Risk Severity Matrix 7 7 Risk Event Response











































- Slides: 43
Risk Severity Matrix 7 -7
Risk Event Response Contingency Plan Trigger Who is Responsibl e
CHAPTER EIGHT Scheduling Resources
PMBOK – Resource Management • Project human resource management: – Includes the processes required to make the most effective use of the people invovled with the project. • Individual contributors • Etc.
PMBOK – Resource Management • Major Processes – Organizational Planning – Staff acquisition
PMBOK – Resource Management • Organizational Planning – Involves identifying, documenting and assigning project roles, responsibilities, and reporting relationships to either individuals or groups. – Reviewed/revised regularly throughout project – Tightly linked to communications planning
PMBOK – Resource Management Organizational Planning Inputs Project Interfaces Staffing Requirements constraints Process Output Role and responsibility assignments Staffing management plan Organization chart Supporting detail
PMBOK – Resource Management • Staff Acquisition – Involves getting the human resources needed (individuals or groups) assigned to and working on the project.
PMBOK – Resource Management Staff Acquisition Inputs Staffing management plan Staffing pool description Recruitment practices Process Output Project Staff Assigned Project team directory
PMBOK – Resource Management • Team development – Includes both enhancing the ability of stakeholders to contribute as individuals as well as enhancing the ability of the team to function as a team. – Complicated by two bosses.
PMBOK – Resource Management Team Development Inputs Project staff Project plan Staffing management plan Performance resports External feedback Process Team Building activities General management skills Reward recognition systems Collocation Training Output
Types of Project Constraints • Technical Constraints • Physical Constraints • Resource Constraints
8 -1 Constraint Examples
Technical Constraints • Also called logic constraints • Sequence of events for project activities • CPM addresses these – X-Planes
Physical Constraints • Contractual • Environmental • Handled similar to resource constraints – X-Planes
Resource Constraints • Parallel activities hold conflict for resources • Wedding example – One person, many tasks • X-Planes
Types of Resource Constraints • People – Most Important • Materials – Exotic • Equipment – Type Size Quantity • Working Capital – My Driveway
Classification of Scheduling • Time Constrained • Resource constrained Customer Project Manager Time Resources
Project Priority Matrix Constrain: The original parameter is fixed. The project must meet the completion date, specs. And scope of the project, or budget Enhance: Given the scope of the project, which criterion should be optimized? Time Constrain Enhance Accept: For which criterion is it tolerable not to meet the original parameters? Accept Performance Cost
Time Constrained • Resource Utilization focus • Level within Slack
Botanical Garden 8 -4
Botanical Garden 8 -4 Results: Reduced resources Required by 25% (from 4 to 3) Did not affect Schedule Why: Some Equipment Not Easily moved. Negatives: Loss of Slack
Resource Constrained Projects • Difficult to manage • No good math models for: • Rules (Heuristics) – Allocation of resources to activities to minimize project delays
Heuristics Rules that Seem to Work • Follow in order: Assign resources according to activities with: 1. Minimum slack Then if tie: 2. Smallest Duration Then if still a tie: 3. Lowest Activity Identification Number
Resource-Constrained Schedule Through Period 0 -1 8 -7
Resource-Constrained Schedule Through Period 1 -2 8 -7
Resource-Constrained Schedule Through Period 2 -3 8 -7
Resource-Constrained Schedule Through Period 2 -3 Continued Next least slack Least Slack Most Slack Assign Least Slack First
Resource-Constrained Schedule Through Period 3 -4 0 x Nothing to do here Can’t assign activity B, its too large (2+2=4>3 So, must leave C and D alone
Resource-Constrained Schedule Through Period 4 -5 -1 x x Nothing to do here Can’t assign activity B, its too large (2+2=4>3 So, must leave C and D alone
Resource-Constrained Schedule Through Period 5 -6 -2 x x x Nothing to do here Can’t assign activity B, its too large (2+2=4>3 So, must leave C and D alone
Resource-Constrained Schedule Through Period 6 -7 x -2 1 x x x 2 x 1 3 Now, we assign activity with least Slack, that is activity B with – 2 periods of Slack. Next activity F has least slack so assign
Resource-Constrained Schedule Through Period 7 -8 x x -2 0 x x x 2 2 x 1 1 x 3 3 Now, we assign activity with least Slack, that is activity B with – 2 periods of Slack. Next activity F has least slack so assign
Resource-Constrained Schedule Through Period 8 -9 x x -2 -1 x x x 2 2 2 x x x 1 1 1 3 3 Now, we assign activity with least Slack, that is activity B with – 2 period of Slack. Next activity F has least slack assign
Resource-Constrained Schedule Through Period 9 -10 x -2 -2 x x x 2 2 x x 1 1 3 3 3 Now, we assign activity with leas Slack, that is activity B with – 2 p of Slack. Next activity F has least s assign
Resource-Constrained Schedule Through Period 10 -11 x -2 -2 x x x 2 2 x x 1 1 3 3 3 2 1 -1 x 3 Now, we assign activity with least Slack, that is activity B with – 2 periods of Slack. Next activity E has least slack so assign
Resource-Constrained Schedule Through Period 11 -12 -2 x x s x 2 2 x x 1 1 3 3 3 2 2 s 3 1 1 x x 3 Now, we assign activity with least Slack, that is activity B with – 2 periods of Slack. Next activity E has least slack so assign
Resource-Constrained Schedule Through Period 1 -14 8 -9
EMR Project Network View— Schedule Before Resources Leveled 8 -11
EMR Project Before Resources Added 8 -12
8 -13 EMR Project—Time Constrained Resource Usage View and Resource Loading Chart
EMR Project Network View Schedule After Resource Leveled 8 -14
EMR Project Resources Leveled 8 -15