Sustainable Water Infrastructure Project SWIP City of Santa
Sustainable Water Infrastructure Project (SWIP) City of Santa Monica Curtis Castle, P. E. Principal Civil Engineer
Project Location
Project Description Advanced Water Treatment Plant + 4. 5 MG Stormwater Tank SWIP will harvest both wastewater and stormwater for direct use (irrigation) and indirect potable recharge. The plant will produce 1 MGD (~1, 140 AFY). The stormwater capacity will be 4. 5 MG, meeting the EWMP / MS 4 requirements
Funding Details Total Project Cost: ~$82. 8 M Matching Funds: $69. 8 M (funding secured by City, includes SFR loan of $56 M) Funding Gap: $13 M Funding Request: $2 M Project is 30% designed, Kiewit is the DB
Benefits Reduce Water Demand Increase Water Supply Improve Water Quality Improve Flood Management
Project Schedule Start Date: Nov 26, 2018 End Date: April 2021 Project Schedule Project Concept Report May, 2016 Project Design Concept March, 2018 Mitigated Negative Declaration August, 2016 60% Design and GMP for Const Sept, 2019 Award Construction GMP Oct, 2019 Complete 100% Design Dec, 2019 Construction Completion April, 2021
Other Considerations SWIP both ensures compliance with MS 4 Permit requirements and increases the supply of drinking water. Santa Monica is committed to the Project and has invested a significant amount of time and resources to date.
- Slides: 7