RENAISSANCE LYON FRANCE RENAISSANCE LYON WP 2 Progress

  • Slides: 14
Download presentation
RENAISSANCE - LYON FRANCE RENAISSANCE LYON WP 2 Progress and Plan (Year 3 -

RENAISSANCE - LYON FRANCE RENAISSANCE LYON WP 2 Progress and Plan (Year 3 - oct 07 oct 08) Christophe Ménézo A/Prof & INSA Lyon-CETHIL (Thermal Science Centre of Lyon) Christophe. menezo@insa-lyon. fr RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 1

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Planned Activities: - Platform of

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Planned Activities: - Platform of measurements of the impact of the PV on the electrical distribution networks (at INSA of Lyon) - Measurements of the impact of PV systems installed in Lyon-Confluence Area on the distribution network RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 2

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement Platform at INSA Electricity

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement Platform at INSA Electricity quality evaluation produced by standard EN 50 -160 inverter Done Site : Electrical Engineering Dpt Definition of platform objectives and design Supplier (Tenesol) RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 3

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement series led on Lyon-Confluence

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement series led on Lyon-Confluence Network Project Submission to the National Research Agency (ANR) Done Agreement between EDF R&D, INES RDI, Transénergie and INPGrenoble Contact with INSA School of Electrical Engineering Master student subject RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 4

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement Platform at INSA Electricity

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement Platform at INSA Electricity quality evaluation produced by standard EN 50 -160 inverter Definition of the measurements protocol Done Installation of the platform : 2 k. Wc Planed Installation of Practical Courses for Engineering Students of INSA M 24 -M 30 j RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 5

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement series led on Lyon-Confluence

WP 2. 1 Electrical Network RENAISSANCE - LYON FRANCE Measurement series led on Lyon-Confluence Network Constructive data-gathering of the distribution network on the Lyon-Confluence area Measurement Protocol definition with EDF R&D and INSA Waiting for construction of the buildings and Photo. Voltaic systems RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 6

WP 2. 2 Experience Feedback Monitoring ENERTECH RENAISSANCE - LYON FRANCE Planned Activities: Multiscale

WP 2. 2 Experience Feedback Monitoring ENERTECH RENAISSANCE - LYON FRANCE Planned Activities: Multiscale Monitoring - Global Monitoring - Detailed Monitoring - Localised Monitoring RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 7

WP 2. 2 Experience Feedback Monitoring RENAISSANCE - LYON FRANCE Global Monitoring (promoters and

WP 2. 2 Experience Feedback Monitoring RENAISSANCE - LYON FRANCE Global Monitoring (promoters and dealers) - Counting and sub-counting heating room and sub-station and Solar Domestic Hot Water - Counting and under counting electricity in building Detailed Monitoring (Enertech) - By housing - Followed Consumption: Cooking, lighting, washing machine - Followed thermal evolution Localised Monitoring (INSA-CETHIL) - Some residences which have been numerically modeled ! Inhabitants ! RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 8

WP 2. 2 Experience Feedback Monitoring RENAISSANCE - LYON FRANCE Detailed Monitoring (Enertech) :

WP 2. 2 Experience Feedback Monitoring RENAISSANCE - LYON FRANCE Detailed Monitoring (Enertech) : expected results (such as in Restart Project) - Thermal Confort Human thermal gain Apartment Electricity Use Domestic Hot Water distribution Cooking Common Electricity Use RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 9

WP 2. 2 Experience Feedback Monitoring RENAISSANCE - LYON FRANCE Tests of sensors accuracy

WP 2. 2 Experience Feedback Monitoring RENAISSANCE - LYON FRANCE Tests of sensors accuracy (INSA-CETHIL) Wireless sensors MINIBAT RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 10

WP 2. 3 European Highlight RENAISSANCE - LYON FRANCE State of progress year 3:

WP 2. 3 European Highlight RENAISSANCE - LYON FRANCE State of progress year 3: 6 first months - Monitoring strategy principles defined -but not fully planed at the moment (contributions of actors Enertch-INSACETHIL-promotors-futur inhabitants, what as to be focused ventilation rate, energy performance of systems (envelop air tightness), apartment behavior (thermal comfort)) - Actually difficult to highlight Monitoring strategy Has to be fixed at a very short term RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 11

WP 2. 3 European Highlight RENAISSANCE - LYON FRANCE Analysis of progress - Strong

WP 2. 3 European Highlight RENAISSANCE - LYON FRANCE Analysis of progress - Strong points : Zaragosa and Lyon not in phase - Experiences of Zaragosa not highlighted enough for Lyon - Networking opportunities should be much more used (webcam exchange for regular exchange for specific topics (focus), …) RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 12

WP 2. 3 European Highlight RENAISSANCE - LYON FRANCE Plans for the next 6

WP 2. 3 European Highlight RENAISSANCE - LYON FRANCE Plans for the next 6 months (end of year 3) - Lyon strategy complete definition and planning of phases Comparison with Zaragossa - Common identification of what has to be highlight ? Identification of strong/weak points on each side? Definition of a monitoring strategy referential? -Key events … INSA-CETHIL organize IBPSA France - Nov. 2008 RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 13

RENAISSANCE - LYON FRANCE ENERTECH WP leader contact ENERTECH WP 2 Olivier Sidler@club-internet. fr

RENAISSANCE - LYON FRANCE ENERTECH WP leader contact ENERTECH WP 2 Olivier Sidler@club-internet. fr RENAISSANCE : a CONCERTO project financed by the European Commission on the six framework program 14