TDC 2TCC 2 WG status report in EATM

  • Slides: 8
Download presentation
TDC 2/TCC 2 WG status report in EATM S. Evrard on behalf of the

TDC 2/TCC 2 WG status report in EATM S. Evrard on behalf of the TDC 2/TCC 2 WG 18. 06. 2013 1. 2. 3. 4. WP breakdown TDC 2/TCC 2 Visit on June 4 th Next issues ENTM agenda

Work package breakdown Activity WPA WDP Transport 15/01 OK Vacuum 22/01 OK Targets and

Work package breakdown Activity WPA WDP Transport 15/01 OK Vacuum 22/01 OK Targets and collimators 29/01 OK XTAX tables 05/02 OK Cooling and Ventilation 06/02 OK Civil Engineering 15/02 Magnets 26/02 OK LV electricity 19/03 OK Cabling 19/03 RP issues 02/04 OK Beam instrumentation 09/04 OK Survey DIMR Collective dose (m. Sv) OK 10. 5

Visit on June 4 th: TCSC dose rate measurement by means of Telerob TCSC

Visit on June 4 th: TCSC dose rate measurement by means of Telerob TCSC contact : 11 m. Sv/h

T 4 measurement from RP – 4 th June 2013 Ratio D/U ~ 1.

T 4 measurement from RP – 4 th June 2013 Ratio D/U ~ 1. 8 M. Calviani / E. Nowak - TCC 2 TDC 2 WG meeting 18 th June 2013 4

New CE issue: the mezzanine floor is not water tight

New CE issue: the mezzanine floor is not water tight

Cabling work: tough working conditions

Cabling work: tough working conditions

Next actions, topics, issues • • Laser scan of TA 801 (Thursday 20/06) BE-ABP

Next actions, topics, issues • • Laser scan of TA 801 (Thursday 20/06) BE-ABP + DGS-RP Survey Work package EN-MEF + BE-ABP New dose rate measurement (Friday 21/06, TBC) EN-HE + DGS-RP Tech. Spec. for: – Underground IT network EN-MEF + IT-CS – Chilled pipe removal (asbestos ? ) EN-CV – Dismantling works EN-MEF + DGS-RP TCSC and Target boxes and monitor storage in B. 954 GS-IS PVC insulation analysis TE-EPC + EN-MME Mezzanine floor water tighness issue GS-SE + EN-CV Risk analysis (cranes BA 80, B 954) EN-HE Shielded containers for target boxes and monitors EN-STI + EN-MEF + DGS-RP • ENTM on July 2 nd all WG members • • •

ENTM agenda July 2 nd • • • Rationales for TDC 2 Consolidation (S.

ENTM agenda July 2 nd • • • Rationales for TDC 2 Consolidation (S. Evrard) Planned Activities (E. Harrouch) ALARA Optimisation (S. Evrard) Transport Issues (J-L Grenard) Waste management (E. Harrouch) Risk analysis (E. Harrouch)