SCT Meeting 24 February 2012 SCT Project Management
SCT Meeting, 24 February 2012 SCT Project Management Issues Rob Cameron KIPAC, SLAC rac@stanford. edu 1
SCT Meeting, 24 February 2012 SCT Project Office Organization As shown in the submitted MRI proposal to NSF – Should add a Quality Assurance function later, during manufacture and testing 2
SCT Meeting, 24 February 2012 Management for CTA-US R&D § It is not cost effective to implement a full project office during the SCT R&D, because of lower funding levels during the phase; so start with limited functions § We should ramp up Project Management activities to be ready to support Prototype SC telescope construction § Systems Engineering work can proceed in parallel to design work in the Design Phase § Project Office can take on resource use and budget reporting task for smaller groups within collaboration 3
SCT Meeting, 24 February 2012 SCT and CTA Project Management § SCT Project must maintain its own schedule § Not consistent with CTA schedule and might it change § But should track possible coordination of activities for resource sharing and cost savings § SCT Project will have its own progress tracking and status reporting functions for the US funding agencies § Try to avoid doubled reporting duties as much as possible § SCT must have its own Systems Engineering support § But coordinate closely with CTA Systems Engineering § Look to having a common Document Control function as much as possible with CTA Project § Look to having common QA and Change Control functions as much as possible with CTA Project 4
SCT Meeting, 24 February 2012 Near-term Project Office Tasks § Several management tasks have early priority for the SCT R&D § Development of WBS for CTA-US work § Get agreement by all US partner institutions for specific work areas, and also re-collect resource data from each institution § The degree of WBS management will be appropriate to size of groups within CTA-US § Outputs generated while producing the WBS: § Schedule: do more detailed task scheduling, plus identification of milestones. Also refine CTA-US schedule in comparison to overall CTA schedule. § Deliverables: hardware items, documents, reports etc. § Resources: Produce a Resource Allocation Matrix across WBS and groups § Costs: Refine CTA-US R&D and Project cost estimates § Implement a simplified resource and cost tracking process § Avoid full Earned Value Management system in R&D phase because of reduced funding levels § Implement status/progress reporting for the funding agencies 5
SCT Meeting, 24 February 2012 Project Management Infrastructure Needs Resource and cost tracking and reporting system § Will be needed in Design Phase § Will work with agencies to establish needed level of detail § A Document Database and Document Control System § Will be needed in Design Phase § Look to CTA Project for common use if possible § Initially need to draft a Document Tree for the SCT Project § Define required documents such as Specifications, Interface Control Documents etc for systems and sub-systems. Look at commonality and consistency of defined documents with CTA Project. § Later: Change Control process § To be in place at the time of the final design of the prototype § Look to CTA Project for common use if possible § 6
SCT Meeting, 24 February 2012 Backup Slides 7
SCT Meeting, 24 February 2012 Backup Slides 8
SCT Meeting, 24 February 2012 Project Office Roles and Responsibilities § Project Scientist/Deputy Project Scientist § Project Manager § Systems Engineer § IT Manager § Administrative Support 9