TEC Module Production Overview Manfred Krammer HEPHY Vienna








- Slides: 8
TEC Module Production Overview Manfred Krammer HEPHY Vienna TEC Meeting, July 14, 2005
TEC Module Production Dashboard TEC Module Production Overview M. Krammer 2
Weekly Production Rates Production has ramped up to an average of 80 modules a week (assembly and bonding) compared to a theoretical possible maximum of 200. TEC Module Production Overview M. Krammer 3
Status TEC Production July 13 Total number of detector grade TEC modules available is 1368. In production (assembled but not yet finished) 153 modules Total need including spares is 6781 Percentage TEC modules available is 20. 17 % Congratulation we have produced 1/5 of the TEC modules TEC Module Production Overview M. Krammer 4
Outlook July/August A large number of hybrids (~635) will become available soon (end of July). Delivery has already started: 218 in shipping to gantries (Lyon, UCSB) and FNAL - about 5 weeks after delivery to CERN! Be prepared to assemble and bond these hybrids during the holiday period. A further 336 hybrids are in production at CERN. TEC Module Production Overview M. Krammer 5
Outlook July/August Instructions for CERN hybrid assembly: http: //wwwhephy. oeaw. ac. at/p 3 w/cms_tracker/modprod_overview/Hyb. Share. txt Default: For Batch 5 and 6: Exceptions from the default: All R 7 from this batch to Lyon Higher priority for R 5 S hybrids 12 W 6 A modules in Brussels TEC Module Production Overview M. Krammer 6
Outlook July/August Expected workload of gantries in July/August For details on module types etc. look at TEC-Org. xls file or the module production web pages. TEC Module Production Overview M. Krammer 7
Alignment Modules Number of alignment modules to be produced in July/August (all numbers from TEC-Org. xls): 70 R 4 A in Lyon 36 R 6 A in Brussels Schedule sensor coating in JENA: 168 W 4 already back in Karlsruhe 60 or 92 delivery July 15 90 delivery July 22 Sample tests (Rint) in Karlsruhe All sensors IV test in Vienna (Strasbourg) Sensors needed for the July/August production will be treated with high priority and should arrive in time in Lyon and Brussels. TEC Module Production Overview M. Krammer 8