Report on 7800 S. Finished Water Pipeline Phase III – 2700 W. to Bangerter

Report on 7800 S. Finished Water Pipeline Phase III – 2700 W. to Bangerter June 8, 2011

7800 S. Phase III Engineer: CH 2 M HILL Inc. Contractor: UDOT/Condie Construction Contract

7800 S. Phase III Engineer: CH 2 M HILL Inc. Contractor: UDOT/Condie Construction Contract Award Date: November 12, 2008 Project Scope: Installation of 24 -inch and 30 -inch pipeline from 2700 West to Bangerter Highway and new vault at 3200 West. Original Contract Amount Final Contract Amount % Change from Original Amount $2, 282, 661 $2, 588, 810 13. 4%

7800 S. Phase III Change Order #3: $225, 640 Change in depth of the

7800 S. Phase III Change Order #3: $225, 640 Change in depth of the bore underneath Bangerter Highway due to conflicting utilities. Change Order #4: $2, 088 Additional potholing at Bangerter Highway. Change Order #7: $3, 175 Changes to the connection to the existing pipe at 2700 West. Change Order #12: $7, 014 Changes in the pressure rating of the pipe in the 3200 West vault and deletion of the interconnection to the old 16 -inch pipe. Change Order #17: $61, 811 Project Acceleration Costs. Change Order #20 $0 Changes to the Pipe Coating Specification

7800 S. Phase III Change Order #23: $22, 626 Utility conflicts on the 24

7800 S. Phase III Change Order #23: $22, 626 Utility conflicts on the 24 -inch and 30 -inch pipeline and changes to the vault at 3200 West. Change Order #24: $58, 825 Delay claims, traffic control credit, Bangerter jack and bore standby costs and liquidated damages.

7800 S. Phase III Jack and bore underneath Bangerter Highway 24 -inch pipe being

7800 S. Phase III Jack and bore underneath Bangerter Highway 24 -inch pipe being installed in 7800 S.

7800 S. Phase III 3200 West Vault under construction Final piece of 30 -inch

7800 S. Phase III 3200 West Vault under construction Final piece of 30 -inch pipe being installed