Status of LS 1 collimator maintenance O Aberle
Status of LS 1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro
Main activities during the LS 1 � Collimator exchange (TCTP vs TCT, IR 1, 2, 5 and 8) � Collimator installation (TCLP, TCL 6 in IR 1 and 5) � New TCAPD (IR 3) � New installation commissioning � Collimator standard maintenance � Special maintenance � TIM / Robot intervention/observations � Alignment � Outlook 2 O. Aberle – CWC March 03 rd 2014
Collimator exchange New production of 16 + 4 TCTP � New production of 2 + 1 TCSP � New production of 2 + 1 TCAPD � Preparation of 2 spare TCLP � Preparation of 1 spare TCP � Layout modification in Pt. 8, removal of 2 TCTVB, shifting TCLIA � Pt. 1: Replacement of 4 TCT + by 4 TCTP + installation of 2 TCLP and 2 TCT � Pt. 2: Replacement of 2 TCT + 2 TCLP by 4 TCTP � Pt. 3: Installation of 2 new TCAPD � Pt. 5: Replacement of 4 TCT + by 4 TCTP + installation of 2 TCLP and 2 TCT � Pt. 6: Replacement of 2 TCS by 2 TCSP � Pt. 7: Remove first TCP on the right side and the three TCP on the left side during ventilation door installation (to prevent damage) and exchange the skewed TCP of IR 7 L (water cooling) � Pt. 8: Replacement of 2 TCT + 2 TCTVB by 4 TCTP � 3 O. Aberle – CWC March 03 rd 2014
New installation commissioning � Check each collimator mechanics and electronics. � Full check of controll system � Slot and infrastructure (support, cabling, cooling water) � Installation and alignment � Vacuum connection and bake-out � Collimator standard maintenance 4 O. Aberle – CWC March 03 rd 2014
Collimator standard maintenance � Check each collimator mechanics and electronics. � Cycle from out to in, to anti-collision and back to out. � Check 5 th axis for clearance � Check water cooling flow � Check temperature sensors � Check switches, LVDT’s, resolvers, motors and drivers � Map sound profile for each collimator � Check rails � Check roller screws 5 O. Aberle – CWC March 03 rd 2014
Collimator roller screw replacement (2011 -12) Dust and debris in the end cap and the housing Some dry screws regreased Up to date 3 rollers screws have been exchanged. -No linear bearing -2 LVDT‘s -1 motor -2 switches 6 O. Aberle – CWC March 03 rd 2014
TIM and Robot intervention � Sound inspection of the collimators done with the TIM in S 34 (23/24 April 2012). � Visual and acoustic inspections with camera can be useful in the future (TIM automatically, Telemax robot more flexible). � Vacuum disconnection testing with the Telemax robot ongoing. � Use of robot for visual inspections/leak tests (He spray). � Profit from the long shutdown to verify the integration and do some hardware tests to confirm the procedures. 7 O. Aberle – CWC March 03 rd 2014
Alignment � Survey is working in the whole machine. � During smoothing, magnets will be aligned and collimators checked (and adjusted if needed). � IR 3 and IR 7 are equipped with additional targets for remote verification with the stretched wire. � New collimators (TCTP, TCSP, TCLP, TCT (TCL 6) and TCAPD) will be aligned. � The TCP’s removed during the installation of the ventilation doors + the skewed TCP in IR 7 L to be checked (high radiation levels, how much deviation can be tolerated? ). 8 O. Aberle – CWC March 03 rd 2014
Schedule – linked to LS 1 LHC planning Number of systems Network Installation 230 V power supply cabling 230 V powered R 2 E cabling works US 15 4 + 1 for TCL-6 OK OK OK UA 23 6 + TDI OK OK UA 27 2 OK UJ 33 7 - USC 55 4 + 1 for TCL-6 US 65 Collimator added Collimator not or replaced during modified during LS 1 Seq Controls Commissioning starting date Controls Commissioning end date 30 June 3 10. Mrz 14. Mrz 1 L TCTP 14/04/2014 1 R TCTP 5/03/2014 TCL-6 ? - 4 17. Mrz 21. Mrz TCTP 12/05/2014 TDI 28/04/2014 - 11 August 5 24. Mrz 28. Mrz TCTP 12/05/2014 11 August 15 September 2 25. Feb 07. Mrz TCAPD 14/02/2014 22 September 28 July 10 12. Mai 16. Mai 5 L TCTP 14/07/2014 5 R TCTP 9/06/2014 TCL-6 ? 0 28 July 5 May 6 31. Mrz 02. Apr 6 L TCSP 13/03/2014 6 R TCSP 18/02/2014 4 (TCP) 34 5 May 11 August 9 22. Apr 09. Mai 7 R TCP 18/02/2014 7 L TCP 10/03/2014 No 3 1 11 August - 8 14. Apr 18. Apr TCTP 9/06/2014 OK No 3 (including TDI) 6 - 2 June 7 02. Apr 11. Apr TCTP 14/04/2014 OK YES 0 1 - - 1 24. Feb Control System Installation Systems ready for commissioning OK OK YES 6 + 2 TCL 6 Planned 28/02/2014 - OK No 3 (including TDI) OK Planned 28/02/2014 - OK No 2 2 OK OK - Ok YES 0 18 No No. End of March Cables available around 20 th March. TCL-6 cables : L 15/04 , R 30/05 No No 6 + 2 TCL 6 2 1 - OK OK - OK System to switch ON 2 TZ 76 21 OK In progress OK No UA 83 2 OK In progress Planned 3/03/2014 - TCTVB Cabling in progress OK UA 87 5 + TDI OK In progress Planned 3/03/2014 - TCTVB Cabling. Finished: To check BA 7 1 OK OK OK - Other works In progress. Cables Planned end of March reconnection in TZ 76: date to confirm Sector Cooldown L Sector Cooldown R 2 2 June 7 30 June Powering Tests New collimators Installation date New collimators New Collimators Calibration Commissioning/calibration Commissioning/Calibration end starting date - � Frame given by LHC planning, Julie is coordinating with Vacuum, transport, powering etc… � Cabling and control system availability � Installation readiness of new collimators 9 O. Aberle – CWC March 03 rd 2014 Calibration end date
Schedule – details by Jerome Collimator added Collimator not or replaced during modified during LS 1 Seq Controls Commissioning starting date Controls Commissioning end date 2 3 10. Mrz 14. Mrz 1 L TCTP 14/04/2014 1 R TCTP 5/03/2014 TCL-6 ? 7 4 17. Mrz 21. Mrz TCTP 12/05/2014 TDI 28/04/2014 2 2 5 24. Mrz 28. Mrz TCTP 12/05/2014 0 18 2 25. Feb 07. Mrz TCAPD 14/02/2014 No 6 + 2 TCL 6 2 10 12. Mai 16. Mai 5 L TCTP 14/07/2014 5 R TCTP 9/06/2014 TCL-6 ? OK System to switch ON 2 0 6 31. Mrz 02. Apr 6 L TCSP 13/03/2014 6 R TCSP 18/02/2014 21 OK No 4 (TCP) 34 9 22. Apr 09. Mai 7 R TCP 18/02/2014 7 L TCP 10/03/2014 UA 83 2 OK No 3 1 8 14. Apr 18. Apr TCTP 9/06/2014 UA 87 5 + TDI OK No 3 (including TDI) 6 7 02. Apr 11. Apr TCTP 14/04/2014 BA 7 1 OK YES 0 1 1 24. Feb Number of systems Control System Installation Systems ready for commissioning US 15 4 + 1 for TCL-6 OK YES 6 + 2 TCL 6 UA 23 6 + TDI OK No 3 (including TDI) UA 27 2 OK No UJ 33 7 Ok YES USC 55 4 + 1 for TCL-6 No US 65 1 TZ 76 10 O. Aberle – CWC New collimators Installation date - March 03 rd 2014
Schedule – linked to LS 1 LHC planning � Work has just started � First ring collimators put back into operational status TCLA. 7 L 3. B 2, TCP. 6 L 3. B 1, TCSG. 5 L 3. B 1 � A lot of work in parallel with surface preparation and installation activities. � J. Finelle from the vacuum team will take pictures when ever a collimator will be disconnected from the vacuum system. � All collimators will be checked for alignment errors, re -alignement has already started in several points. 11 O. Aberle – CWC March 03 rd 2014
Outlook � Improve the sound and image quality for the TIM, very powerful tool for the future. � Investigate on the capabilities of the Telemax or similar robots for inspections and interventions. � Reference sound recording of all collimators? � Improve the accessibility to the screw (cap) (Phase 2!) � A regular check during long breaks and shut-downs with re-lubrication of the screw. � Check every slot for 5 th axis motion limitations. � Sven De Man is the new reference person for the LHC tunnel situation concerning collimators 12 O. Aberle – CWC March 03 rd 2014