Substation L 1 MCC L 1 Update 2
Substation L 1/ MCC L 1 Update #2 July 27, 2012
Status of Procurement § Substation § All approval drawings submitted § Testing is expected to take place August 8 -10 § Delivery will occur soon after testing is completed § MCC § All approval drawings submitted § Expected arrival date of Mid to Late August (55 -75 working days after approval drawings reach factory floor) § Drawings approved on 5/30/2012 § Cable § All cable delivered § Stored in LINAC § 350 MCM will be stored at warehouse until installation is closer § Panelboard § Delivered § Needs to be assembled
Status of Procurement (Cont. ) § Safety Switches § Delivered § Stored in LINAC § Cable Supports § Delivered § Stored in LINAC § Support Structures § Will be built out of unistrut § Assembly has not yet begun § Support frames will be built in house § Junction Box § Drawing is complete § Fabrication companies have yet to respond § Since only one needs to be ordered it is unlikely that a company will construct this enclosure § Will be submitting the drawing to the machine shop soon
Project Schedule § Currently at a stand still § Complexity § Safety issues § Install should still be okay for originally planned September install § General Cleanup 2 -3 weeks prior to shutdown of substation § Temporary electrical power will be setup the weekend prior § It could take riggers several days to remove and install substations § Small clearances § Large weights § May be several more days if given okay to shore the floor
Issues § Substantial Weight Increase § 10, 500 lbs. vs. 17, 700 lbs. § Gallery floor has a very low load limit (350 lbs. /sq. ft. ) § This could effect everyday operations § Fork lifts, Tour groups, Removing equipment from downstairs § Could be wrong § Stevenson has no suitable indoor crane § Ceiling height is too low for carrydeck crane § 55, 000 lbs. § Shoring the floor may not be a possibility § Much of the transformer will need to be dismantled § Secondary bus bars, frame, sheet metal § Increases electrician time
Suggestions § FESS has been notified that it needs to begin looking into ways to fix this issue § Cut a hole in the ceiling § Has been done at other sites around the lab § Install outside § Requires Federal to make outdoor gear § Engineering Expense § Siemens subcontract issue § Expensive cable runs § Rigging job would be simplified § Aesthetics committee
Temporary Power Plan § “Siphon” power from panel DHP-L 2 -2 Circuit #1 § Cable will be run on temporary supports § 4 conductor 350 mcm cable is heavy (~7 lbs. /ft. ) and will need an open area to lay § Some cable will be put on the floor but will be covered by a cable bridge § Setup 2 temporary panel board(s) § Run cable to individual loads § DHP panels, MCC loads § DHP panels will be locked out and tagged out § Group lockbox § MCC loads will have configuration control locks § We will check current prior to using any MCC loads to ensure they will not trip off during operation § Power will be provided 24 hours a day
Installation Costs § 1 Crew of Riggers (4 -6 men) § Unknown Cost § Will remain unknown until a plan is put in place by FESS § 2 Week of Electricians § $100/manhour x 2 electricians x 80 hours = $16, 000 § Cable § 2/0 - $3, 500 § 2 – $3, 700 § House Power § $4, 200 for panelboard § $2, 000 for assembly § Miscellaneous Stock purchases § $2, 100 Total Cost : $31, 500 -> excluding rigging Previous Estimate: $23, 000 -> excluding rigging Increase can be attributed to increased electrician time and panelboard cost
Commissioning § Visual Inspection § Hi-Pot § Disconnect panel boards from temporary power § Reconnect panel boards § DHP-L 1 -1 will be turned on first § Fire alarms § Lighting § Etc. § DHP-L 1 -2 § DHP-L 1 -3
What Will Become of the Removed Equipment? § Transformer will be kept as a spare § Currently have 1 spare for 8 transformers (5 – high rise, 3 – LINAC) § Transformer will be examined to make sure it is in good working order § Will be stored in Booster parking lot § Will be placed on a truck the same day it is removed to avoid excess rigger fees § Breakers § Will be rebuilt and tested § Used as spares § Primary Switch § Will be rebuilt and tested § Used as a spare
Future § Create Site Wide Monitoring Network Intranet LINAC Profibus Section 1 (This Install)PIP Project ? ? 2 LINAC Profibus Section (MCC L 2) $65 k PIP Project Booster Profibus West Booster Profibus (Specifications Written) PIP Project Booster Profibus East Not PIP (Specifications Written) Cross Gallery Profibus Substation CG-1 Note: CG-1 has been moved (Specification Written) $200 kand will from PIP schedule, now be handled by headquarters
Booster Y-BE 2 Update § What we did § § § Current measurements Voltage measurements Thermal imaging scans Listened Disconnected all loads Y-BE 2 § What we will do § Move Spare to F 0 § All tests that are performed on new transformers will be performed on spare § Oil samples § Order new substation Y-BW 2
- Slides: 12