Section II Applications of Measurements 2 Earthwork Profile

  • Slides: 14
Download presentation
Section II Applications of Measurements 2. Earthwork ﻛﻤﻴﺎﺕ ﺍﻟﺤﻔﺮ ﻭ ﺍﻟﺮﺩﻡ

Section II Applications of Measurements 2. Earthwork ﻛﻤﻴﺎﺕ ﺍﻟﺤﻔﺮ ﻭ ﺍﻟﺮﺩﻡ

Profile Leveling ﺍﻟﻘﻄﺎﻋﺎﺕ ﺍﻟﻄﻮﻟﻴﺔ • To collect data about topography along a reference line.

Profile Leveling ﺍﻟﻘﻄﺎﻋﺎﺕ ﺍﻟﻄﻮﻟﻴﺔ • To collect data about topography along a reference line. • Mainly to compute volumes of cut and fill ﺍﻟﺤﻔﺮ ﻭ ﺍﻟﺮﺩﻡ for a proposed linear structure, such as: highways, railroads, transmission lines, canals. Then the best route can be chosen. • The result: elevations at definite points (stations) along a reference line, usually the center line.

Field Procedures Profile leveling

Field Procedures Profile leveling

 • First a backsight at a BM is observed. • Then, a number

• First a backsight at a BM is observed. • Then, a number of intermediate sights are observed at the locations needed, do not have to be at equal distances. • When the distance becomes too long, or readings become hard to observe, a turning point ﻧﻘﻄﺔ ﺩﻭﺭﺍ ﻥ is constructed. • You cannot keep the backsight distance equal to the foresight distance. • Elevation computation: – – Elevation of line of sight (LS) = EBM + BSBM. Elevation of any intermediate point = ELS - ISIP. Elevation of point at FS = ELS - FSPOINT Handle new level positions as in differential leveling, construct a turning point and knowing BS and FS readings, compute a new elevation of line of sight.

Example Point Backsight (BS) ﻣﺆﺨﺮﺓ BM 09 1. 573 Intermediate sight (IS) ﻣﺘﻮﺳﻄﺔ 1.

Example Point Backsight (BS) ﻣﺆﺨﺮﺓ BM 09 1. 573 Intermediate sight (IS) ﻣﺘﻮﺳﻄﺔ 1. 472 2 1. 718 1. 352 4 5 6 Elevation of line of sight (HI) ﻣﻨﺴﻮﺏ ﺧﻂ ﺍﻟﻨﻈﺮ Elevation 20. 00 1 3 Foresight (FS) ﻣﻘﺪﻣﺔ 1. 551 1. 181 1. 492 1. 212 2. 101

Answer Point Backsight (BS) ﻣﺆﺨﺮﺓ BM 09 1. 573 Intermediate sight (IS) ﻣﺘﻮﺳﻄﺔ 1.

Answer Point Backsight (BS) ﻣﺆﺨﺮﺓ BM 09 1. 573 Intermediate sight (IS) ﻣﺘﻮﺳﻄﺔ 1. 472 2 1. 718 1. 352 4 5 Elevation of line of sight (HI) ﻣﻨﺴﻮﺏ ﺧﻂ ﺍﻟﻨﻈﺮ 21. 573 1 3 Foresight (FS) ﻣﻘﺪﻣﺔ 20. 00 20. 101 19. 885 1. 551 21. 374 1. 181 1. 212 Elevation 20. 022 20. 193 1. 492 6 2. 101 21. 094 19. 882 18. 993

Drawing and Using Profiles • Drawn using a software now. • To manually draw

Drawing and Using Profiles • Drawn using a software now. • To manually draw a profile and compute earthwork: – Assume the horizontal axis is the distance and the vertical axis is the elevation. – Use a larger scale for the elevation than the scale of the distance, usually 10 times larger. – Draw the design line at the proposed grade ﺍﻟﻤﻴﻞ. – Compute the areas of cut and fill. – Multiply area by width to get volumes. – Gradient ( ﺍﻟﻤﻴﻞ percent grade) is the rise or fall in m per 100.

1 m 10 m Horizontal scale 1: 2500 Vertical scale 1: 250

1 m 10 m Horizontal scale 1: 2500 Vertical scale 1: 250

Example The table below shows ground elevations along the centerline of a proposed pipeline.

Example The table below shows ground elevations along the centerline of a proposed pipeline. If the bottom of the trench to be excavated is at elevation (+115 m) at point (A) and slopes -1%, and the trench is 2 m wide, compute the volumes of cut and fill. {Answer is given in lecture} Point Distance (m) Elevation (m) A 0. 0 115. 0 B 100 117. 2 C 200 116. 0 D 300 112. 0 E 400 110. 5 F 500 110. 0

Borrow-Pit Method ﺍﻟﻤﻴﺰﺍﻧﻴﺔ ﺍﻟﺸﺒﻜﻴﺔ • Not suitable for linear features, very useful for construction

Borrow-Pit Method ﺍﻟﻤﻴﺰﺍﻧﻴﺔ ﺍﻟﺸﺒﻜﻴﺔ • Not suitable for linear features, very useful for construction sites. • The site is divided into equal squares. Elevations are then measured at the corners of the grid ﺍﻟﺸﺒﻜﺔ , which are given names that correspond to the corner coordinates in the grid, ex: 3 -D, 4 -A, etc. Then heights of cut or fill (hij) over design elevation are computed. Where is the height at the intersection of axes i with axis j, then: V = (hijn) A yd 3 ( ) 4*27 • The idea is to multiply each height by the number of complete squares it is common to (n), the product is then multiplied by (A/4) where A is the area of one of the squares

The volume on any square, or part of a square is equal to the

The volume on any square, or part of a square is equal to the average height(elevation difference) at the corners, times the area. To compute the volume: 1 - draw a line between the cut and the fill areas 2 - compute the total volume of all the complete cut squares, do the same for the fill, use the previous formula 3 - Compute the incomplete squares separately and add them to the squares. 4 - Compute the difference between the cut and the fill. , pay attention to the expansion factor.

A 1 2 B C h. A 1 h. B 1 V 1 =

A 1 2 B C h. A 1 h. B 1 V 1 = A * (h. A 1 + h. B 1 + h. A 2 + h. B 2) / 4 V 2 =A * (h. B 1 + h. C 1 + h. B 2 +h. C 2) / 4 h. A 2 h. B 2 h. C 1 h. C 2 V 3 = A* (h. A 2 + h. B 2 + h. A 3 +h. B 3) / 4 h. B 3 3 h. A 3 Total volume V = A* {(h. A 1 + h. B 1 + h. A 2 + h. B 2) / 4} + A* {(h. B 1 + h. C 1 + h. B 2 +h. C 2) / 4} + {A*(h. A 2 + h. B 2 + h. A 3 +h. B 3) / 4} = (h. A 1 +2 h. B 1 + h. C 1 + 2 h. A 2 + 3 h. B 2 + h. C 2 + h. A 3 + h. B 3) / 4

Example The table below shows the heights of cut and fill in meters at

Example The table below shows the heights of cut and fill in meters at the corners of a 20 m grid. Compute the volume of soil to be imported or disposed. Assume 25% expansion factor for the fill. ( + is cut, - is fill) Corner A-1 B-1 C-1 D-1 A-2 B-2 C-2 Height +3. 1 +2. 8 +2. 0 +4. 0 +2. 8 +2. 2 +1. 5 Corner D-2 A-3 B-3 C-3 D-3 A-4 B-4 Height +1. 2 +2. 0 +1. 7 +1. 0 0. 0 +1. 5 +0. 8 Corner C-4 D-4 Height 0. 0 - 3. 00