Risk management process n Risk An uncertain event
- Slides: 18
Risk management process n Risk ¨ An uncertain event that, if it occurs, has a positive or negative effect on project objectives n Risk Management ¨A proactive attempt to recognize and manage internal events and external threats that affect the likelihood of a project’s success ISE 491 - Ch. 6 n What can go wrong (risk event) n How to minimize the risk event’s impact (consequences) n What can be done before an event occurs (anticipation) n What to do when an event occurs (contingency plans) 1
The risk event graph FIGURE 7. 1 ISE 491 - Ch. 6 2
Risk Management’s Benefits n A proactive rather than reactive approach n Reduces surprises and negative consequences n Prepares the project manager to take advantage of appropriate risks n Provides better control over the future n Improves chances of reaching project performance objectives within budget and on time ISE 491 - Ch. 6 3
The Risk Management Process ISE 491 - Ch. 6 FIGURE 7. 2 4
Managing risk n Step 1: Risk identification ¨ Generate a list of possible risks through brainstorming, problem identification and risk profiling. n n Macro risks first, then specific events Step 2: Risk assessment ¨ Scenario analysis ¨ Risk assessment matrix ¨ Failure Mode and Effects Analysis (FMEA) ¨ Probability analysis n Decision trees, NPV, and PERT ¨ Semiquantitative ISE 491 - Ch. 6 scenario analysis 5
Risk breakdown structure ISE 491 - Ch. 6 FIGURE 7. 3 6
Example: Risk Profile for a product development project FIGURE 7. 4 ISE 491 - Ch. 6 7
Impact scales FIGURE 7. 5
Risk assessment form FIGURE 7. 6 ISE 491 - Ch. 6 9
Risk severity matrix 5 Red zone (major risk) User backlash Likelihood 4 Interface problems Yellow zone (moderate risk) 3 System freezing 2 Hardware malfunction 1 1 2 3 Impact ISE 491 - Ch. 6 4 Green zone (minor risk) 5 from FIGURE 7. 7 10
Managing risk (cont’d) n Step 3: risk response development ¨ Mitigating n n risk Reducing the likelihood an adverse event will occur Reducing impact of adverse event ¨ Transferring n Paying a premium to pass the risk to another party ¨ Avoiding n risk Changing the project plan to eliminate the risk or condition ¨ Sharing n risk Allocating risk to different parties ¨ Retaining n ISE 491 - Ch. 6 risk Making a conscious decision to accept the risk 11
Contingency planning n Contingency plan ¨ An alternative plan that will be used if a possible foreseen risk event actually occurs ¨A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event n Risks of not having a contingency plan ¨ Having no plan may slow managerial response ¨ Decisions made under pressure can be potentially dangerous and costly ISE 491 - Ch. 6 12
Risk response matrix FIGURE 7. 8 ISE 491 - Ch. 6 13
Risk and contingency planning n Technical risks ¨ Backup strategies if chosen technology fails ¨ Assessing whether technical uncertainties can be resolved n Schedule risks ¨ Use of slack increases the risk of a late project finish ¨ Imposed duration dates (absolute project finish date) ¨ Compression of project schedules due to a shortened project duration date ISE 491 - Ch. 6 14
Risk and contingency planning (cont’d) n Costs risks ¨ Time/cost dependency links: costs increase when problems take longer to solve than expected. ¨ Deciding to use the schedule to solve cash flow problems should be avoided. ¨ Price protection risks (a rise in input costs) increase if the duration of a project is increased. n Funding risks ¨ Changes in the supply of funds for the project can dramatically affect the likelihood of implementation or successful completion of a project. ISE 491 - Ch. 6 15
Contingency funding and time buffers n Contingency funds ¨ Funds n to cover project risks—identified and unknown Size of funds reflects overall risk of a project ¨ Budget n reserves Are linked to the identified risks of specific work packages ¨ Management n n reserves Are large funds to be used to cover major unforeseen risks (e. g. , change in project scope) of the total project Time buffers ¨ Amounts of time used to compensate for unplanned delays in the project schedule ISE 491 - Ch. 6 16
Contingency fund estimate (000 s) TABLE 7. 1 ISE 491 - Ch. 6 17
Managing risk (cont’d) n Step 4: risk response control ¨ Risk control n Execution of the risk response strategy n Monitoring of triggering events n Initiating contingency plans n Watching for new risks ¨ Establishing a change management system n Monitoring, tracking, and reporting risk n Fostering an open organization environment n Repeating risk identification/assessment exercises n Assigning and documenting responsibility for managing risk ISE 491 - Ch. 6 18
- Risk response matrix
- Agreement the meaning of which is uncertain
- Credit risk market risk operational risk
- Is a near miss a sentinel event
- Worksheet 12-8 compound probability
- Independent event vs dependent event
- Independent event vs dependent event
- 5 ws of event management
- Newsworthy event background event source
- Newsworthy event (s) background event (s) sources
- Key risk indicators for vendor management
- Risk map
- Certain and uncertain digits
- Levy in a sentence
- Kode icd 10 oat
- Representing knowledge in an uncertain domain
- Uncertain events
- Uncertain examples
- Steps in risk management process