SPS LS 2 – BA 5 • • Enlarged quadrupole Ion pump consolidation (LSS & arc+) Wire scanner installations LSS 5 reconfiguration • • Component purchasing TIDVG design review Layout design – fixed Vacuum chamber production 26/11/2018 6
SPS LS 2 – BA 6 • • • TPSG 6 installation MST exchange Ion pump consolidation (arc-) Impedance optimisation ZS removal 26/11/2018 7
SPS LS 2 – Planning Current planning has smoothed Q 1 2019 peak but remains Q 1/2 2020 peak Man power limited to be updated from last meeting 26/11/2018 8
SPS LS 2 – Ti 2/Ti 8 • New layout • • • Layout design – fixed Component procurement 6 x new TCDIL Sectorisation of TED General maintenance • • • Non-conformities – planned Sector valve pressure switch Components purchased 26/11/2018 9