Superconducting RF Operational Experience at FNAL Elvin Harms

  • Slides: 18
Download presentation
Superconducting RF Operational Experience at FNAL Elvin Harms Proton Accelerators for Science & Innovation

Superconducting RF Operational Experience at FNAL Elvin Harms Proton Accelerators for Science & Innovation Workshop 12 -14 January 2012

Outline Introduction • SRF Facilities at Fermilab • Operational Experience • § § §

Outline Introduction • SRF Facilities at Fermilab • Operational Experience • § § § Cavities Cryomodules Beam facilities Impressions • Summary • 2 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

Introduction • Fermilab has a growing capability in operating SRF facilities § § 3

Introduction • Fermilab has a growing capability in operating SRF facilities § § 3 Cavity R&D Test facilities Beam-based facilities Cavity processing & cryomodule assembly Expertise with sub-systems necessary for reliably operating SRF facilities Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

SRF Facilities at Fermilab • Fermilab has been developing the infrastructure and expertise to

SRF Facilities at Fermilab • Fermilab has been developing the infrastructure and expertise to be a key player in Superconducting RF technology applications • NML facility • MDB: Horizontal Test Stand, HINS, & MP-9 • Industrial area: Vertical Test Stand, • A 0: Photoinjector & Third Harmonic Effort CMTF/NML MDB & MP-9 Industrial area A 0 4 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

A 0 - Birthplace of SRF Activities • Photoinjector § § § • North

A 0 - Birthplace of SRF Activities • Photoinjector § § § • North cave § § § 5 Gun ‘Capture Cavity 1’ superconducting 9 -cell cavity In operation from 1992 until October 2011 Routine, almost ‘turn key’ operation User line for novel beam dynamics studies Deflecting mode cavity R&D for CKM, ILC, etc. Test bed for 3. 9 GHz effort Single cell R&D Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

IB 1 - Vertical Test Stand • • • Sized for testing 1. 3

IB 1 - Vertical Test Stand • • • Sized for testing 1. 3 GHz 9 -cell cavities+ 206 tests to date, 70+ tests per year maximum throughput Expansion of two more test stands in progress § § • 6 VTS-2: on-line in September VTS-3: 2013 Maximum throughput ~250 tests/year Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

MDB • Horizontal Test Stand § § § Single dressed 1. 3 GHz and

MDB • Horizontal Test Stand § § § Single dressed 1. 3 GHz and 3. 9 GHz cavities In operation since August 2007 16 cavities tested - several more than once 300 k. W RF system @ 1. 3 GHz 80 k. W RF system @ 3. 9 GHz Cryogenics • • • § § § • 7 3 parallel Tevatron refrigerators 625 Watts each @ 4. 5 K 1. 8 K operation w/ pump @ 10 g/s LLRF, interlock system, Vacuum, etc. ~ 1 cavity test/month All ACC 39 cavities S-1 Global CM-2 HINS/Single Spoke Resonator R&D Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

NML/CM-1/ASTA • • • First ILC-style cryomodule in the U. S. brought into operation

NML/CM-1/ASTA • • • First ILC-style cryomodule in the U. S. brought into operation here Future e- beam facility: Advanced Superconducting Test Accelerator (ASTA) 2 SRF systems in operation § § • • Cryo system commissioned in 2009 CM-1 cooldown: November 2010 RF system for CM-1: early 2011 Complete Cryomodule powered: June 2011 In (routine) operation since Run ends in February CM-2 to follow § 8 CC-2 CM-1 first Fermilab-built ILC (TTF) style cryomodule Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

CM-1 Experience Fermilab mean Gradient = 23. 7 MV/m Average gradient degradation is 19%

CM-1 Experience Fermilab mean Gradient = 23. 7 MV/m Average gradient degradation is 19% 9 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

NML/ASTA electron gun booster cavities CC-1 flat beam transform 3 rd harmonic cavity deflecting

NML/ASTA electron gun booster cavities CC-1 flat beam transform 3 rd harmonic cavity deflecting mode cavity chicane beam dump 1 st cryomodule spectrometer magnet test beamlines beam dump 40 -Me. V Injector - begin beam operation in 2012 • 1. 5 cell, 1. 3 GHz electron gun with Cs 2 Te photocathode; identical to DESY/PITZ design • Two 9 -cell 1. 3 GHz superconducting booster cavities (one currently installed, one from A 0 PI) • Superconducting 3. 9 GHz cavity (eventually) for bunch linearization • Three skew quadrupoles for flat beam transformation • Chicane for bunch compression (R 56 = 0. 198) • 3. 9 GHz, normal conducting deflecting mode cavity for longitudinal beam diagnostics (from A 0 PI) • Vertical spectrometer dipole deflects beam 22. 5° to dumps for beam energy measurement • Test beamlines will be configured to suit experiments; example shown here is for emittance exchange • ~40 Me. V beam energy 10 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

NML/ASTA 11 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

NML/ASTA 11 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

CMTF Cleanroom Cold Boxes RF Systems Test Stands Compressor Building Test Beams Gun Injector/

CMTF Cleanroom Cold Boxes RF Systems Test Stands Compressor Building Test Beams Gun Injector/ 40 Me. V line CM-1+ Beam Absorbers Tunnel Extension Original NML Building 12 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

CMTF 13 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

CMTF 13 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

SRF Operational Experience • Demonstrated capabilities § § § § • Subtle(? ) transition

SRF Operational Experience • Demonstrated capabilities § § § § • Subtle(? ) transition from student -> teacher § § § § 14 Cryogenics Cavity processing High power RF systems Low Level RF (Adaptive) Lorentz Force Detuning Compensation Controls Operations CM-1 was a ‘kit’ CM-2 is Fermilab-built India & China collaborations S-1 Global participation Industrial engagement Requests to share expertise But - still lots to learn… Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

CM-2 - Vertical Results = CM 2 ILC S 0 spec 15 Harms -

CM-2 - Vertical Results = CM 2 ILC S 0 spec 15 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

Operational Experience Impressions • Subgroups have successfully operated separate facilities for some time §

Operational Experience Impressions • Subgroups have successfully operated separate facilities for some time § § • • Operation of ASTA is the culmination - for now Fruitful, collaboration with other institutions to develop SRF capabilities § • Cornell, Argonne, JLab, DESY, TTC, + others including UK groups (e. g. 3. 9 GHz crab cavity) New opportunities emerging/merging § § 16 Test stands Photoinjector Clean rooms Cryogenics Decommissioning of Photoinjector area ASTA IARC etc. Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

Operational Experience Impressions-2 • Only limited involvement in operating Fermilab’s facilities § § •

Operational Experience Impressions-2 • Only limited involvement in operating Fermilab’s facilities § § • • Similar experience at HTS Photoinjector had a fairly regular stream of students and involvement from other institutions § • Operation of ASTA should expand the possibilities Protons (hadron) vs. Electrons (leptons): § 17 2 visitors for CM-1 operation (both from DESY and invited) Indian collaborators Immaterial in large measure - SRF is SRF Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012

Summary • • Fermilab has made significant strides in assembling and putting SRF infrastructure

Summary • • Fermilab has made significant strides in assembling and putting SRF infrastructure into operation CM-1 operation now and CM-2 operation (with beam) later this year is significant Much to share, yet much to learn: Collaboration Welcome opportunities to expand the use of what has been developed Thank you for your attention! 18 Harms - Science & Innovation Workshop/RF & Magnets 12 -14 January 2012