SLAC National Accelerator Laboratory Conventional Facilities Status LCLS
SLAC National Accelerator Laboratory Conventional Facilities Status • LCLS Conventional Facilities Introduction – Key Elements – Staff – Schedule • Construction Status • Remaining Issues December 2, 2008 Accelerator Readiness Review 1 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory CD-4 (7/31/2010) First Light in FEH Hutch BO X-Rays in NEH First Light in FEE Install Undulators FEE/NEH Install now LTU/Und Install PEP-II run ends LCLS Installation and Commissioning Time-Line PPS J F MAM J J A S ON D J F M AM J J A S OND J F MAM J J Down? 2008 2009 2010 Linac/BC 2 Commissioning December 2, 2008 Accelerator Readiness Review LTU/Und NEH Ops & Commissioning Re-establish FEL/FEE e- to SL 2 Commissioning 2 Nov. 3, 2008 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Substantial Completion Dates Central Utility Plant NOV 08 Undulator Hall NOV 08 Beam Transfer NOV 08 Near Experimental Hall NOV 08 Beam Dump NOV 08 Front End Enclosure NOV 08 Xray/Diagnostics NOV 08 Far Experimental Hall NOV 08 December 2, 2008 Accelerator Readiness Review 3 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory December 2, 2008 Accelerator Readiness Review 4 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory December 2, 2008 Accelerator Readiness Review 5 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Equipment Warranties Equipment Testing Reports Mark up Drawings and Specifications Subcontractor Financial Records Final Acceptance Records December 2, 2008 Accelerator Readiness Review 6 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory December 2, 2008 Accelerator Readiness Review 7 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory TCCo —> LCLS CF Install. compl. Dwgs of Record Commiss. Test reports Final Punch List Final accepta nce Building/Housing shop dwgs n/a 15 -Nov-08 30 -Nov-08 Saenz AC Pwr √ shop dwgs √ 15 -Nov-08 30 -Nov-08 Sevilla Ch. W. √ shop dwgs √ 15 -Nov-08 30 -Nov-08 Baclit/Sevilla Hot W. √ shop dwgs √ 15 -Nov-08 30 -Nov-08 Baclit/Sevilla LCW √ shop dwgs √ 15 -Nov-08 30 -Nov-08 Baclit/Sevilla HVAC √ shop dwgs √ 15 -Nov-08 30 -Nov-08 Saenz C. Air √ shop dwgs √ 15 -Nov-08 30 -Nov-08 Sevilla √ shop dwgs 31 -Oct-08 15 -Nov-08 30 -Nov-08 Saenz Status e-beam System (thru e–DUMP) Fire System s CF Recip. Sump 30 -Nov shop dwgs √ 15 -Nov-08 30 -Nov-08 Baclit/Sevilla Radio n/a n/a n/a Phones √ shop dwgs n/a 15 -Nov-08 30 -Nov-08 Saenz Magnets n/a n/a n/a Vacuum n/a n/a n/a Mag. Power spl n/a n/a n/a Controls n/a n/a n/a December 2, 2008 Accelerator Readiness Review 8 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Beam Transport Hall December 2, 2008 Accelerator Readiness Review 9 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Undulator Hall December 2, 2008 Accelerator Readiness Review 10 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Electron Beam Dump Area December 2, 2008 Accelerator Readiness Review 11 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory December 2, 2008 Accelerator Readiness Review 12 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Access Tunnel December 2, 2008 Accelerator Readiness Review 13 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory 20 ITEMS REMAINING December 2, 2008 Accelerator Readiness Review 14 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory CF Construction Organization Project Director John Galayda Deputy Proj. Director Mark Reichanadter Project Controls and Support Office Exec. CF Committee R. Claus, J. Jobe B. Miller M. Reichanadter SLAC Services Support Associate Project Director – Civil Construction Jess Albino Change Processing Jim Dee John Azevedo Turner Bill Jangraw Project Executive Cost / Schedule Anita Malahowski CF System Manager David Saenz Administrative Support Lee Anne De Wan Concepcion Zelaya Engineering Group Leader Javier Sevilla Site Manager Jacobs Facilities, Inc Dave Mc. Donough SLAC ES&H Subject Matter Experts (SME) University Technical Rep – Group Leader Jesse Saldivar CM/GC – Turner Mike Owens – Sr. PM Matt Zybura -APM JE Design PM Cypress JE Walnut Creek Structural Ken Yang Electrical Lori Shewchuk UTR – CM Dumitru Ciorbea General Superintendent Nick Tyler Turner Procurement – Pre-purchased Equipment JE Portland JE Boston Mechanical Engineer Ray Baclit Electrical Engineer Khalid Ahmed UTR – Structural Ken Yang UTR – CM Richard Maggi C. M. Tunnels Eric Alward - HMM Turner Project Office Rutherford /Chekene Gyimah Kasali UTR – Mechanical Javier Sevilla Sub Contractors Site Safety Rep Andrew Leone December 2, 2008 Accelerator Readiness Review 15 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory Summary • Substantial Completion has been achieved. • Punch list items are currently being addressed. • Installation tasks were successfully supported with Beneficial Occupancy and logistics under CF direction. • All systems accepted and ready for transfer to installation or laboratory service groups. • Plans are in place for the beam commissioning program. December 2, 2008 Accelerator Readiness Review 16 Jess Albino albino@SLAC. Stanford. edu
SLAC National Accelerator Laboratory End of presentation December 2, 2008 Accelerator Readiness Review 17 Jess Albino albino@SLAC. Stanford. edu