SERBIA HUTCHINSON R inenjering Hutchinson Ruma Project Details
SERBIA HUTCHINSON R inženjering
Hutchinson, Ruma Project Details Building Type Industrial building Building Size 9. 000 m² Project Dates January 2015 – December 2015 Saint-Gobain Products & Systems Partitions Ceilings Fire resistant systems
Hutchinson, Ruma Contractor Company Name R inženjering Main Representative Mr. Branislav Šaranović Company Size 6 Specialised in Drylining systems
Hutchinson, Ruma Building Owner Architect Contractor Saint. Gobain Project Manager Hutchinson Studio Structura R inženjering Mina Milinović Balać
Hutchinson, Ruma Hutchinson opened its first factory in Serbia in 2016. Production complex 'HUTCHINSON' is located in Serbia in Industrial Zone of municipalities Ruma. In total coverage of 9000 m² it is divided in tree sections: production section, administrative section and warehouse. Ruma is located over 60 km from the country’s capital Belgrade. The local authorities provided 7. 8 hectares of land for the new production facility. The value of investment in Ruma has been estimated at EUR 7, 3 m. Hutchinson is operated by a global workforce of more than 35, 200 employed at 96 facilities in 23 countries. Of these, over 21, 400 workers are employed at the French group’s 63 sites in Europe, according to figures from Hutchinson.
Hutchinson, Ruma
Hutchinson, Ruma - Key features of the project are specially designed working and production place - Simplicity for savings - Feel good, work well - Using technologies summer heat to manage - Healthy buliding => healthy air - Ecological awareness - Combining massive, steel
Hutchinson, Ruma A particulary demanding section of the project was during the drywall installation. It was challenging to achieve the desired level of sound insulation fulfilling at the same time the fire resistance requirements for up to 120 min of fire resistance for partition.
Hutchinson, Ruma Suspended ceilings are EI 90 fire resistant and based on Rigips metal studs CD/UD, Nonius hangers and 3 layers of fire resistant boards 15 mm thickness.
Hutchinson, Ruma
Hutchinson, Ruma Key challenges • Complete construction work carried out in less than 8 months • High walls in production area • Special fire protection demands
Hutchinson, Ruma Main Saint-Gobain products and systems used Fire protection / Rigips partitions and ceiling with RF boards – 90 and 120 minutes fire protection • Production halls and offices • http: //www. rigips. rs/index. php? id=spusteni-plafoni-otporni-na-pozar-ei-30 ---ei-90 -nezavisni-odmeduspratne-konstrukcije-41013 Sound insulation / Rigips partitions with Isover wool • Production halls and offices • http: //www. rigips. rs/index. php? id=zidovi-sa-metalnom-potkonstrukcijom-cwuw-75 -34005 Ecological Concept • All areas • http: //www. rigips. rs/index. php? id=usteda-energije_1440057251
Hutchinson, Ruma Key achievements • • • Good relationship and cooperation within the team Very good reference for industrial type of building Enabling superior technical support for architects and contractors with good recommendation for next projects Precise dinamyc of deliveries due to short construction time Well organized stocks on construction site for additional savings
SERBIA Photography Credits: Miroslav Ružić HUTCHINSON R inženjering – Studio Structura SGCP Marija Arsić