Steel Erection 29 CFR 1926 Subpart R Overview
Steel Erection 29 CFR 1926, Subpart R
Overview of the rule v Applies v Does to not apply to v Examples activities of steel erection 1 a
Preplanning operations and construction sequence v Approval requirements to begin steel erection • Written notification • Anchor bolt repair, replacement, modification 2 a
Preplanning operations and construction sequence v Commencing operations • Notification of concrete/mortar strength 2 b
Site layout requirements v Adequate access roads v Adequate pedestrian and vehicle control v Properly graded and drained storage areas 2 c
Overhead hoisting operations v Working v Routes under suspended loads for suspended loads 2 d
Site-specific erection plan 2 e
Hoisting and rigging of steel members & materials v Cranes and derricks regulations in § 1926. 550 3 a
Hoisting and rigging of steel members & materials v Hoisting and rigging operations • Competent person responsibilities • Pre-shift visual inspection and reporting deficiencies • Operator and rigger responsibilities 3 b
Working under loads v Preplanning routes for suspended loads v Working under loads 3 c
Multiple lift requirements v Criteria for multiple lifts v Rigging of the multiple lift assembly 3 d
Structural steel assembly v Structural stability v Multi-story v Slips, structures trips, and falls 4 a
Plumbing-up equipment v Competent v Installing person equipment 4 b
Installing metal decking v Common v Holes hazards and openings v Laying and securing metal decking 4 c
Column stability and the use of anchor rods v General requirements for erection stability v Repairing, replacing or field modification of anchor rods 5 a
Connecting beams and columns v Releasing v Securing v Double the load diagonal bracing connections v Column splicing v Erecting perimeter columns 6 a
Erection and attachment of open web steel joists v Danger of the process v General requirements v Attaching girders steel joists and v Landing and placing loads on steel joists 7 a
Systems-engineered metal buildings v Application v Anchoring v Rigid requirements of columns frames v Construction loads 8 a
Systems-engineered metal buildings v Girt and eave strut-to-frame connections v Anchorage systems points for fall arrest v Purlins as walking/working surfaces v Placing loads 8 b
Falling object protection v Provides employees with protection v Requirements items aloft for securing loose v Protection from falling objects 9 a
Fall protection threshold heights v General requirements for fall protection v Installing perimeter safety cables v Requirements connectors for 10 a
Fall protection threshold heights v Controlled decking zones v Guardrail, personal fall arrest, and positioning device systems v Custody of fall protection systems and equipment 10 b
Steel erection rule training requirements v Employees hazards exposed to fall v Training for multiple lift rigging v Training for connectors v Controlled decking zones training requirements 11 a
- Slides: 23