TE-VSC Activities for YETS 20152016 Te nt a tiv e Pl a nn in

TE-VSC Activities for YETS 20152016 Te nt a tiv e Pl a nn in g Jose A. Ferreira, Paul Demarest

TE-VSC activities (PSB) • • [BI line] Repair primary pump of fixed pumping group.

TE-VSC activities (PSB) • • [BI line] Repair primary pump of fixed pumping group. [BR 10] Test VPI 1 L 1 [BR 10] Replace VGP 14 L 5 if sector vented [BR 20] Replace leaking vacuum chamber in QFO 72 in 7 L 5 [BR 20] Replace vacuum chambers in 4 L 1 [BT] Test BT. VPI 23 Identification of unused cables (VSC-ICM). Weeks 49 -2 9/9/2020 Document reference 2

TE VSC support activities (PSB) • • • [Survey] Install new supports/adjustment jacks on

TE VSC support activities (PSB) • • • [Survey] Install new supports/adjustment jacks on bending magnet – 7 L 5? [TE-ABT] Pressure test septa cooling circuits BI. SMV 20, BE. SMH, BI. SMH, BT. SMV 10 and BT. SMV 20) [BE-BI] Replacement of BT 3. BPM 20 (1 day + pump down) [BE-BI] Wire scanner replacement (? ) [BE-BI] Replacement of BTP. BPM 20 (1 day + pump down) 9/9/2020 Document reference 3

TE-VSC activities (PS) • • • Repair short-circuits SS 01 Replacement of ion pump

TE-VSC activities (PS) • • • Repair short-circuits SS 01 Replacement of ion pump VPI 14, Replacement of gauges VGR 08, VGP 17, VGP 18, VGP 28, VGR 32 Consolidation of one fixed pumping group in PR 80 (Replacement of sector valve, turbo and controllers) New e-cloud monitor to be installed SS 98 9/9/2020 Document reference 4

TE-VSC support activities (PS) • • [BE-RF] Replacement of RF tuner in cavities SS

TE-VSC support activities (PS) • • [BE-RF] Replacement of RF tuner in cavities SS 08, 88 and 89 [BE-RF] Assist with repair of coupler on RF cavity SS 08. [Survey] Replacement of ion pumps to allow survey in positions 35, 36, 55, 60, 66, 86 and 99. [TE-ABT] Replacement of septa: SMH 16, SEH 31, SMH 42 [TE-ABT] Pressure test septa cooling circuits SMH 26 and SMH 57 [BE-BI] Installation of WCM in SS 03 [BE-BI] New BPM in SS 90 9/9/2020 Document reference 5

Other activities LINAC 2: Remove 5 BCTs in LBE, LBS and LTB lines, endoscopy

Other activities LINAC 2: Remove 5 BCTs in LBE, LBS and LTB lines, endoscopy of RFQ and maintenance of pumping groups • LINAC 3: Replacement of ITH. BCT 41 and some LIU-IONs activities • 9/9/2020 Document reference 6

Resources • • • 2 teams of 2 technicians for PS complex (includes LINAC

Resources • • • 2 teams of 2 technicians for PS complex (includes LINAC 2, LINAC 3, LINAC 4, AD and ISOLDE) In case of over-allocation TE-VSC will request prioritisation. We can only work on parallel activities if feasible. PSR – PSB. TE-VSC does not establish priorities or planning. We only give advice about the technical feasibility. All new or modified components must be vacuum acceptance tested before installation. Please send them ASAP. If one component has to be submitted during the YETS it must be included in the planning, as the same teams working in the machines carry out the vacuum acceptance testing. If components arrive late or are not accepted it will delay the installation. 9/9/2020 Document reference 7

Follow-Up • Share. Point site accessible to machine coordinators, to collect all requests, follow

Follow-Up • Share. Point site accessible to machine coordinators, to collect all requests, follow up ECRs and IMPACTs and check resources. 9/9/2020 Document reference 8