Tests and commissioning activities for the Static Var

  • Slides: 24
Download presentation
Tests and commissioning activities for the Static Var Compensators (SVCs) Karsten Kahle, Charles Genton,

Tests and commissioning activities for the Static Var Compensators (SVCs) Karsten Kahle, Charles Genton, Francisco R. Blánquez Power Converter Group (TE-EPC) FOM, 25. 8. 2020 Indico 3976873

SVC Tests and Commissioning activities in LS 2 Agenda Introduction SVC MEQ 59 for

SVC Tests and Commissioning activities in LS 2 Agenda Introduction SVC MEQ 59 for the Meyrin 18 k. V network SVC BEQ 1 for SPS SVCs for LHC SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 2

SVC Tests and Commissioning activities in LS 2 Introduction SVC MEQ 59 for the

SVC Tests and Commissioning activities in LS 2 Introduction SVC MEQ 59 for the Meyrin 18 k. V network SVC BEQ 1 for SPS SVCs for LHC SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 3

Why do we need SVCs? - Particle accelerators (power converters, RF etc. ) are

Why do we need SVCs? - Particle accelerators (power converters, RF etc. ) are very rough loads, comparable to heavy industry such as steel plants and rolling mills etc. - However, to obtain the precision required by the particle accelerators, the electrical network voltage needs to be a perfect 50 Hz sine-wave - In addition, our large cycles of reactive power would disturb the European 400 k. V network. SVCs strongly reduce the impact we have onto the outside network. Purpose of Static Var Compensators Assure the power quality of the 18 k. V networks, to allow the precision our accelerators require. SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 4

Basic topology of an SVC An SVC is composed of: TCR: Thyristor-Controlled Reactor Functions:

Basic topology of an SVC An SVC is composed of: TCR: Thyristor-Controlled Reactor Functions: • Network voltage stabilisation • Variable reactive power compensation Harmonic filters: passive filters tuned to specific frequencies Functions: • Harmonic filtering • Fixed reactive power compensation SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 5

Basic topology of an SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM

Basic topology of an SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 6

Impact of SVC switching manoeuvres Switch-On the harmonic filters Switch-On TCR: no disturbances Switch-On

Impact of SVC switching manoeuvres Switch-On the harmonic filters Switch-On TCR: no disturbances Switch-On harmonic filters: overvoltage +30% Recording of line voltages phase – ground (transient overvoltage typically +30% for 10… 20 ms) Voltage R – ground S – ground overvoltage T - ground Ref. EDMS 1026201 SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 7

Overview of SVC projects during LS 2 Four (4) large SVC projects simultaneously during

Overview of SVC projects during LS 2 Four (4) large SVC projects simultaneously during LS 2 Total project budget about 20 MCHF SVC MEQ 59 for Meyrin network (rating 25 Mvar) SVC BEQ 1 for SPS (150 Mvar) Harmonic Filters of PA 4 and PA 8 for LHC (25 Mvar) And new control systems for TCRs in PA 2 -4 -6 -8. SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 8

SVC Tests and Commissioning activities in LS 2 Introduction SVC MEQ 59 for the

SVC Tests and Commissioning activities in LS 2 Introduction SVC MEQ 59 for the Meyrin 18 k. V network SVC BEQ 1 for SPS SVCs for LHC SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 9

MEQ 59 for Meyrin 180 112 New SVC MEQ 59, located next to the

MEQ 59 for Meyrin 180 112 New SVC MEQ 59, located next to the 66 k. V transformer station in Meyrin (ref. GIS Portal # 1439) SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 10

MEQ 59 for Meyrin SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM

MEQ 59 for Meyrin SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 11

MEQ 59 for Meyrin TCR coils (low-noise design) 12

MEQ 59 for Meyrin TCR coils (low-noise design) 12

MEQ 59 for Meyrin Installation work is 100% completed Commissioning taking place now (heat

MEQ 59 for Meyrin Installation work is 100% completed Commissioning taking place now (heat run tests) Most commissioning activities completed: Before 6 September 2020 Only very few SVC switchings required after 7 September 2020 Dynamic performance tests with Booster machine: W 41/2020 (starting 5. 10. 2020) Impact of SVC switching is limited to Booster and PS (supply by dedicated 66/18 k. V transformer in s/station ME 59). Activities directly coordinated with EN-EL. Switching manoeuvres always coordinated with CCC-TI. SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 13

SVC Tests and Commissioning activities in LS 2 Agenda Introduction SVC MEQ 59 for

SVC Tests and Commissioning activities in LS 2 Agenda Introduction SVC MEQ 59 for the Meyrin 18 k. V network SVC BEQ 1 for SPS SVCs for LHC SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 14

BEQ 1 for SPS BE substation BEQ 1 400 k. V substation CCC BEQ

BEQ 1 for SPS BE substation BEQ 1 400 k. V substation CCC BEQ 3 BEQ 2 b. 774 SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 15

BEQ 1 for SPS SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM

BEQ 1 for SPS SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 16

BEQ 1 for SPS SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM

BEQ 1 for SPS SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 17

BEQ 1 for SPS SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM

BEQ 1 for SPS SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 18

BEQ 1 for SPS Installation work is 95% completed Commissioning starts now, until Mid

BEQ 1 for SPS Installation work is 95% completed Commissioning starts now, until Mid October First powering tests: end of Sept. / beginning of October Dynamic performance tests with SPS Mains beginning of 2021 (during TE-EPC commissioning of the SPS Mains) Impact of SVC switching is limited to one part of the SPS machine network, incl. the SPS pulsed loop (network of 400/18 k. V transfo EHT 1). Activities directly coordinated with EN-EL. Switching manoeuvres always coordinated with CCC-TI. SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 19

SVC Tests and Commissioning activities in LS 2 Agenda Introduction SVC MEQ 59 for

SVC Tests and Commissioning activities in LS 2 Agenda Introduction SVC MEQ 59 for the Meyrin 18 k. V network SVC BEQ 1 for SPS SVCs for LHC SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 20

SVCs for LHC The projects SEQ 4/SEQ 8 concern the consolidation of the harmonic

SVCs for LHC The projects SEQ 4/SEQ 8 concern the consolidation of the harmonic filters. SEQ 4: Installation work is 50% completed, Powering tests in W 46, 47, 48/2020 SEQ 8: Installation work will take place W 36 – W 49/2020, Powering tests in W 51/2020 and W 1/2021 In addition, the Thyristor Controlled Reactors (TCRs) receive a new digital control system (in all 4 LHC points). Impact of SVC switching is always limited to the machine network of the concerned LHC point. Switching manoeuvres always coordinated with CCC-TI. SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 21

SEQ 4/SEQ 8 for LHC PA 4 LHC PA 8 SVC Tests and Commissioning

SEQ 4/SEQ 8 for LHC PA 4 LHC PA 8 SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 22

SVCs for LHC System Pre-requisites EPC proposed schedule Feedback from LHC Coordination Meeting on

SVCs for LHC System Pre-requisites EPC proposed schedule Feedback from LHC Coordination Meeting on 14. 7. 2020 LHC PA 6, Powering tests of TCR and harmonic filters 66/18 k. V transformer and cooling water 28. , 29. , 30. 7. 2020 Maintenance in Sept. 2020 Tests are completed. T. b. d. LHC PA 2, Powering tests of TCR and harmonic filters 66/18 k. V transformer and cooling water TE-EPC ready from W 38/2020, 4 weeks of tests required W 38 - W 41/2020 approved LHC PA 4, Powering tests of TCR and harmonic filters 66/18 k. V transformer and cooling water TE-EPC ready from W 42/2020, 3 weeks of tests required Maintenance CV W 42 -45, Powering tests W 46 -47 -48/2020. LHC PA 8 (stage 1), Modif. of 66/18 k. V measurement circuit Switch-off 66/18 k. V transfo for 1. 5 days. Switch-over between LHC machine network and LHC loop. 1. 5 days anytime between today and end of October 2020 Possible betw. W 42 and W 45 during CV and CRYO maintenance. LHC PA 8 (stage 2), Powering tests of TCR and harmonic filters 66/18 k. V transformer and cooling water From December 2020, 3 weeks of tests needed Powering tests W 51/2020 and W 1/2021. SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 23

Thank you. Any questions? SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM

Thank you. Any questions? SVC Tests and Commissioning activities in LS 2 (TE-EPC), FOM 25. 8. 2020 24