SSD Installation Plan • ID – Name – Duration – Start date – Finish date • 79 – Install SSD – 50, 5 days – 7/1/03 – 9/12/03 • xx – SSD shipping – 1 week – 8/11/03 – 8/18/03 – Main shipping, earlier shipments will include cables and 3 -ladder sectors. • • • 81 – Install SSD on cone – 12 days – 8/19/03 – 8/31/03 82 – Install/Test cabling on cone – 12 days – 9/1/03 – 9/11/03 90 – Rig Cone to Rails – 0, 5 days – 9/12/03 – 9/15/03 91 – Survey SSD to SVT – 3 days – 9/15/03 – 9/18/03 91 bis – Install SSD shield – 2 days – 9/18/03 – 9/20/03 – Can be done in parallel with the task 92 and 93 (Test Utility Connections and Clean TPC IFC)
SSD Installation Plan • 83 – Install SSD power cables – 1 week – 8/19/03 – 9/20/03 – Can be done on the West side in parallel with the BEMC installation. Need a lifting engine (don’t remember the name) to route cables all around the TPC wheels • 84 – Install RDO boxes – 1 week – 9/13/03 – 9/20/03 – All rdo board cables already installed • 100 – Connect East rdo and LV cables – 3 days – 10/3/03 – 10/8/03 • 107 – Connect West rdo and LV cables – 0, 5 day 10/9/03 – 10/10/03 • xx – SSD commissioning – 2 weeks – 10/11/03 – 10/25/03 – Need the STAR DAQ