Santa Rita Jail Going off the Grid Alameda

  • Slides: 26
Download presentation
Santa Rita Jail Going off the Grid Alameda County/RESCO CCAEA Meeting February 5, 2010

Santa Rita Jail Going off the Grid Alameda County/RESCO CCAEA Meeting February 5, 2010

The Energy Program Team Established in 1987 GSA/TSD ó ó ó 1 Program Manager

The Energy Program Team Established in 1987 GSA/TSD ó ó ó 1 Program Manager 1 Project Manager 2 Electrician/Construction Coordinators Project and Cost Savings Oriented Minimum 10% IRR

Accomplishments Energy Program: 1987 -2010 $ Total Energy Saving Capital Projects Value = $50

Accomplishments Energy Program: 1987 -2010 $ Total Energy Saving Capital Projects Value = $50 M $ Total Energy Incentives and Refunds = $28 M $ Current Annual Utility Budget = $11. 5 M $ Current Annual Energy Cost Avoidance = $7. 5 M

Juvenile Justice Center LEED Gold 2007

Juvenile Justice Center LEED Gold 2007

Santa Rita Jail, Dublin, CA Construction 1984 -1989 Occupied Space: 1 million sqft. Peak

Santa Rita Jail, Dublin, CA Construction 1984 -1989 Occupied Space: 1 million sqft. Peak Electrical Load: 3. 2 m. W (8/00) 18 Housing Units 4300 inmates 513 Sheriff’s Dept. staff 80 GSA staff

Santa Rita Jail 2007 Utility Cost Electricity: $ 980, 000 Natural Gas: $ 900,

Santa Rita Jail 2007 Utility Cost Electricity: $ 980, 000 Natural Gas: $ 900, 000 Water: $ 860, 000 Sewage: $ 540, 000 Total: $ 3, 280, 000 (35% of GSA’s Utility Costs)

Fluorescent Lighting and Exhaust Fan Motor Retrofit (1995) 9, 000 Efficient Light Fixtures Retrofitted

Fluorescent Lighting and Exhaust Fan Motor Retrofit (1995) 9, 000 Efficient Light Fixtures Retrofitted 600 Energy Efficient Motors Replaced

Largest Rooftop Solar Power System on a Government Facility (2002) $450 K Annual Energy

Largest Rooftop Solar Power System on a Government Facility (2002) $450 K Annual Energy Cost Savings, 10% of Energy Used from the Sun

The Chilled Water Plant Retrofit

The Chilled Water Plant Retrofit

Cool Roof Application

Cool Roof Application

First Mega. Watt Class Fuel Cell Cogeneration Plant (2006)

First Mega. Watt Class Fuel Cell Cogeneration Plant (2006)

Santa Rita Jail Integrated Energy & Water Efficiency Project (2009): Hot Water Boiler Plant

Santa Rita Jail Integrated Energy & Water Efficiency Project (2009): Hot Water Boiler Plant Renovations Four High Efficiency Boiler 2 Domestic Hot Water Heat Exchangers

Santa Rita Jail: Reduced Hot Water Temperature 54 New Hot Water Coils 52 New

Santa Rita Jail: Reduced Hot Water Temperature 54 New Hot Water Coils 52 New Hot Water Expansion Compensators

Santa Rita Jail: Lighting Retrofit Gym before retrofit Retrofitted • 9000 Florescent Lighting Fixtures

Santa Rita Jail: Lighting Retrofit Gym before retrofit Retrofitted • 9000 Florescent Lighting Fixtures Replaced • 250 HID with Fluorescent Fixtures Gym after retrofit Permanently Delamped • 7000 Fluorescent Lamps

Santa Rita Jail: Water Efficiency Retrofitted • 1400 Inmate Flush Valves • 1400 Inmate

Santa Rita Jail: Water Efficiency Retrofitted • 1400 Inmate Flush Valves • 1400 Inmate Lavatory Valves • 150 Inmate Showers Valves Replaced • 160 Staff/Public Toilets • 30 Staff/Public Urinals • 210 Staff/Public Sink Aerators • 30 Staff Showerheads • 8 Smart Irrigation Controllers

Santa Rita Jail: Laundry Water and Heat Reclamation

Santa Rita Jail: Laundry Water and Heat Reclamation

Santa Rita Jail: Cooling Tower Water Treatment

Santa Rita Jail: Cooling Tower Water Treatment

Santa Rita Jail Energy & Water Efficiency Projects (1993 – 2009) Results $1. 7

Santa Rita Jail Energy & Water Efficiency Projects (1993 – 2009) Results $1. 7 M in Yearly Electrical Cost Savings: 65% Reduction $285 K in Natural Gas Cost Savings: 40% Reduction $540 K in Water/Sewage Cost Savings: 50% Reductions

Santa Rita Jail: Day Room Induction Lighting Retrofit (Feb 2010) 250 W/400 W Existing

Santa Rita Jail: Day Room Induction Lighting Retrofit (Feb 2010) 250 W/400 W Existing Metal Halide before retrofit Retrofit • 864 Lighting Fixtures 120 W Retrofitted Induction after retrofit Savings • 243 k. W Demand Reduction • 1. 7 M k. Wh Energy Reduction

Santa Rita Jail: Smart. Grid (2010)

Santa Rita Jail: Smart. Grid (2010)

Project Partners n Alameda County, California - Santa Rita Jail n Chevron Energy Solutions

Project Partners n Alameda County, California - Santa Rita Jail n Chevron Energy Solutions And… 22

SRJ Smart Grid Project Goals Existing 1. 2 MW Solar PV • True system

SRJ Smart Grid Project Goals Existing 1. 2 MW Solar PV • True system integration of renewable and clean distributed energy resources Existing 1. 0 MW Fuel Cell Smart Grid New 12 k. W Wind Power • Superior Utilization and Control of renewable and clean distributed energy resources • Improved local utility grid stability, and demand response • Improved local power quality and reliability Reduction of DHW Energy Load New 2 MW Battery Facility Energy Efficiency Measures • Off-grid Island capability • Energy price arbitrage capability • Demand Response Capabilities New Solar Thermal

System Design – Load Impacts n Cloudy Spring Day – Solar Output Uneven 25

System Design – Load Impacts n Cloudy Spring Day – Solar Output Uneven 25

Santa Rita Jail Smart Grid Project Total Project Cost: $12, 100, 000 Funding: DOE

Santa Rita Jail Smart Grid Project Total Project Cost: $12, 100, 000 Funding: DOE Grant: RESCO Grant: PG&E Incentive Chevron ES Share: PG&E Share: County Share: $ 6, 200, 000 $ 1, 980, 000 $ 3, 000 $ 120, 000 $ 350, 000 $ 450, 000