Resource Planning Resource Planning Estimating Schedule Activity Resource
- Slides: 21
Resource Planning
Resource Planning Estimating Schedule Activity Resource Requirements • Determining what resources will be required (labor, equipment, material) • What quantity for each resource will be required. 51 • When are resources available to perform project activities.
Resource Planning Resource Estimating Techniques • Expert Judgment – Any group or person with specialized knowledge. • Bottom-Up Estimating – Decompose activities into smaller work components. • Three Point Estimating – Optimistic, pessimistic and most likely values are determined to calculate estimate. 51
Resource Planning Resource Histogram • A bar chart showing the amount of time assigned to a resource for the time interval. • Resource availability is depicted as a line for comparison purposes. • Resources assigned more work than available hours are considered “overallocated”. 51
Resource Planning Resource Histogram 40 hrs 52 Week 8 Week 7 Week 6 Week 5 Week 4 Week 3 Week 2 Week 1 Resource Histogram
Resource Planning Resource Conflict and Balancing • Project calendar – defines the workable time periods for the project. • Resource calendar – defines the workable time periods for the specific resource. 52 • Conflicts in resource availability and schedule activity dates must be resolved to ensure the project will be completed according to accepted project objectives.
Resource Planning Resource Leveling • Schedule network analysis technique applied to a schedule model that has a critical path identified. • Schedule start and finish dates can be modified to reflect resource availability. • Identifies under-allocated resources 52
Resource Planning Resource Leveling • Different methods for resource leveling • Project Manager analyzes effects on project objectives (time and cost) for resolving resource conflict. 52
Resource Leveling Methods 1. Do Nothing if over-allocation is within acceptable limits • Schedule/Time Impact – None • Resource/Cost Impact - None 52
Resource Leveling Methods 2. Delay non-critical tasks within available float • Schedule/Time Impact – None • Resource/Cost Impact – None (except for inflation effects) 53
Resource Leveling Methods 3. Extend non-critical task durations within the available float • Schedule/Time Impact – None • Resource/Cost Impact – None (except for inflation effects) 53
Resource Leveling Methods 4. Add or substitute resource of equal or greater capability • Schedule/Time Impact – May need to consider learning curve for new resource. (Duration may shorten if resources are added – schedule crashing) • Resource/Cost Impact – Cost impact if substitute resource has higher costs 53
Resource Leveling Methods 5. Delay critical path tasks • Schedule/Time Impact – Schedule impact equal to the delay • Resource/Cost Impact – Cost impact due to project time extension and inflation costs delay 53
Resource Leveling Methods 6. Extend critical path task durations • Schedule/Time Impact – Schedule impact equal to the delay • Resource/Cost Impact – Cost impact due to project time extension and inflation costs 53 delay
Resource Leveling Methods 7. Authorize Overtime • Schedule/Time Impact – Could shorten schedule (schedule crashing) • Resource/Cost Impact – Cost impact due to premium cost rates $ 53
Resource Leveling Methods 8. Split the task into non-sequential pieces • Schedule/Time Impact – Schedule impact if part of task extends beyond float (soft logic) • Resource/Cost Impact – Cost impact due to project time extension and inflation costs and inefficiencies in splitting task 53
Resource Leveling Methods 9. Modify the scope • Schedule/Time Impact – Could shorten schedule due to less work or quality of work being accomplished • Resource/Cost Impact – Could go either way. In the short term, costs could be less due to less work, but long term costs may increase 54
Module 5 Exercise – Resource Leveling 55
Module 5 Exercise – Resource Leveling Resource Histogram 4. 0 J F 3. 0 B B E E J J C C C F E E G A A D D G G H H W 1 W 2 W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 2. 0 1. 0 55
Module 5 Exercise – Resource Leveling 55
Module 5 Exercise – Resource Leveling Resource Histogram 4. 0 3. 0 E E F J J G C C F E E J A A D D G G H H W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 B B C C C A A W 1 W 2 2. 0 1. 0 55 56
- Calculating time of death worksheet
- Activity duration estimating
- Perfect square activity
- Agile estimating and planning by mike cohn
- Kertas kerja pemeriksaan biasanya dikelompokkan dalam
- Independent activity schedule ideas
- Nec activity schedule example
- Airline schedule planning
- Activity 2 limiting reactants activity
- Activity corrections
- Aoa diagram
- Activity 1 introductory activity
- Activity 1 activity 2
- Activity 3 explore me more
- Activity 2
- Types of information system
- Rounding and estimating
- Mcaces
- Estimation of degradation function
- Gao cost estimating and assessment guide
- How to estimate decimals
- Tendering and estimating