Simple Change Process under NEC 3 End Instruct

  • Slides: 3
Download presentation
Simple Change Process under NEC 3 End Instruct CE Contractor No Accept EWN Yes

Simple Change Process under NEC 3 End Instruct CE Contractor No Accept EWN Yes Raise a CE Yes Approve RFQ Raise RFQ No Client End No Website: www. big-dada. co. uk E-mail: info@big-dada. co. uk For a comprehensive review of your business, get in touch today To find out how Dada Enterprises can help you call us on +44 (0) 207 101 0695.

Steps in validating a Early Warning Notice (EWN) Form 18: Compensation Event Notification by

Steps in validating a Early Warning Notice (EWN) Form 18: Compensation Event Notification by the PM Reject/ End Approve (Form 18) Reject Client Start Is EWN valid? Risk Reduction Meeting Reject (Form 20) Is CE valid ? Contractor Reject PMI Approve (Form 5) (Form 19) Reject/ End FORMS USED 18 Compensation Event Notification by the Employer Reject 19 Compensation Event Notification by the Contractor Form 19: 20 Employer’s Reply to a Compensation Event Notification Compensation by the Contractor 21 Employer’s Reply to a Quotation for a Compensation Event Notification Event by the Contractor 22 Employer’s Assessment for a Compensation Event Website: www. big-dada. co. uk E-mail: info@big-dada. co. uk Accept and raise RFQ • If raised by Contractor: Form 20 • If raised by Client: Form 18 Contractor’s RFQ Client Response to RFQ (Form 21) PMI (Form 5) Client Start Raising a Compensation Event (CE) without an Early Warning For a comprehensive review of your business, get in touch today To find out how Dada Enterprises can help you call us on +44 (0) 207 101 0695. Contractor

Early Warning – For matters that might/could effect time, cost or quality Identification of

Early Warning – For matters that might/could effect time, cost or quality Identification of possible issue/event that could affect time/cost/quality EWN Raised (by either party) Risk Reduction Meeting Action to move EW forward EWN not yet resolved Resolution/conclusion of early warning matter Non-event, or no mitigation required Event or mitigation that will lead to notification of a CE (for a reason listed under clause 60. 1) Consideration of any resultant actual cost in terms of draw down from Contractors risk pot Risk Register revised by Project Manager - early warning closed Refer to CE process map for next step Website: www. big-dada. co. uk E-mail: info@big-dada. co. uk Mitigation without need for CE For a comprehensive review of your business, get in touch today To find out how Dada Enterprises can help you call us on +44 (0) 207 101 0695.