Schedule Access to the hall b 508 Magdalena
Schedule Access to the hall b 508. Magdalena Kowalska
ISOLDE schedule Protons to ISOLDE: 10 July; 1 st beam – wk 29; physics from around July 28 (planned for 21 July before) Stop: 15 December 20 weeks of physics (21 wks available in principle) 2
ISOLDE schedule V 1. 0 -1. 1, Apr 25 th HRS delayed by 1 -2 wks -> v 1. 2 in preparation Each collaboration and setup get some beam Ø priority for IS exp waiting long or failed before 530 shifts requested 260 scheduled so far: Ø 14 wks Ø 29 IS exp. 5 LOIs Buffer time on HRS: Physics not delayed in spite of HRS problems 3
ISOLDE schedule 4
Access to ISOLDE From beginning of July: Ø Access to HIE-ISOLDE worksite: only local physicists when moving equipment Ø Access for users from Jura side 5
Access to ISOLDE Users requesting dosimeter after Jul 1 st: (www. cern. ch/isolde/get-access-isolde-facility) No temporary dosimeters possible To obtain dosimeter: Ø Ø Follow online courses on general safety (as before) Follow online RP course on Supervised Areas (as before) Follow ISOLDE online RP course – NEW, being finalised Present RP form signed by home institute – NEW, available since last week To access ISOLDE (after July 22 nd): Ø Follow 2 -h RP ISOLDE practical course – NEW (2 pm Tue, Fri, 1 st course planned for Jul 22 nd) CERN staff requesting dosimeters: as before (online courses + 1 -day course) Users and staff with valid dosimeters: After July 1 st: Follow ISOLDE online RP course Follow new procedure when present medical certificate expires Access to ISOLDE via dosimeter, not CERN card 6
Access to ISOLDE In case of doubts: contact us Equivalent of medical certificate required by CERN until now If provided by institute. If nothing written: it will be taken as 2 years. Institute can decide on a shorter validity. 7 RP-responsible. If none: person signing the home institution declaration.
b 508 From E. Siesling 8
b 508 Status: Building ready April 2014 -> May Ø to do inside: doors, sanitaria, false ceiling & walls (waiting for CV/EL) Ø Infrastructure ready June 2014 -> September CV: re-design caused substantial delay (3 mnts) Ø System summary and final approval expected this week EL – waited for CV input Ø Proposal from contractor expected this week EL and CV to start asap Asphalt & metal passage structure this month Installation controlled access June 2014 -> July Tourniquet and fences installation Installations users as of July 2014 -> As soon as possible (August, September? ) ISOLDE Milestones: Protons to Isolde 10 July 2014; physics ISOLDE start 21 July physics from 508 start. . 9
- Slides: 9