Republic of Serbia Ministry of Construction Transport and
Republic of Serbia Ministry of Construction, Transport and Infrastructure Railway Infrastructure Projects
Characteristics of the Republic of Serbia railway network • 3739 km railway lines, from which: 1) 3444 km of single track lines 2) 295 km of double track lines • 1546 km electrified • 44% of network is designed for axel load of 22, 5 t • 872 km railway lines on Corridor X • Current maximum projected speeds 120 km/h • 334 tunnels (153 km), 956 bridges (40 km) • 2132 level crossings
Orient East Med Corridor on the territory of WB 6 Railway lines within Orient East Med Corridor: • Section: Budapest – Subotica – Beograd – Niš – Presevo - Skopje – Gevgelija – Thessaloniki • Section: Stalać – Kraljevo – Priština – General Jankovic - Skopje (Trubarevo) • Section: Beograd (Resnik) – Vrbnica Podgorica – Bar
Completed Railway Projects • Section Gilje-Cuprija-Paracin, railway line Beograd-Nis, 10, 5 km, financed by EIB IV loan, € 45, 9 mil. • Procurement of materials for six sections, 112 km, EBRD 4, € 30, 2 mil. • Three northern sections of Corridor X, 65, 7 km, financed by a loan from the Russian Federation and RS budget, $ 48, 7 mil. • Three southern sections of Corridor X (railway line Nis-Presevo), 46, 5 km, financed by a loan from the Russian Federation and RS budget, $ 37, 1 mil. • Reconstruction of the railway section Resnik - Valjevo (railway line Belgrade - Border with Montenegro), 77, 6 km, Russian Federation and RS budget, $ 72 mil. • Construction of a bridge over the Danube river in Novi Sad, financed by EU, City of Novi Sad, AP Vojvodina and RS budget, € 57, 2 mil. • Reconstruction and modernization of section Junction G-Rakovica. Resnik (Belgrade nod), 7, 5 km, financed by EBRD 5 loan, € 23, 7 mil.
Completed Railway Projects • Overhaul 271, 5 km of regional railway lines, RS budget and budget of Infrastructure Manager, € 127 mil. • Overhaul railway section Predejane-Dzep (Koridor X), 4, 5 km, budget of Infrastructure Manager, € 1, 9 mil. • Construction of railway station Belgrade Center - Prokop I (Phase 1), Kuwaiti Fund for Arab Economic Development, € 23, 7 mil. • Procurement of 27 diesel engines (DMV), Russian Federation and RS budget, $ 100 mil. • Procurement of 21 EMU, EBRD € 100 mil.
Ongoing Railway Projects ₋ Reconstruction and modernization of section Belgrade Centre-Stara Pazova (railway line Belgrade-Subotica. BCP with Hungary), 34, 5 km, financed by a loan from Chinese EXIM Bank and RS budget, $ 350, 2 mil. ₋ Construction of tunnel and viaducts on section Stara Pazova-Novi Sad (railway line Belgrade-Subotica- BCP with Hungary), 4, 2 km, financed by a loan from the Russian Federation and RS budget, $ 337, 6 mil. ₋ Reconstruction and modernization of section Stara Pazova-Novi Sad (railway line Belgrade-Subotica-BCP with Hungary), 40, 4 km, financed by a loan from the Russian Federation and RS budget, $ 247, 8 mil. Project goal: construction, modernization and reconstruction of the part of the existing railway and the construction of the new track to provide a doubletrack railway line for passenger and freight traffic for speeds of up to 200 km/h.
Ongoing and projects under preparation ₋ Reconstruction of railway line Jajinici – Mala Krsna 59 km and overhaul of station Mala Krsna , financed by EBRD loan , € 39, 3 mil. ₋ Renewal of Electrical Infrastructure, EBRD, € 3, 5 mil. ₋ Procurement of tamping machines, EBRD ₋ Procurement of track recording cars, EBRD, € 2, 2 mil. ₋ Procurement of heavy motorized railcars, EBRD, € 4, 5 mil. ₋ Procurement of Software for making timetable, EBRD ₋ Рepair and modernization of 5 multipurpose electric motor sets, EBRD, € 3, 5 mil. ₋ Procurement of new multisystem electric locomotives, EBRD, € 64 mil.
Projects Under Preparation ₋ Reconstruction and modernization of railway line Nis-Dimitrovgrad, 108 km, financed by WBIF grant, EIB loan and RS budget, € 268, 2 mil. ₋ Construction Intermodal terminal in Batajnica, IPA and RS budget ₋ Reconstruction and modernization of section Nis-Brestovac (railway line Nis. Presevo), 23 km, financed by IPA 2015 and RS budget, € 62, 7 mil. ₋ Innovation of complex railway Technical passenger station Zemun -TPS Zemun, € 47 mil. ₋ Overhaul 327, 5 km of regional railway lines, RS budget and budget of Infrastructure Manager, € 30, 7 mil.
Planned Railway Projects • Reconstruction, modernization and construction of the second track of section Novi Sad-Subotica (railway line Belgrade-Subotica-BCP with Hungary), 108, 2 km, value $ 1. 163 mil. The creditor is Chinese EXIM bank. • Reconstruction and modernization of the Belgrade-Nis railway line (remaining portion of 198 km): • Reconstruction and modernization of section Resnik-Kovacevac-Velika Plana (57, 9 km) • Reconstruction and modernization of section Velika Plana-Stalac (74 km) (IPA for technical documentation) • Reconstruction, modernization and construction of second track Stalac-Đunis (17, 5 Km) (WBIF grant for technical documentation) • Reconstruction and modernization of section Đunis - Niš (48, 64 km) (IPA for technical documentation) • Reconstruction and modernization of the sections on the railway line (Nis) Brestovac-Presevoborder with Republic of Macedonia (remaining part of 88 km) (WBIF grant for technical documentation) • Reconstruction and modernization of the double track section Stara Pazova - Golubinci-Šid-BCP with Croatia (86 km) (WBIF grant for technical documentation) • Reconstruction and modernization railway section Valjevo – Vrbnica-BCP with Montenegro (railway line Belgrade-Vrbnica-BCP with Montenegro, 209, 8 km) • Project for construction of a single operational center for managing the railway traffic on the railway network of the Republic of Serbia • Procurement of new EMU. The creditor is EBRD, € 100 mil.
Republic of Serbia Ministry of Construction, Transport and Infrastructure Thank you for your attention!