TCVFD Fire Station Project

TCVFD Fire Station Project

Fire Dep’t Cons’t Committee Chairman: Roger Chatterton-Chief/Gen Mngr Committee: Dick Hamilton Citizens: 1/10/2022 Barry

Fire Dep’t Cons’t Committee Chairman: Roger Chatterton-Chief/Gen Mngr Committee: Dick Hamilton Citizens: 1/10/2022 Barry Bowen Kellie Gant Dewey Baird Hal Pflueger Ken Rieke Bill Beermann Mike Mc. Hugh 2

Fire Dep’t Cons’t Committee • Committee History 1. 2. 3. 4. Jan 09 -Formed

Fire Dep’t Cons’t Committee • Committee History 1. 2. 3. 4. Jan 09 -Formed Feb 09 -Ken Rieke – Eliminated self March 09 -Dewey Baird/Project Mgr March 09 -TC Planning Dep’t Meeting - rezone/use permit form - lot line adjust/merger form 5. March 09 -Hayfork VFD visit/lessons learned 1/10/2022 3

Fire Dep’t Cons’t Committee • Hayfork VFD Lessons Learned: 1. 2006 -Hayfork VFD awarded

Fire Dep’t Cons’t Committee • Hayfork VFD Lessons Learned: 1. 2006 -Hayfork VFD awarded Trinity Co CDBG General Planning & Technical Assistance Grant to develop master plan for public safety facility 2. CDBG provided $32 K for Preliminary master plan & conceptual design development drawings for 11 K sf metal facility (6 fire vehicles, 1 ambulance, office, trng rm, kit, laundry, day rms, bd rms & bath rms) 3. $107 K buys HVFD’s construction drawings now being reviewed by TC Planning Dep’t 1/10/2022 4

Fire Dep’t Cons’t Committee • Trinity Co. Planning Dep’t Meeting 1. Process & proposed

Fire Dep’t Cons’t Committee • Trinity Co. Planning Dep’t Meeting 1. Process & proposed fees 2. Rezone – Commercial>Public Facility 3. Merge lots 1/10/2022 5

FEES Rezone Use Permit Enviro Review Fish & Game Enviro. Hlth. Merger Total 1/10/2022

FEES Rezone Use Permit Enviro Review Fish & Game Enviro. Hlth. Merger Total 1/10/2022 CURRENT $ FUTURE $ 790. 00 1900. 00 745. 00 1925. 00 1090. 00 1760. 00 2043. 00 219. 00 350. 00 5237. 00 8197. 00 Delta = $2960. 00 6

DEVELOPMENT PROCESS • • Rezone & Merge lots Obtain use permit Ongoing grants research

DEVELOPMENT PROCESS • • Rezone & Merge lots Obtain use permit Ongoing grants research & development Site work, i. e. , boring, testing Develop “Program Summary” > concept 30 – 50 – 95% Plans, $ dependant Construction, $ dependant 1/10/2022 7

Use Permit Application Process • • Application/fee submittal Media/letter announcements Public/agency comment period 30

Use Permit Application Process • • Application/fee submittal Media/letter announcements Public/agency comment period 30 -45 day Planning Dept review 30 day Planning Commission Hearing 30+ day Recommendation to Supervisors 30+ day Supervisor’s public hearing 30+ day Use Permit Process time 4 -6 months 1/10/2022 8

Lot Merger Application Process • Concurrent w/ Use Permit/Rezone • Generally 60 days •

Lot Merger Application Process • Concurrent w/ Use Permit/Rezone • Generally 60 days • *May require surveyors services 1/10/2022 9

Next Steps 1. Rezone & Merger App Submittals 2. Review Codes, i. e. ,

Next Steps 1. Rezone & Merger App Submittals 2. Review Codes, i. e. , H&S Sec 16000 -1600, Calif Bldg Reg for Architects, Title 24 3. Prepare Program Summary 4. Ongoing grant research/development 5. RFP development for PLANS 6. Review on the shelf fire house plans 7. Recruit an Admin Assistant 1/10/2022 10