Smith Homes Redevelopment GREENSBORO HOUSING AUTHORITY RAD Collaborative
Smith Homes Redevelopment GREENSBORO HOUSING AUTHORITY RAD Collaborative 1
Background ØIn December 2013, GHA received approval HUD for a Portfolio Award under the Rental Assistance Demonstration (RAD) for 20 properties (2, 213 units) ØIn April 2019, GHA received the multi-phase commitment to enter into a housing assistance payment contract (CHAP) award for Smith Homes, which consist of six phases totaling 430 units ØTo date, GHA assembled a team of master planners (Lord Aeck Sargent), civil engineer (Timmons Group) and architect (Cline Architects) and commenced the planning and design efforts ØCurrently, submitted Financing Plan for initial phase (consisting of TOA units combined with another RAD property Ø 1 st on-site development with LIHTC financing will commence in 2020 2
Neighborhood Area Map 3
PROJECT OVERVIEW (Aerial) 4
Existing Building Layout 5
Planning Process 6
Community Engagement 7
Existing Site Assessment Map 8
Master Development Plan 9
The Phasing Plan ØOnsite / Off-site Composition: q 350 -380 units replaced onsite q 50 – 80 units transfer of assistance ØProposed Phasing: q. Initial (1 st) Phase – 30 units transfer of assistance (2019) q 2 nd Phase – 130 units LIHTC Development (2020) q 3 rd Phase – 23 units LIHTC Development (2021)* q 4 th Phase – 80 units LIHTC Development (2021) q 5 th Phase – 80 units LIHTC Development (2022) q 6 th Phase – 87 units LIHTC Development (2024)* *These phases may include RAD / Section 18 disposition strategy or Transfer of Assistance scenario 10
11
Infrastructure Costs (Estimated) ØInfrastructure - Site Costs: $18, 250, 000 (Estimates): Demolition ; $ 4 300 000 Site Work; $ 6 000 Infrastructure; $ 7 950 000 12
THE END Questions and Answers 13
- Slides: 13