conceptual Design Report H. Schmickler CLIC Design J. P. Delahaye CLIC/ILC Collaboration Technical Design Phase R. Corsini CLIC Physics & Detectors L. Linssen CLIC @ Collaboration Board 29 -05 -09 CTF 3 project G. Geschonke 3

World-wide CLIC / CTF 3 collaboration 32 institutes involving 19 funding agencies of 17

World-wide CLIC / CTF 3 collaboration 32 institutes involving 19 funding agencies of 17 countries 32 collaborating institutes Ankara University (Turkey) Argonne National Laboratoory, (USA) Athens University (Greece) Berlin Tech. Univ. (Germany) BINP (Russia) CERN CIEMAT (Spain). P. Delahaye Finnish J Industry (Finland) Gazi Universities (Turkey) JINR (Russia) JLAB (USA) KEK (Japan) Karlsruhe Univ. (Germany) LAL/Orsay (France) LAPP/ESIA (France) LLBL/LBL (USA) EPAC 2008 / CTF 3 G. Geschonke, CERN CLIC @CLIC Collaboration Board 29 -05 -09 NCP (Pakistan) INFN / LNF (Italy) North-West. Univ. Illinois (USA) J. Adams Institute, (UK) IRFU/Saclay (France) Helsinki Institute of Physics (Finland) IAP (Russia) IAP NASU (Ukraine) Instituto de Fisica Corpuscular (Spain) Oslo University (Norway) Patras University (Greece) PSI (Switzerland), Polytech. University of Catalonia (Spain) RAL (England) RRCAT-Indore (India) Royal Holloway, Univ. London, (UK) SLAC (USA) Svedberg Laboratory (Sweden) 4 4 Thrace University (Greece) Uppsala University (Sweden)

CLIC/CTF 3 Multi-Lateral Collaboration of Volunteer Institutes 31 institutes involving 19 funding agencies from

CLIC/CTF 3 Multi-Lateral Collaboration of Volunteer Institutes 31 institutes involving 19 funding agencies from 17 countries Organized as a Physics Detector Collaboration Collab. Board: Chair: M. Calvetti/INFN; Spokesperson: G. Geschonke/CERN Mo. U with addenda describing specific contribution (& resources) http: //clic-meeting. web. cern. ch/clic-meeting/CTF 3_Coordination_Mtg/Table_Mo. U. htm Members (full responsibility of work packages and providing corresponding resources): • CERN members with additional voluntary contributions: CERN, Finland (HIP), France (IRFU, LAL, LAPP), Germany (Karlsruhe), Greece (Athens, Patras, Thrace) , Italy (LNF), Norway (Oslo U. ), Spain (CIEMAT, UPC, IFIC), Sweden (Uppsala), Switzerland (PSI), UK (Cockcroft, JAI, RHUL) • CERN non members with voluntary contributions: India (RRCAT), Japan (KEK), Pakistan (NCP), Russia (BINP, IAP, JINR), Turkey (Ankara U. , Gazi U. ), Ukraine (IAP), USA (ANL, JLAB NWU, SLAC) Mo. U under discussion: China (IHEP, Tsinghua Univ. ), Iran (IPM), J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 5

CLIC/CTF 3 Collaboration Recent new members • Argonne National laboratory/ANL (USA) • Positron generation

CLIC/CTF 3 Collaboration Recent new members • Argonne National laboratory/ANL (USA) • Positron generation studies • Greek Universities: National Technical University of Athens University of Patras The Democritus University of Thrace Beam Instrumentation – High precision mechanical studies and construction – Digital electronics – Controls sytems – Machine Detector Interface – • Karlsruhe University: Laboratory for Application of Synchrotron Radiation/LAS (Germany) • Development of Superconducting Wigglers for the CLIC Damping Ring • Important development of collaboration between CERN, KEK and SLAC about Structures designs, construction and tests as well as GHz Klystron for stand alone power tests J 12. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 6

J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 7

J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 7

Participants to CLIC 08 215 (registered) from 57 Inst. of 18 countries • China:

Participants to CLIC 08 215 (registered) from 57 Inst. of 18 countries • China: Tsinghua University • Finland: Helsinki Univ, HIP • Poland: Inst of Nucl Phys • France: CEA Saclay, LAL, IPNL- • Spain: CIEMAT, IFIC, Catalonia Univ. , IN 2 P 3, IRFU-SPP, LAPP, LPHNE • Germany: Bonn Univ. , DESY, Forschungszentrum Karlsruhe, Greifswald Univ. , Max. Planck Inst. • Greece: Nat Tech Univ. , NTU Athens • India: BARC-RRCAT, Ravishankar Shukla Univ • Italy: LNF-INFN • Japan: KEK • Norway: Univ of Oslo • Pakistan: NCP, Air Univ. J. P. Delahaye • Russia: BINP, JINR, SINP-MSU UPC Univ • Sweden: MAX-Lab, Uppsala Univ. • Switzerland: EPFL, ETH, PSI • Turkey: Ankara Univ. , TAEA • United-Kingdom: ASTe. C, Birmingham Univ. , Cockcroft Inst. , Euclid Tech. Lab, Manchester Univ. , RHUL, JAI, Oxford Univ. , RAL, Lancaster Univ. , STFC • United-States: ANL, Colorado Univ. , Cornell Univ. , LBNL, FERMILAB, SLAC, NASA Inspires CLIC @ Collaboration Board 29 -05 -09 8

FP 7 - Eu. CARD • European Coordination of Accelerator Research and Development •

FP 7 - Eu. CARD • European Coordination of Accelerator Research and Development • Eu. CARD is an “Integrating Activity” (IA) supported by the European Commission (EC) and coordinated by CERN • 37 “beneficiaries” (participating labs, universities and companies) from 12 European countries. • Duration: April 2009 – March 2013 • Overall budget: 33 M€, EC contribution: 10 M€ • Details at: https: //eucard. web. cern. ch/Eu. CARD/index. html J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 9

NETWORKING ACTIVITIES JOINT RESEARCH ACTIVITIES HFM FAIR PP External communcation & dissemination (incl. Public

NETWORKING ACTIVITIES JOINT RESEARCH ACTIVITIES HFM FAIR PP External communcation & dissemination (incl. Public information website) Col. Mat Acc. Net ANAC Euro. Lumi Laserlab II HEP community at large, general public SLHC-PP Project management and internal communication RFTech NEU 2012 EUROnu DS SRF MICE (TA-STFC) J. P. Delahaye ILCHi. Grade. PP NCLinac Hi. Rad. Mat@SPS (TA-CERN) TRANSNATIONAL ACCESS CLIC @ Collaboration Board 29 -05 -09 10

Eu. CARD WP 9 “NCLinac” • Full name: “Technology for normal conducting higher energy

Eu. CARD WP 9 “NCLinac” • Full name: “Technology for normal conducting higher energy linear colliders” • 5 tasks: – NCLinac Coordination and Communication – Normal conducting High Gradient Cavities PETS, alignment & HOM’s, breakdown simulation, BD diagnostics, precise assembly – Linac and Final Focus Stabilisation Quadrupole mock-up, FF test-stand – Beam Delivery System tuning procedures at ATF 2, high-precision BPM’s, Laser-wire – Drive Beam Phase control 20 fs RF monitor, electro-optical monitor • Partners: CERN, CIEMAT, CNRS, INFN, PSI, RHUL, • Resources: 6. 5 MEuros, 540 persons-years STFC, UNIMAN, UOXF-DL, UU J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 11

A necessary and beneficial CLIC /ILC Collaboration http: //clic-study. web. cern. ch/CLIC-Study/CLIC_ILC_Collab_Mtg/Index. htm •

A necessary and beneficial CLIC /ILC Collaboration http: //clic-study. web. cern. ch/CLIC-Study/CLIC_ILC_Collab_Mtg/Index. htm • Focusing on subjects with strong synergy between CLIC & ILC • making the best use of the available resources • adopting systems as similar as possible • identifying and understanding the differences due to technology and energy (technical, cost…. ) • developing common knowledge of both designs and technologies on status, advantages, issues and prospects for the best use of future HEP • preparing together by the Linear Collider Community made up of CLIC & ILC experts: • the future evaluation of the two technologies • proposal(s) best adapted to the (future) HEP requirements J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 12

CLIC and ILC layouts ILC @ 500 Ge. V J. P. Delahaye CLIC @

CLIC and ILC layouts ILC @ 500 Ge. V J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 13

Subjects with strong synergy Working Groups & Conveners CLIC ILC Physics & Detectors L.

Subjects with strong synergy Working Groups & Conveners CLIC ILC Physics & Detectors L. Linssen, D. Schlatter F. Richard, S. Yamada Beam Delivery System (BDS) & Machine Detector Interface (MDI) D. Schulte, R. Tomas Garcia E. Tsesmelis B. Parker, A. Seriy Civil Engineering & Conventional Facilities C. Hauviller, J. Osborne, V. Kuchler Positron Generation (new) L. Rinolfi J. Clarke Damping Rings (new) Y. Papaphilipou M. Palmer Beam Dynamics D. Schulte A. Latina, K. Kubo, N. Walker Cost & Schedule P. Lebrun, K. Foraz, G. Riddone J. Carwardine, P. Garbincius, T. Shidara J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 14

Evolution of CLIC-ILC collaboration Towards Linear Collider management? • Joint meeting on 12/06 at

Evolution of CLIC-ILC collaboration Towards Linear Collider management? • Joint meeting on 12/06 at CERN of: CLIC SC + ILC EC + CERN management Agenda: - evolution of CLIC/ILC collaboration - future policy about Linear Colliders - CLIC and ILC (better) synchronisation (workshops, publications, etc…) J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 15

CLIC Work program till 2010 • Demonstrate feasibility of CLIC technology • Major key

CLIC Work program till 2010 • Demonstrate feasibility of CLIC technology • Major key issues addressed in CTF 3 • Design of a linear Collider based on CLIC technology http: //clic-study. web. cern. ch/CLIC-Study/Design. htm • Estimation of its cost in the CERN area • CLIC Physics study and detector development: http: //clic-meeting. web. cern. ch/clic-meeting/CLIC_Phy_Study_Website/default. html • Conceptual Design Report including cost by 2010 J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 16

CLIC feasibility issues J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 17

CLIC feasibility issues J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 17

Nominal performance of Accelerating Structures Design@CERN, Built/Tested @KEK, SLAC KEK J. P. Delahaye CLIC

Nominal performance of Accelerating Structures Design@CERN, Built/Tested @KEK, SLAC KEK J. P. Delahaye CLIC target CLIC @ Collaboration Board 29 -05 -09 18

Power Production Structure (PETS ) design, built@CERN, power tests @ CTF 3, SLAC CTF

Power Production Structure (PETS ) design, built@CERN, power tests @ CTF 3, SLAC CTF 3 Measured (current) Measured (power) Model (power) J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 19

PETS ON/OFF The tunable choke “proof of principle” high power tests at SLAC (autumn

PETS ON/OFF The tunable choke “proof of principle” high power tests at SLAC (autumn 2009) with klystron. The mechanical design is under way. If tests will be successful, one of the TBL PETS will then equipped with such a device ON The short position in choke moved by 5. 4 mm OFF J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 20

Conceptual Design Report (CDR) preparation J. P. Delahaye CLIC @ Collaboration Board 29 -05

Conceptual Design Report (CDR) preparation J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 21

Beyond 2010 • Work plan (2011 -2015) assuming successful feasibility demonstration by 2010 :

Beyond 2010 • Work plan (2011 -2015) assuming successful feasibility demonstration by 2010 : 201006_CLIC_LTP_2006_15. doc • Preparation of a Technical Design Report • Task Force (R. Corsini) with preliminary report to ACE and final report end June in order to: • define detailed work program • identify possible schedule based on planned resources (CERN and Collaborators) • Plan work by the various teams described with resources in CERN Medium Term Plan next year (MTP 10). J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 22

J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 23

J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 23

CLIC resources in MTP 09 Medium Term Plan (2009 -2014) J. P. Delahaye CLIC

CLIC resources in MTP 09 Medium Term Plan (2009 -2014) J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 24

J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 25

J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 25

CLIC LTP Proposal MTP 08 Int. Budget 09 Possible future MTPs MTP 09 White

CLIC LTP Proposal MTP 08 Int. Budget 09 Possible future MTPs MTP 09 White Paper 2011 -2014 Acc: 190 MCHF Det: 16 MCHF J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 Complemented by welcome volunteer contributions from Collaborating Institutes 26

Tentative long-term CLIC scenario Shortest, Success Oriented, Technically Limited Schedule Technology evaluation and Physics

Tentative long-term CLIC scenario Shortest, Success Oriented, Technically Limited Schedule Technology evaluation and Physics assessment based on LHC results for a possible decision on Linear Collider with staged construction starting with the lowest energy required by Physics Council decision on CLIC TDR phase extension to be adapted to detailed work program (Corsini) and resources availability J. P. Delahaye Conceptual Design Report (CDR) Technical Design Report (TDR) CLIC @ Collaboration Board 29 -05 -09 Project approval ? First Beam? 27

Conclusion • Well defined CLIC organisation and R&D work program towards feasibility demonstration and

Conclusion • Well defined CLIC organisation and R&D work program towards feasibility demonstration and CDR edition by end 2010 • Endorsed after detailed scrutiny by Advisory Committee • Under schedule but still lot of work to be done! • Definition of program after 2010 towards TDR by mid 2009: • Requested by Collaboration Institutes • Reflection on work program (task force) • CERN resources planned • CLIC/CTF 3 collaboration very fruitful and expanding • Excellent spirit of competitive collaboration with ILC J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 28

Spares J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 29

Spares J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 29

Strategy for Design & Parameters • Design at 3 Te. V (nominal) and 500

Strategy for Design & Parameters • Design at 3 Te. V (nominal) and 500 Ge. V (comparison with ILC) • Define range of beam parameters from conservative to nominal at both energies • Conservative beam parameters at 500 Ge. V being demonstrated or addressed somewhere by 2010 • Realistic and optimum 500 Ge. V design • As a fist stage towards nominal energy of 3 Te. V • Optimum parameters and components (Accelerating Structure with reduced accelerating gradient and good efficiency • Larger beam emittances and relaxed tolerances • Realistic scenario of successive upgrades in 4 phases • energy and luminosity • Provide more time for gradual improvement and feasibility demonstration of nominal parameters J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 30

CLIC Parameters and upgrade scenario http: //cdsweb. cern. ch/record/1132079/files/CERN-OPEN-2008 -021. pdf 4 th phase:

CLIC Parameters and upgrade scenario http: //cdsweb. cern. ch/record/1132079/files/CERN-OPEN-2008 -021. pdf 4 th phase: 3 Te. V luminosity upgrade 3 Te. V nominal parameters 2 nd phase: 500 Ge. V luminosity upgrade 500 Ge. V nominal parameters 3 rd phase: 0. 5 to 3 Te. V energy upgrade 3 Te. V conservative parameters 1 rst phase: Initial operation 500 Ge. V conservative parameters J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 31

Beam emittances at Damping Rings J. P. Delahaye CLIC @ Collaboration Board 29 -05

Beam emittances at Damping Rings J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 32

Beam sizes at Collisions J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09

Beam sizes at Collisions J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 33

326 klystrons 33 MW, 139 ms combiner rings drive beam accelerator 2. 37 Ge.

326 klystrons 33 MW, 139 ms combiner rings drive beam accelerator 2. 37 Ge. V, 1. 0 GHz 1 km delay loop TA R=120 m , e- main linac , 12 GHz, 100 MV/m 21. 04 km BC 2 IP 1 e+ main linac 245 m TA R=120 m CLIC overall layout 3 Te. V booster linac, 9 Ge. V, 2 GHz injector 2. 4 Ge. V J. P. Delahaye Drive Beam Generation Complex BDS 2. 75 km 48. 3 km e- 1 km CR 1 decelerator, 24 sectors of 868 m BDS 2. 75 km BC 2 delay loop CR 2 CR 1 245 m drive beam accelerator 2. 37 Ge. V, 1. 0 GHz Circumferences delay loop 80. 3 m CR 1 160. 6 m CR 2 481. 8 m BC 1 e- DR 365 m e+ injector, 2. 4 Ge. V CLIC @ Collaboration Board 29 -05 -09 Main Beam Generation Complex Main & Drive Beam generation complexes not to scale 34

326 klystrons 33 MW, 29 ms combiner rings drive beam accelerator 2. 47 Ge.

326 klystrons 33 MW, 29 ms combiner rings drive beam accelerator 2. 47 Ge. V, 1. 0 GHz 1 km delay loop TA R=120 m e- main linac , 12 GHz, 80 MV/m, 4. 39 km BC 2 IP 1 e+ main linac 245 m TA R=120 m CLIC overall layout 0. 5 Te. V booster linac, 9 Ge. V, 2 GHz injector 2. 4 Ge. V J. P. Delahaye Drive Beam Generation Complex BDS 1. 87 km 13. 0 km e- 1 km CR 1 decelerator, 5 sectors of 868 m BDS 1. 87 km BC 2 delay loop CR 2 CR 1 245 m drive beam accelerator 2. 47 Ge. V, 1. 0 GHz Circumferences delay loop 80. 3 m CR 1 160. 6 m CR 2 481. 8 m BC 1 e- DR 365 m e+ injector, 2. 4 Ge. V CLIC @ Collaboration Board 29 -05 -09 Main Beam Generation Complex 35

CLIC main parameters http: //cdsweb. cern. ch/record/1132079? ln=fr Center-of-mass energy Beam parameters http: //clic-meeting.

CLIC main parameters http: //cdsweb. cern. ch/record/1132079? ln=fr Center-of-mass energy Beam parameters http: //clic-meeting. web. cern. ch/clic-meeting/clictable 2007. html CLIC 500 G Conservative Accelerating structure Total (Peak 1%) luminosity CLIC 3 Te. V Nominal Conservative 502 0. 9(0. 6)· 1034 Nominal G 2. 3(1. 4)· 103 1. 5(0. 73)· 103 4 Repetition rate (Hz) 5. 9(2. 0)· 1034 4 50 Loaded accel. gradient MV/m 80 100 Main linac RF frequency GHz 12 Bunch charge 109 6. 8 3. 72 Bunch separation (ns) 0. 5 Beam pulse duration (ns) 177 156 Beam power/beam (MWatts) 4. 9 14 Hor. /vert. norm. emitt (10 -6/10 -9) Hor/Vert FF focusing (mm) Hor. /vert. IP beam size (nm) Hadronic events/crossing at IP Coherent pairs at IP 3/40 2. 4/25 2. 4/20 0. 66/20 10/0. 4 8 / 0. 1 8 / 0. 3 4 / 0. 07 248 / 5. 7 202 / 2. 3 83 / 2. 0 40 / 1. 0 0. 07 0. 19 0. 57 2. 7 10 100 5 107 3. 8 108 BDS length (km) 1. 87 2. 75 Total site length km 13. 0 48. 3 Wall plug to beam transfert eff J. P. Delahaye CLIC @ Collaboration 7. 5%Board 29 -05 -09 6. 8% 36

CLIC – Main tunnel Schedule& Machine installation 3 Te. V 3 additional years 500

CLIC – Main tunnel Schedule& Machine installation 3 Te. V 3 additional years 500 Ge. V 7 years ready for HW commisioning 11 -9 (4. 39 km) 9 -7 (4. 39 km) 7 -5 (4. 39 km) 5 -3 (4. 39 km) 3 -1 (6. 26 km) 1 -2 (6. 26 km) 2 -4 (4. 39 km) 4 -6 (4. 39 km) 6 -8 (4. 39 km) 8 -10 (4. 39 km) 1 Civil Engineering 2 3 4 5 General Services 6 7 8 9 10 09 -Oct-0216 October 2008 J. P. Delahaye. CLIC 08 Workshop - Katy Foraz 37

CLIC Chart 09 CLIC/CTF 3 Collab. Board M. Calvetti/LNF CLIC Advisory Committee T. Raubenheimer/SLAC

CLIC Chart 09 CLIC/CTF 3 Collab. Board M. Calvetti/LNF CLIC Advisory Committee T. Raubenheimer/SLAC CLIC Steering Committee J. P. Delahaye CLIC meeting G. Geschonke Conceptual Design Report Editorial Board: H. Schmickler Technical Design Phase R. Corsini CLIC Physics & Detectors L. Linssen CLIC Design & Parameters J. P. Delahaye Beam Physics D. Schulte CTF 3 project G. Geschonke/R. Corsini CTF 3 Committee G. Geschonke Structure development W. Wuensch Commissioning & Operation R. Corsini Structure tests S. Doebert Installation & Exploitation L. Rinolfi & G. Geschonke Technical design H. Schmickler CALIFE W. Farabolini/CEA Cost, Power & Schedule P. Lebrun Two Beam Test Stand R. Ruber/UU-I. Syratchev TBL S. Doebert Photo Injector S. Doebert J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 12 GHz Test Stand K. Schirm 38

CLIC Web Site and Doc • Web site reflecting the CLIC organisation http: //clic-study.

CLIC Web Site and Doc • Web site reflecting the CLIC organisation http: //clic-study. web. cern. ch/CLIC-Study/Mtgs_Wkg_Grp. htm • Documentation on EDMS: https: //edms. cern. ch/cedar/plsql/navigation. go_to_tree? cookie=7682580&p_top_id=1724490 942 J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 39

CLIC in HEP context Complementary to LHC Collaborative competition with ILC CDR ILC TDR

CLIC in HEP context Complementary to LHC Collaborative competition with ILC CDR ILC TDR 1 ILC TDR 2 CLIC CDR CLIC TDR CARE J. P. Delahaye CLIC @ Collaboration Board 29 -05 -09 40