SEEGRID2 WP 3 progress report www seegrid eu

  • Slides: 88
Download presentation
SEE-GRID-2 WP 3 progress report www. see-grid. eu SEE-GRID-2 PSC 05 Meeting, Thessaloniki, Greece

SEE-GRID-2 WP 3 progress report www. see-grid. eu SEE-GRID-2 PSC 05 Meeting, Thessaloniki, Greece 11 -12 September 2007 Antun Balaz WP 3 Leader Institute of Physics, Belgrade antun@phy. bg. ac. yu The SEE-GRID-2 initiative is co-funded by the European Commission under the FP 6 Research Infrastructures contract no. 031775

Overview WP 3 WP 3 objectives and activities position in SEE-GRID-2 deliverables and milestones

Overview WP 3 WP 3 objectives and activities position in SEE-GRID-2 deliverables and milestones schedule activities reports country reports Action points and issues SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 2

WP 3 objectives & activities (1) Develop the next-generation SEE-GRID infrastructure § Next generation

WP 3 objectives & activities (1) Develop the next-generation SEE-GRID infrastructure § Next generation of EGEE middleware (g. Lite), the VOMS, the WMS, information services and file catalogue services will be assessed having in mind project and WP 3 objectives § SEE-GRID infrastructure deployment regarding the middleware services will follow and adapt its services according to the results of the assessment. Support in deployment and operations of the Resource Centres § Next generation monitoring services will be deployed so as to support the over-the-board infrastructure monitoring. § The current SEE-GRID helpdesk will be expanded in SEE-GRID-2, with the main goal of full EGEE interoperability. § Support the expansion and deal with the overall upgrade of the current infrastructure by proliferation of RCs in each SEE country increasing: q q the total available regional resources (CPUs, storage, etc. ) thus boosting the capacity and reliability of the provision of Grid services at regional level, and the diversity and distribution of participating teams per country thus strengthening cooperation and collaboration at national level. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 3

WP 3 objectives & activities (2) Network resource provision and assurance § WP 3

WP 3 objectives & activities (2) Network resource provision and assurance § WP 3 will also deal with network resource provision, in close cooperation with the SEEREN 2 project, thus ensuring stable connectivity for the RCs in the region. § Attention will be paid to Bandwidth-on-Demand requirements, to cater for bandwidth-intensive applications in case they need dedicated resources for particular experiments. CA and RA guidelines and deployment § Regional SEE-GRID catch-all Certification Authority (CA) will continue to operate providing certificates for countries without a CA. § Experienced CA team will provide support for per-country CA deployment and accreditation. The cycle to establish a National Grid CA will be in compliance with the procedures and accreditation process of the EU Grid Policy Management Authority (EUGrid. PMA). § Operations will be strengthened so as to support per-country CA operations SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 4

WP 3 objectives & activities (3) User portal deployment and operations § A user-friendly

WP 3 objectives & activities (3) User portal deployment and operations § A user-friendly multi-Grid access portal will be deployed, enabling universal and more flexible user access to the regional infrastructure. § The work on the SEE-GRID-2 portal should increase the userfriendliness of being able to select a grid and execute a workflow on the selected grid, so that interoperability of different grids is seamlessly and transparently solved at the application (workflow) level. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 5

WP 3 objectives & activities (4) A 3. 1 - Implementation of the advanced

WP 3 objectives & activities (4) A 3. 1 - Implementation of the advanced SEE-GRID infrastructure (UOB-IPB/IPP) § Deals with support for configuration, deployment and operations of the Resource Centres within the SEE-GRID pilot infrastructure, as well as transition of mature centres into EGEE. § Effort: 89 PMs § Subactivities: q q q A 3. 1. 1 - Expand the existing SEE-GRID topology by inclusion of new sites per SEE country A 3. 1. 2 - Deploy M/W components and OS in SEE Resource Centers A 3. 1. 3 - Test the site installations in local and Grid mode A 3. 1. 4 - Operate the SEE-GRID infrastructure A 3. 1. 5 - Monitor the infrastructure performance and assess its usage A 3. 1. 6 - Certify and Migrate SEE-GRID sites from Regional Pilot to Global production-level e. Infrastructures SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 6

WP 3 objectives & activities (5) A 3. 2 - Network Resource Provision and

WP 3 objectives & activities (5) A 3. 2 - Network Resource Provision and Bo. D requirements (IPP) § Support liaison actions to ensure adequate network provision, including the requirements for Bandwidth-on-demand, if and where necessary depending on the application. § Effort: 39 PMs A 3. 3 - Deploy and operate Grid CAs (GRNET) § Should provide CA and RA guidelines and help establish percountry CAs to cover the authentication issues § Effort: 73 PMs A 3. 4 - Provide a user portal (SZTAKI) § Supports the deployment of a user-friendly and multi-grid interoperable portal for convenient Grid access and usage. § Effort: 15 PMs SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 7

WP 3 position in SEE-GRID-2 (1) WP 1 Project Administrative and Technical Management WP

WP 3 position in SEE-GRID-2 (1) WP 1 Project Administrative and Technical Management WP 2 Strategies & Policies WP 3 Infrastructure & Operations A 4. 1: Select multidisciplinary applications A 3. 3: Deployment and Operational support for accredited Grid Certification Authorities A 2. 1: Study grid deployment solutions A 2. 2: Deliver sustainable roadmap for SEE NGIs A 3. 1: Implementation (deploy, test, operate, monitor, certify, migrate) of an advanced SEE Grid Infrastructure A 3. 4: Grid access Portal A 4. 2: Adopt applications for the SEE user communities A 4. 4: Assess application usage A 4. 3: Support deployed applications A 3. 2: Network resource provision WP 4 Users & Applications WP 5 Training, Dissemination and Communication SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 8

WP 3 position in SEE-GRID-2 (2) Results of WP 2 will be used as

WP 3 position in SEE-GRID-2 (2) Results of WP 2 will be used as inputs § D 2. 1 - Regional and National Organisational and Policy Schemes § D 2. 2 - Sustainable organizational and operational approach § D 2. 3(a, b) - Sustainability and Impact Analysis of SEE National Grid Initiatives Results of WP 3 used as input to WP 4 All partners participate in WP 3 Activities start in M 1, end in M 24 WP 3 planned budget is 672, 512. 00 €, or ~33. 6% of the SEE-GRID-2 budget WP 3 is planned to take 216 PMs, or ~34. 2% of all SEEGRID-2 PMs SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 9

WP 3 Deliverables & Milestones (1) D 3. 1 a - Infrastructure Deployment Plan,

WP 3 Deliverables & Milestones (1) D 3. 1 a - Infrastructure Deployment Plan, M 04 (CERN) § Describes the envisaged infrastructure deployment execution plan to be followed in the region. § Prepared and submitted on time D 3. 2 - CA and RA guidelines for new candidates, M 05 (GRNET/AUTH) § This deliverable describes the guidelines and best practices of the per-country CA and RA organization and policies. § Prepared and submitted on time D 3. 3 - Portal specifications and functionality, M 06 (SZTAKI) § This deliverable provides the characteristics and structure of the multi-grid user-oriented portal. § Prepared and submitted on time SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 10

WP 3 Deliverables & Milestones (2) D 3. 1 b - Infrastructure Deployment Plan,

WP 3 Deliverables & Milestones (2) D 3. 1 b - Infrastructure Deployment Plan, M 14 (CERN) § Final version of D 3. 1. § Prepared and submitted on time We are currently in M 17 Future: D 3. 4 - Infrastructure overview and assessment, M 23 (UOB-IPB) § This deliverable presents an overview and assessment of the progress in the regional infrastructure and operations in the life of the project SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 11

WP 3 Deliverables & Milestones (3) M 3. 1 - Infrastructure Deployment Plan Defined

WP 3 Deliverables & Milestones (3) M 3. 1 - Infrastructure Deployment Plan Defined § M 04, Status: OK M 3. 2 - CA and RA guidelines for new candidates defined § M 05, Status: OK M 3. 3 - Portal operational across the pilot Grid § M 12, Status: OK SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 12

WP 3 schedule M 01 - Start of WP 3 M 04 - Infrastructure

WP 3 schedule M 01 - Start of WP 3 M 04 - Infrastructure Deployment Plan (M 3. 1, D 3. 1 a) M 05 - CA and RA guidelines for new candidates (M 3. 2, D 3. 2) M 06 - Portal specifications and functionality (D 3. 3) M 12 - Portal operational across the pilot Grid (M 3. 3) M 14 - Final Infrastructure Deployment Plan (D 3. 1 b) M 17 – This is where we are currently M 23 - Infrastructure overview and assessment (D 3. 4) M 24 - End of WP 3 (and of the project) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 13

WP 3 activities overview A 3. 1: Implementation of the advanced SEE-GRID infrastructure (UOB-IPB/IPP)

WP 3 activities overview A 3. 1: Implementation of the advanced SEE-GRID infrastructure (UOB-IPB/IPP) A 3. 2: Network Resource Provision and Bo. D requirements (IPP) A 3. 3: Deploy and operate Grid CAs (GRNET) A 3. 4: Provide a user portal (SZTAKI) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 14

A 3. 1: Overview Infrastructure status § g. Lite deployment status § SEEGRID VO

A 3. 1: Overview Infrastructure status § g. Lite deployment status § SEEGRID VO metrics and accounting Operations § § SLA conformance monitoring per site Helpdesk tickets procedures and statistics analysis GOOD shifts MPI support on SEE-GRID sites Operational & monitoring tools deployment & integration § § § HGSM SAM (+ porting to My. SQL) Wiat. G R-GMA Pakiti SEE-GRID Wiki status WP 3 developments Infrastructure, Site and VO metrics SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 15

Infrastructure status (1) Concerning the middleware deployments, the current SEE-GRID infrastructure supports a set

Infrastructure status (1) Concerning the middleware deployments, the current SEE-GRID infrastructure supports a set of core services which provide user access to resources: § Catch-all Certification Authority for the region has been officially accredited by the EU Grid Policy Management Authority - EUGrid. PMA, and is currently operational thus enabling regional sites to obtain user and host certificates § Virtual Organisation Management Service (VOMS), server has been installed as an authorization system for the SEE-GRID Virtual Organisation (VO), which provides information on the user's relationship with the Virtual Organization, his/her groups, roles and capabilities § Workload management service (lcg-RB and glite-WMSLB) and Information Services (BDII) nodes (several instances) have been installed at partners’ sites and are operational § My. Proxy is operational, and supports certificate renewal § FTS deployed and used in production SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 16

Infrastructure status (2) SEE-GRID total and free CPUs in the last year SEE-GRID-2 PSC

Infrastructure status (2) SEE-GRID total and free CPUs in the last year SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 17

Infrastructure status (3) SEE-GRID infrastructure contains currently the following resources: § 30 sites in

Infrastructure status (3) SEE-GRID infrastructure contains currently the following resources: § 30 sites in SEE-GRID production § 6 sites in certification phase (2 AL + 1 HR + 2 RO + 1 MD) § CPUs: 1105 total, but unknown number available to SEEGRID VO; increase of approx. 400 CPUs compared to PSC 04 § Storage: 17. 6 TB (no increase) All sites on g. Lite-3, with 3 sites on g. Lite-3. 1 and the rest on g. Lite-3. 0 glite-CE final assessment by EGEE is that this service is not stable enough for production; we agree glite-WMSLB actively used Guides provided for deployment of g. Lite-3. 1 WNs on SL 4. 5 (32 -bit); in preparation guide for 64 -bit WNs SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 18

Infrastructure (4): VO membership steady growth start of project § ~90 members end of

Infrastructure (4): VO membership steady growth start of project § ~90 members end of 02/07 § ~110 members end of 08/07 § ~160 members Bonn Presentation

Infrastructure (5): VO members per country Bonn Presentation

Infrastructure (5): VO members per country Bonn Presentation

Operations (1) SLA conformance monitored per site; tools used: § § § HGSM SAM

Operations (1) SLA conformance monitored per site; tools used: § § § HGSM SAM GStat Wiat. G Helpdesk SLA conformance analysis: § SEEGRID 2 -WP 3 -RS-018 -SLA-Q 5 -2007 -08 -06. xls Helpdesk tickets procedures § GOOD shifts introduced, initial results positive § Tickets handling: response times need to be improved! § Problems with GOOD shifts – some partners not performing duty! Helpdesk statistics analysis: § SEEGRID 2 -WP 3 -RO-008 -PSC 05 -Helpdesk_Statistics-2007 -09 -10. xls § SEEGRID 2 -WP 3 -RS-020 -PSC 05 -Tickets_not_closed-a-2007 -09 -11. xls OPS role implemented in VOMS, documented, implemented & used SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 21

Operations (2) MPI support on SEE-GRID sites § Important for many applications § Current

Operations (2) MPI support on SEE-GRID sites § Important for many applications § Current support not sufficient § Seems there is a problem with setup on some sites – GOOD shifts are addressing this, but this is not sufficient Proposal: WG to be created which should define minimal standards for MPI support, and provide template scripts and JDL files for submission of MPI jobs WG can be composed of representatives from sites supporting MPI and having experience: § § Bulgaria Turkey Greece Serbia SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 22

Operational & monitoring tools deployment status § HGSM – Turkey § SAM (+ porting

Operational & monitoring tools deployment status § HGSM – Turkey § SAM (+ porting to My. SQL) – Bosnia and Herzegovina with CERN support § BBm. SAM (Bosnia and Herzegovina) § Wiat. G § R-GMA – Bulgaria § Pakiti SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 23

HGSM (1): Background HGSM is a central database that holds all crucial information about

HGSM (1): Background HGSM is a central database that holds all crucial information about a grid site It has an interactive interface for users to see and update the information available in the database It has exports to interface with other services to enable integration between HGSM and other services that make use of HGSM's information HGSM is constantly improved with new features and new exports to enhance its functionality, role and information exchange over grid services for administrative purposes

HGSM (2): Latest Development Period (Initiation and Planning) Started in May-2007 with appearance of

HGSM (2): Latest Development Period (Initiation and Planning) Started in May-2007 with appearance of requests for new functionality and enhancements due to inefficiency of HGSM in some areas in the GIM list. Since the requests was big and required some major changes in HGSM structure, an “Internals Document” is prepared and passed to people in the discussion in the end of May. During June, the requests are anaylzed and refined down so everybody was aware of the missing parts, possible solutions and impacts of the new functionality

HGSM (3): Latest Development Period (Finalizing and Taking Action) In the end of June

HGSM (3): Latest Development Period (Finalizing and Taking Action) In the end of June a detailed “Roadmap Document” -which covers the problems, solutions and a stepby-step action plan in every detail- is prepared and opened for discussion in the GIM list. The Document is revised and updated according to feedback taken by the list. Document yielded 4 revisions, three drafts and a final which is published on Jul 12, 2007. Active development started on Jul, 16 according to plan announced in the Document.

HGSM (4): The Improvements (and Progress So Far) Following improvements are qualified for this

HGSM (4): The Improvements (and Progress So Far) Following improvements are qualified for this development period: § Revision of visual interface fields. (100%) § Introduction universal exporting subsystem which can be used by humans and other computers. (80%) § Introduction of an importing subsystem which can import exported data for administrators. (0%, 10 Sep) § An automatic field filling tool for administrators. (0%, 24 Sep) § Functionality improvement on various pages of visual interface. (0%, 8 Nov) § Improving the handling of supported applications in HGSM and developing a MAUI configuration editing tool for reflecting changes to grid sites directly and automatically. (0%, 22 Nov) § Enabling HGSM to track site information history for statistical purposes. (0%, 3 Dec) Note: Dates indicate rough estimations of kick-off dates.

SAM/BBm. SAM Server Portal § BBm. SAM q q q Service availability and SLA

SAM/BBm. SAM Server Portal § BBm. SAM q q q Service availability and SLA calculations implemented MAINTENANCE status implemented in a better way Enhanced OVERVIEW (main) page of BBm. SAM – Showing uptime for last 24 h – Filters available for: country, tier, certified status, last test state § BBmobile. SAM q Now also showing uptime percentage for last 24 h § HGSM integration q Preparation for HGSM shift to new version § Database q q Now running strictly off My. SQL, no Oracle used Reorganization of indexes – improved performance SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 28

Wiat. G: Introduction Web application for visualization of BDII information § http: //bdii. phy.

Wiat. G: Introduction Web application for visualization of BDII information § http: //bdii. phy. bg. ac. yu/Wiat. G/pl/Wiat. G. pl Used as an operational tool for site monitoring Highly responsive tool because it uses AJAX § Partial refresh (client receives part by part of the page) § Asynchronous (server is processing in the background, so one may send several requests) Current version seeks for: CE, g. CE, RB, g. RB, SE, LFC, FTS and Grid. ICE Documentation available: § http: //wiki. egee-see. org/index. php/Wiat. G PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 29

Wiat. G: Who is using it Several regional projects § § § EUMed. GRID

Wiat. G: Who is using it Several regional projects § § § EUMed. GRID (bdii. isabella. grnet. gr) EUChina. Grid (euchina-bdii-1. cnaf. infn. it) EELA (lnx 112. eela. if. ufrj. br) Baltic. Grid (bdii. mif. vu. lt) Int-EU-Grid (i 2 g-ii 01. lip. pt) Health-e-Child (hec-maat-server 2. cern. ch) http: //hec-maat-server 1. cern. ch/Wiat. G/pl/Wiat. G. pl ROC CERN § PROD § PPS § OPS (lcg-bdii. cern. ch) (pps-bdii. cern. ch) (sam-bdii. cern. ch) PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 30

Wiat. G: Technologies Following technologies are included in Wiat. G: § Perl is used

Wiat. G: Technologies Following technologies are included in Wiat. G: § Perl is used for LDAP connection to BDII and generation of HTML and XML data. § XML, the format for sending data from the web server to the client. § Cascading Style Sheets (CSS), a markup language used to define the presentation style of a page. § Java. Script, a scripting language. § XMLHttp. Request, an object that is used to exchange data between web client and web server. § Document Object Model (DOM), which provides a logical view of a web page as a tree structure. PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 31

Wiat. G: Architecture Wiat. G Server Side Browser Client XMLHTTPRequest callback() Java Script Call

Wiat. G: Architecture Wiat. G Server Side Browser Client XMLHTTPRequest callback() Java Script Call HTML & CSS Data HTTP Request Apache. HTTPServer XML Data LDAPto. XML script Query User Interface Response LDAP BDII PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 32

Wiat. G in action PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2

Wiat. G in action PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 33

Wiat. G: Further development (short term) Addition of new services (My. Proxy, local. LFC,

Wiat. G: Further development (short term) Addition of new services (My. Proxy, local. LFC, VO software tags, …) Development of the new tool “What should be at the Grid” (Wsbat. G) § Based on the site configuration exported from HGSM/GOCDB § Visually identical tool, providing the expected status of BDII in Wiat. G PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 34

Wiat. G: Further development (long term) Wiat. GS User Interface Wiat. G User Interface

Wiat. G: Further development (long term) Wiat. GS User Interface Wiat. G User Interface s. BDII web service Check correctness of s. BDII data Check equality of s. BDII-BDII information Check correctness of BDII data Wsbat. G User Interface HGSM/GOCDB web service Check equality of BDII-HGSM/GOCDB information Check correctness of HGSM/GOCDB data Alarms Dashboard SAM Alarms Dashboard UI PSC 05 Thessalonica, Meeting - Thessaloniki, 11 -12, September SEE-GRID-2 PSC 05 meeting, Greece -Greece, September 2007 35

R-GMA (1) Accounting views for SEEGRID-only sites per site accounting: ● https: //gserv 1.

R-GMA (1) Accounting views for SEEGRID-only sites per site accounting: ● https: //gserv 1. ipp. acad. bg: 8443/Accounting SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 36

R-GMA q Accounting views for SEEGRID and EGEE sites that support SEEGRID – per

R-GMA q Accounting views for SEEGRID and EGEE sites that support SEEGRID – per country/institution user accounting https: //gserv 1. ipp. acad. bg: 8443/Accounting-2 SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 37

R-GMA (2) q Accounting views for Job success rates and other statistics –in progress,

R-GMA (2) q Accounting views for Job success rates and other statistics –in progress, currently running on our own data only. https: //gserv 1. ipp. acad. bg: 8443/Jmon SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 38

R-GMA (3) q Accounting views for Job success rates and other statistics –in progress,

R-GMA (3) q Accounting views for Job success rates and other statistics –in progress, currently running on our own data only. https: //gserv 1. ipp. acad. bg: 8443/Jmon SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 39

Pakiti: Overview Pakiti Client § Installed on all nodes § Checks software versions against

Pakiti: Overview Pakiti Client § Installed on all nodes § Checks software versions against configured repositories § Sends report once per day to pakiti server Pakiti Server § Running at the Aristotle University of Thessaloniki § Main Components: q Feed – Daily reports from clients q Site Administrator’s front-end – Detailed view of the rpm package status at each node – Access is permitted only to each the administrator’s of each site via TLS Authentication using X. 509 v 3 Certificates § Addon Components q ROC Manager’s front-end – Aggregated view of the status of all the sites in the ROC – Developed by the AUTH GOC SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 40

Pakiti: Status of the Service Pakiti enabled sites in SEE-GRID ROC: Bosnia Herzegovina Romania

Pakiti: Status of the Service Pakiti enabled sites in SEE-GRID ROC: Bosnia Herzegovina Romania § BA-04 -PMFSA Bulgaria § § BG 01 -IPP BG 02 -IM BG 04 -ACAD BG 05 -SUGRID Croatia § HR-01 -RBI Greece § HG-01 -GRNET § HG-03 -AUTH § RO-01 -ICI Serbia § § § AEGIS 01 -PHY-SCL AEGIS 02 -RCUB AEGIS 03 -ELEF-LEDA AEGIS 04 -KG AEGIS 05 -ETFBG Turkey § TR-01 -ULAKBIM § TR-05 -BOUN SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 41

Pakiti and reporting The deployment of pakiti on sites is voluntary Sites deploying it

Pakiti and reporting The deployment of pakiti on sites is voluntary Sites deploying it provide accurate information on updates status on their nodes Proposal is that, in order to further improve status of SEE-GRID sites, all sites report in their 3 M reports the following: § Middleware version changes during the quarter § Status of updates (not needed if pakiti is deployed) § Major operational issues Template will be provided for this; if pakiti is deployed) such report would just contain one line with g. Lite version changed and paragraph or two describing operational issues encountered (basically, structured version of section 2. 3 of 3 M reports, now submitted by each site) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 42

SEE-GRID reorganized Wiki Reorganized SEE-GRID Wiki is now the main Wiki § http: //wiki.

SEE-GRID reorganized Wiki Reorganized SEE-GRID Wiki is now the main Wiki § http: //wiki. egee-see. org/index. php/SEE-GRID_Wiki Many documents still missing, main being: § § § Participating in SEEGRID as a Site (AP 1) Policy Documents (AP 3) SEEGRID certification procedure (AP 4) LFC (AP 6) RGMA (AP 7) My Proxy (AP 8) BDII/RB (AP 9) FTS (AP 10) SAM (AP 11) Grid. ICE(AP 12) How to Join the SEEGRID infrastructure as a user (AP 14) Grid usage basics (AP 16) Effort needed by all partners; UKIM coordinating SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 43

WP 3 developments HGSM Wiat. G Accounting glite-yaim-seegrid soon-to-be deployed apt/yum repository SEE-GRID-2 PSC

WP 3 developments HGSM Wiat. G Accounting glite-yaim-seegrid soon-to-be deployed apt/yum repository SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 44

Infrastructure, Site and VO metrics Infrastructure growth (CPUs, storage, memory? ) Bandwidth growth? Site

Infrastructure, Site and VO metrics Infrastructure growth (CPUs, storage, memory? ) Bandwidth growth? Site availabilities and downtimes (CE, SE) Accounting data (per site, per country, per application, per VO, per user community, time distribution); here SEEGRID VO and national VOs should be considered Job success rates (per site, per country, per application, per VO, per user community, time distribution); here SEEGRID VO and national VOs should be considered VO membership time evolution, distribution per country, per application, per user community; here SEEGRID VO and national VOs should be considered SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 45

A 3. 2: Status Concerning the bandwidt-on-demand some tests were done in order to

A 3. 2: Status Concerning the bandwidt-on-demand some tests were done in order to investigate the following protocols and services using our new router - CISCO 12000 XR: § § Resource Reservation Protocol (RSVP); Generalized Multi Protocol Label Switching (GMPLS); Differentiated Services (Diff. Serv); Standard activities for Bo. D. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 46

A 3. 3: Overview of the work CA establishment in SEE Region § Each

A 3. 3: Overview of the work CA establishment in SEE Region § Each country must setup each own national Certification Authorities § Each CA must be accredited by the EUGrid. PMA § see-ca-incubation mailing list (see-ca-incubation@grid. auth. gr) q q q Support during the process of establishing a new CA and for the accreditation period CA common procedures and best practices advices are provided Help on writing the CP/CPS documents § Process for establishing a new CA takes around one year SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 47

A 3. 3: Status New accredited CAs in the Region § Serbian CA (AEGIS

A 3. 3: Status New accredited CAs in the Region § Serbian CA (AEGIS CA) q q Accreditation request on August 23, 2006 Under review by Grid. AUTH team and SRCE CA (on behalf of EUGrid. PMA) Accredited on June 1, 2007 Operational since June 10, 2007 § Romanian CA (ROSA CA) q q q Accreditation request on January 25, 2006 Under review by Grid. AUTH team, PK-GRID CA and CESNET CA (on behalf of EUGrid. PMA) Accredited on August 1, 2007 Grid CA candidates § Montenegro CA (MREN CA) q CP/CPS reviewed by Grid. AUTH (via see-ca-incubation mailing list) on July 10, 2007 § F. Y. R. O. M. CA (MARGI CA) q q Accreditation request on May 4, 2007 First CP/CPS not yet available All candidates are encouraged to participate at the EUGrid. PMA meetings (Next meeting in Thessaloniki, Sept 19 -21) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 48

A 3. 4: Overview Official SEE-GRID 2 Portal user maintenance (52 users) § Quota

A 3. 4: Overview Official SEE-GRID 2 Portal user maintenance (52 users) § Quota management, user management Official SEE-GRID 2 Portal maintenance § Software (P-GRADE Portal version 2. 5) q P-GRADE Portal software bug fixing SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 49

A 3. 4: Status and development Portlets development has been done by turkish partner

A 3. 4: Status and development Portlets development has been done by turkish partner (P-GRADE Portal Development Alliance) § Already active /beta-test/ in a private portal installation. New portlets § File Management Portlet to manage the remote files through the LFC catalog and the LCG interface. q q Hot topic! Intended to merge into official P-GRADE Portal v 2. 5. § Credential management portlet to complement the existing certificate portlet with info, change pass-phrase and destroy operations. q Intended to merge with the default certificates portlet. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 50

WP 3 country reports Greece Switzerland/CERN Bulgaria Romania Turkey Hungary Albania Bosnia and Herzegovina

WP 3 country reports Greece Switzerland/CERN Bulgaria Romania Turkey Hungary Albania Bosnia and Herzegovina FYR of Macedonia Serbia Montenegro Moldova Croatia Work performed since PSC 04 Conformance to WP 3 objectives Issues, if any SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 51

Greece Pakiti Service enabled for SEE-GRID infrastructure § https: //monitor. grid. auth. gr/services/pakiti/ROC/SEE-GRID October

Greece Pakiti Service enabled for SEE-GRID infrastructure § https: //monitor. grid. auth. gr/services/pakiti/ROC/SEE-GRID October 2007 § HG-06 -EKT will support SEEGRID VO q 228 CPUs, 9. 3 TB Storage Exact Resources Dedicated for SEEGRID VO to be decided. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 52

Switzerland/CERN Support to WP 3 operations § GOOD shifts § Solving operational problems Support

Switzerland/CERN Support to WP 3 operations § GOOD shifts § Solving operational problems Support for SAM deployment and improvements, as well as liaison activities with SAM development team Liaison activities with operations in other regional Grid projects Strong involvement in operations-related developments: § Wiat. G, Wsbat. G § SEE-GRID apt/yum repository Bonn Presentation

Bulgaria (1) Status of the infrastructure and plan for expansion § 5 sites infrastructure

Bulgaria (1) Status of the infrastructure and plan for expansion § 5 sites infrastructure – significantly stable with good up-time § All sites upgrading now to SL 4 WNs. § Core services, monitoring tools: q q R-GMA: graphical on-line user interface Accounting views for – SEEGRID-only sites per site accounting – SEEGRID and EGEE sites that support SEEGRID – per country/institution user accounting – Job success rates and other statistics –in progress, currently running on our own data only. q q q FTS: used in production by SALUTE WMS – moved to a better hardware. BDII stability and capability improvements SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 54

Bulgaria (2) CPU April 06 • 5 production sites in BG • After start

Bulgaria (2) CPU April 06 • 5 production sites in BG • After start of EGEE II added new cluster with 80 CPUs and low-latency Myrinet interconnect for 80 CPUs – unique resource for special MPI jobs September 07 Storage Tape 30 1 TB - 132 3. 2 TB 10 TB • BG 01 -IPP (12 CPU) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 • BG 04 -ACAD (80 CPU) 55

Bulgaria (3): Petri net performance analysis Anastas Misev from Macedonia was at IPP in

Bulgaria (3): Petri net performance analysis Anastas Misev from Macedonia was at IPP in a visit, sponsored by project BIS 21++, working on his Ph. D. thesis on Grid scheduling and failover. Host professor was E. Atanassov His analysis of our RB rb 001 shows that § The overall success rate of the analyzed data is somewhere near 70% § The percentage of the successful jobs greatly depends on the users experience. Jobs by more experienced users have success rate above 80%. Interactive diagram helps in identifying the bottlenecks in the process model. It can show throughput time between any 2 transitions Color coding to specify low, middle and high waiting time Conclusions: § Job re-submission does not help in 99% of cases § 20% of the 470 jobs submitted by one user had waiting times above 57 hours, and all of them failed. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 56

Bulgaria (4): Job success rate – Top ten CEs We have made a pivot

Bulgaria (4): Job success rate – Top ten CEs We have made a pivot analysis of the CEs and the final statuses of the jobs. The top 10 CEs are shown in the table below. Note that the percentage of successful jobs is more then 90%. Top 10 CEs CE name Final Status DONE ABORT CANCEL Grand Total ce. ulakbim. gov. tr: 2119/jobmanager-lcgpbs-see 754 222 976 ce 002. ipp. acad. bg: 2119/jobmanager-lcgpbs-see 639 66 705 ce 01. ariagni. hellasgrid. gr: 2119/jobmanagerpbs-see 1317 2 1319 ce 01. athena. hellasgrid. gr: 2119/jobmanagerpbs-see 3008 105 3113 ce 01. isabella. grnet. gr: 2119/jobmanager-pbssee 768 358 ce 01. kallisto. hellasgrid. gr: 2119/jobmanagerpbs-see 2188 193 2381 ce 01. marie. hellasgrid. gr: 2119/jobmanager-pbssee 1296 40 1336 ce 02. grid. acad. bg: 2119/jobmanager-pbsmyrinet 1120 19 ce 02. grid. acad. bg: 2119/jobmanager-pbs-see 2883 160 3043 ce 101. grid. ucy. ac. cy: 2119/jobmanager-lcgpbssee 1008 3 1011 14981 1168 Grand Total SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 1 2 3 1127 1141 16152 57

Bulgaria (5): BG. ACAD CA – Status overview Accredited by EUGrid. PMA on March

Bulgaria (5): BG. ACAD CA – Status overview Accredited by EUGrid. PMA on March 05, 2007 Included in the IGTF CA RPM distribution from version 1. 13 Effective operations started March 21, 2007 Web-page: http: //www. ca. acad. bg/ Location: IPP-BAS, Sofia, Bulgaria Personnel: § 4 CA staff members; § 2 RA. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 58

Bulgaria (6): BG. ACAD CA – Status overview During the period March-August, 2007: §

Bulgaria (6): BG. ACAD CA – Status overview During the period March-August, 2007: § Total of 40 certificates are signed by BG. ACAD CA, including: q q 30 user certificates 10 host certificates § Total of 3 certificates are revoked by BG. ACAD CA. § Regular patches and updates to CA’s OS and software applied. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 59

Bulgaria (7): BG. ACAD CA - Development A concise end-user guide is written and

Bulgaria (7): BG. ACAD CA - Development A concise end-user guide is written and published on the web-site. It covers the basics of the application process. A shell-script for easier certificate request generation is developed and published. It contains step-by-step instructions and examples. Three cron-jobs are developed on the CA’s web server. These scripts monitor the following things: § Validity of the published certificates § Expiration of the published CRL Instant e-mail notifications to the CA’s staff members are provided. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 60

Romanian CA was accredited by Eu. Grid. PMA body and it will be operated

Romanian CA was accredited by Eu. Grid. PMA body and it will be operated by the Romanian Space Agency (ROSA) Site operational problems § Technical: Air cooling (RO-03 -UPB), Room renovation (RO-06 UNIBUC) § Non-technical(vacations and other personnel issues): all § RO-01 -ICI, RO-03 -UPB, RO-05 -INCAS, RO-06 -UNIBUC: uncertified status § RO-07 -NIPNE, RO-08 -UVT: certified Objectiv no. 1: Re-certify all the sites until 1 st. October § Migrate RO-05 -INCAS to EGEE if possible Bonn Presentation

Turkey (1): Sites Operation/Ticket Handling A new EGEE site has been added (TR-05 -BOUN)

Turkey (1): Sites Operation/Ticket Handling A new EGEE site has been added (TR-05 -BOUN) by the beginning of April 2007. Dedicated resources: TR-01 -ULAKBIM site (48 CPUs for seegrid, 16 CPUs for sgdemo) and TR-05 -BOUN (8 CPUs for seegrid). From Classic SE to DPM migration has been completed at TR-01 -ULAKBIM and TR-05 -BOUN. DPM ownership patches have been done. SEE-GRID-2 accounting patches have been done. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 62

Turkey (2): Sites Operation/Ticket Handling Although seegrid jobs has run successfully, there has been

Turkey (2): Sites Operation/Ticket Handling Although seegrid jobs has run successfully, there has been frequent SAM failures of TR-05 -BOUN in the last three months due to unknown prd/sgm account problems. We will compensate this lack of availability with forthcoming good performance of the site. Within October 2007, SEE-GRID-2 TR-* sites are planned to be upgraded to Scientific Linux 4. 5 together with glite 3. 1 middleware. Periodical updates, security patches have been done for all SEE-GRID-2 TR-* sites. Regular user, site problems were handled through SEE -GRID and national helpdesks. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 63

Turkey (3): Core services Smooth operation of the following core services has been enabled:

Turkey (3): Core services Smooth operation of the following core services has been enabled: § Core services supporting seegrid VO: RB, BDII, WMS, MYPROXY, P-GRADE Portal § Core services supporting sgdemo VO: RB, BDII, WMS, MYPROXY, LFC, P-GRADE Portal RB/WMS statistics have been provided for D 3. 1 b. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 64

Turkey (4): P-GRADE portal File Manager Portlet for Remote Storage Elements has been reviewed

Turkey (4): P-GRADE portal File Manager Portlet for Remote Storage Elements has been reviewed and tested together with SZTAKI. Specification of the file management for remote storage elements portlet was co-authored by SZTAKI and METU, and it is developed by METU. The portlet supports: LFC interaction commands for directory management and file management through LCG file naming conventions, namely, LFN and GUID. Credential Manager Portlet for My. Proxy has been reviewed and tested. The portlet is to be integrated with the P-GRADE Grid Portal. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 65

Hungary OS upgrade to SL 4. 4 Glite upgrade to 3. 0 x Recabling

Hungary OS upgrade to SL 4. 4 Glite upgrade to 3. 0 x Recabling of the internal network (new switch deployed) Maintenance § Grid-Operator-On-Duty (GOOD) 1 week in may/june § Infrastructure support, resolving Helpdesk tickets (script installation/hardware changes/security updates) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 66

Albania (1): Overall progress Change of CA § Follow-up of certificate problems Received local

Albania (1): Overall progress Change of CA § Follow-up of certificate problems Received local funding for equipment § Installed glite in biggest part of equipment Creation of new sites § § § New experimental site at INIMA New experimental site at FIE Preparations for site of FNS Preparations for site of FECO Plans for University of Elbasani and of Shkodra SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 67

Albania (2): INIMA Old site AL-01 -INIMA following upgrades New site AL-04 -INIMA with

Albania (2): INIMA Old site AL-01 -INIMA following upgrades New site AL-04 -INIMA with 9 nodes (4 nodes will be transferred in other universities) Problems with new status and building of INIMA … SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 68

Albania (3): FIE Power supply problems, have to put some money to resolve the

Albania (3): FIE Power supply problems, have to put some money to resolve the problem, to by inverters. Switched of during vacances SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 69

Albania (4): FNS Cluster installed Problem with real IPs, in some institutions § Administrative

Albania (4): FNS Cluster installed Problem with real IPs, in some institutions § Administrative problems to get separate Internet link § … … SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 70

Bosnia and Herzegovina (1) BA-01 -ETFBL functioning correctly § New 4 x WN (C

Bosnia and Herzegovina (1) BA-01 -ETFBL functioning correctly § New 4 x WN (C 2 D, 1 GB RAM, 80 GB HDD) § New SE – C 2 D, 2 GB RAM, 2 x 320 GB HDD BA-03 -ETFSA § New server node - HP ML 110 G 4, X 3040, 4 GB, 2 x 160 GB § New 11 WNs - HP dc 5750, MT A 64 -35, 1 GB, 160 GB § New Switch BA-04 -PMFSA § New 4 x WN (C 2 D, 1 GB RAM, 160 GB HDD) § New Switch BA total now: § Total CPUs: 50+ § Total Storage: 1+ TB Availability much better SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 71

Bosnia and Herzegovina (2) SAM Server Portal § BBm. SAM q q q Service

Bosnia and Herzegovina (2) SAM Server Portal § BBm. SAM q q q Service availability and SLA calculations implemented MAINTENANCE status implemented in a better way Enhanced OVERVIEW (main) page of BBm. SAM – Showing uptime for last 24 h – Filters available for: country, tier, certified status, last test state § BBmobile. SAM q Now also showing uptime percentage for last 24 h § HGSM integration q Preparation for HGSM shift to new version § Database q q Now running strictly off My. SQL, no Oracle used Reorganization of indexes – improved performance SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 72

FYR of Macedonia (1): Cluster addition equipment MK-01 -UKIM cluster § 18 new nodes

FYR of Macedonia (1): Cluster addition equipment MK-01 -UKIM cluster § 18 new nodes added using Virtual. Box WN § Tested with support of Antun § Currently installed on the old CE node but a new CE will be installed to support these WNs By the end of the year § 16 new CPUs will be installed (non Virtual. Box) § 2 TB storage SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 73

FYR of Macedonia (2): Cluster addition equipment MK-02 -ETF cluster § 24 new CPU

FYR of Macedonia (2): Cluster addition equipment MK-02 -ETF cluster § 24 new CPU added § By end of september new SE and CE will be installed § SE 1 TB storage SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 74

FYR of Macedonia (3): New Clusters MK-03 § Still in progress § Hardware purchase

FYR of Macedonia (3): New Clusters MK-03 § Still in progress § Hardware purchase is done § Consultations of initial installation SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 75

FYR of Macedonia (4): Other activities Wiki pages will be provided for the installation

FYR of Macedonia (4): Other activities Wiki pages will be provided for the installation of Virtual. Box WN CA status: § Software is installed. § We will proceed in September with the review by EUGRID PMA. § Our representative was attending the last EUGRID PMA meeting in Turkey. SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 76

Serbia (1): Infrastructure status 6 sites across the country Current number of CPUs: 195

Serbia (1): Infrastructure status 6 sites across the country Current number of CPUs: 195 (increase of 43 compared to PSC 04) Storage: 0. 4 TB (approx. the same) Expansion plans § All 3 rd parties already have a site § We expect two new sites, one in Novi Sad (Faculty of Agriculture, University of Novi Sad), and one in Nis (IRVAS SME) § Hardware delivery for AEGIS 01 -PHY-SCL is expected this week, 32 64 -bit cores, and storage upgrade to more than 20 TB; another purchase is being finalized (more CPUs) § AEGIS will propose hardware purchase from Serbian National Investment Plan for the whole NGI SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 77

Serbia (2): Core services / SEEGRID Resources LCG-RB, GLITE-WMS, BDII, My. Proxy, LFC at

Serbia (2): Core services / SEEGRID Resources LCG-RB, GLITE-WMS, BDII, My. Proxy, LFC at IPB LFC at UOB for SEEGRID and SGDEMO VO VOMS for AEGIS VO, can be deployed as a backup for SEEGRID VO if necessary Support to T-infrastructure § In all core services § In sites: AEGIS 02 -RCUB, AEGIS 04 -KG SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 78

Serbia (3): AEGIS CA CP/CPS Document finalised Object identifier: 1. 3. 6. 1. 4.

Serbia (3): AEGIS CA CP/CPS Document finalised Object identifier: 1. 3. 6. 1. 4. 1. 23658. 10. 1. 1. 0 Date: 02 December 2006 DNs: § § § Issuer: C=RS, O=AEGIS, CN=AEGIS-CA Subject: C=RS, O=AEGIS, OU=XXX, CN=Subject-name Country: Must be “RS” Organization: Must be “AEGIS” Organization. Unit: Must be the name of the subject's institute Common. Name: First name and last name of the subject for user certificates, DNS Bonn Presentation

Serbia (4): AEGIS CA Accreditation request on August 23, 2006 Under review by Grid.

Serbia (4): AEGIS CA Accreditation request on August 23, 2006 Under review by Grid. AUTH team and SRCE CA (on behalf of EUGrid. PMA) Accredited on June 1, 2007 Operational since June 10, 2007 Already issued 53 user and host certificates Bonn Presentation

Serbia (5): Other activities Leading WP 3; overall activities coordination and representation at various

Serbia (5): Other activities Leading WP 3; overall activities coordination and representation at various Grid meetings Providing core services Wiki contributions: § GLITE-3 guide § SL 4. 5 WN g. Lite-3. 1 guide for 32 bit and 64 bit architectures Grid-Operator-On-Duty, doing it on shifts and coordinating MW deployment, assessment, upgrade coordination Operations coordination Development coordination § Collaboration with EGEE § Collaboration with other regional Grid projects Development involvement § Problems identification, support for debugging and patching § Customizations of YAIM and providing glite-yaim-seegrid SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 81

Montenegro Sites & upgrades § 1 site (MREN-01 -CIS) q WN : Upgrade from

Montenegro Sites & upgrades § 1 site (MREN-01 -CIS) q WN : Upgrade from 4 to 24 CPUs and upgrade on SL 4. 4 q Storage : upgrade to 0. 54 Tb q Migration from Classic SE to DPM SE q MPI support No centralized services of SEE-GRID in Uo. M CA § CP/CPS document was written and sent to see-ca-incubation mailing list for approval and suggestions Sites operation and ticket handling status/problems § Few problems with DPM SE installation SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 82

Moldova (1) MD-01 -TUM site configuration, setting up and internal tests procedures MD-01 -TUM

Moldova (1) MD-01 -TUM site configuration, setting up and internal tests procedures MD-01 -TUM site hardware issues resolved (caused a delay in internal tests and site further operation) Working on CA service development § Learning other countries CA experience. § Study of Eugrid. PMA documents and selection of those appropriate for conditions in Moldova Determination of future sites hardware configuration Organization of the tender for purchasing of the equipment according to the Mo. Us with 3 institutions (Institute of the Mathematics and Computer Science, State University of Medicine and Pharmaceutics, Faculty of Radio Electronics of the Technical University of Moldova) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 83

Moldova (2) New sites are expected to join MD-GRID infrastructure till the end of

Moldova (2) New sites are expected to join MD-GRID infrastructure till the end of the project: § MD-02 -IMI site which will be installed in the Institute of the Mathematics and Computer Science (8 Intel Xeon quad core CPUs, 1, 5 TB of storage) § MD-03 -SUMP site which will be installed in the State University of Medicine and Pharmaceutics (5 Intel PIV CPUs, 1 TB of storage) § MD-04 -RENAM, which will be placed in the FRE TUM (Faculty of Radio Electronics of the Technical University of Moldova) NOC of the RENAM Association (8 Intel Xeon dual core CPUs, 2 TB of storage) SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 84

Croatia (1): Site status HR-01 -RBI site § WNs upgraded to q q Debian

Croatia (1): Site status HR-01 -RBI site § WNs upgraded to q q Debian 4. 0 g. Lite 3. 1 TAR § sgdemo and MPI enabled § node packages up-to-date HR-02 -GRF site § hardware being purchased § 4 nodes ~ 30 CPUs: q q 2 8 2 2 x Intel Xeon 5310 Quad. Core CPU, 1. 6 GHz, 8 MB L 2 C GB ECC FBD RAM x 500 GB SATA HDD x Gigabit Ethernet Bonn Presentation

Croatia (2): Other activities VOMS server regular maintenance § primary for seegrid § backup

Croatia (2): Other activities VOMS server regular maintenance § primary for seegrid § backup for sgdemo, see National CA operated by SRCE GOOD shifts Wiki updates § BDII response time § standalone SAM § VOMS configuration local user support for middleware problems preparation of review reports about seegrid VO Bonn Presentation

WP 3 APs and Issues (1) Communication / response problems Deadlines must be reasonably

WP 3 APs and Issues (1) Communication / response problems Deadlines must be reasonably set but also respected All sites need to resolve their operational problems, and solve all Helpdesk tickets, esp. the outstanding ones SLA conformance monitoring will continue Helpdesk improvements needed – statistics extraction needs to be perfected; currently this is difficult (end of October) Wiki reorganization and updates ASAP finished Application SEEGRID VO VOMS roles started to be used by WP 4 application developers ASAP Application level accounting implemented partially; should be fully implemented and used ASAP SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 87

WP 3 APs and Issues (2) Moldova to join the infrastructure by finishing certification

WP 3 APs and Issues (2) Moldova to join the infrastructure by finishing certification of MD-01 -TUM site ASAP 3 M reporting of sites to include information on updates and operational problems according to the template (to be provided) Partners should be more responsible when performing GOOD shifts MPI WG to be established and to define standard for MPI setup of SEE-GRID sites; to finish its work until mid. October Infrastructure, site, VO metrics to be precisely defined What happened to live UI (Boro)? SEEGRID VO commitments ASAP Review of critical SAM tests SEE-GRID-2 PSC 05 Meeting - Thessaloniki, Greece, 11 -12 September 2007 88