Project Scheduling Lagging Crashing and Activity Networks Chapter

  • Slides: 15
Download presentation
Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 © 2007 Pearson Education

Project Scheduling: Lagging, Crashing and Activity Networks Chapter 10 © 2007 Pearson Education

Lags in Precedence Relationships The logical relationship between the start and finish of one

Lags in Precedence Relationships The logical relationship between the start and finish of one activity and the start and finish of another activity. Four logical relationships between tasks 1. Finish to Start 2. Finish to Finish 3. Start to Start 4. Start to Finish

Finish to Start Lag • • Most common type of sequencing Shown on the

Finish to Start Lag • • Most common type of sequencing Shown on the line joining the modes – Added during forward pass – Subtracted during backward pass 0 A 6 Spec Design 6 6 B 11 Design Check 5 ot n is s g la e a k s i Th e sam slac th ivity act 15 C 22 Lag 4 Blueprinting 7

Finish to Finish Lag Two activities share a similar completion point – The mechanical

Finish to Finish Lag Two activities share a similar completion point – The mechanical inspection cannot happen until wiring, plumbing, and HVAC installation are complete 15 D 21 Wiring 6 10 A 16 Plumbing 6 Lag 3 16 B 21 HVAC 5 21 C 22 Inspection 1

Start to Start Lag 30 Logic must be maintained by both forward and backward

Start to Start Lag 30 Logic must be maintained by both forward and backward pas s D 36 Wiring 6 Lag 3 31 A 33 Plumbing 6 33 B 36 HVAC 5 36 C 37 Inspection 1

Start to Finish Lag • 30 D 36 Wiring 6 • Least common type

Start to Finish Lag • 30 D 36 Wiring 6 • Least common type of lag relationship Successor’s finish dependent on predecessor’s start Lag 3 28 22 A 28 Plumbing 6 B 33 HVAC 5 33 C 34 Inspection 1

Gantt Charts ü Establish a time-phased network ü Can be used as a tracking

Gantt Charts ü Establish a time-phased network ü Can be used as a tracking tool Benefits of Gantt charts 1. Easy to create and comprehend 2. Identify the schedule baseline network 3. Allow for updating and control 4. Identify resource needs

Create a Gantt chart based on the activities listed in the table. Task Time

Create a Gantt chart based on the activities listed in the table. Task Time Pred Z 8 -- U 3 W Y 5 Z T 6 V X 8 Z S 7 U, T W 4 Y, X R 9 S V 5 W

Gantt Chart With Resources in MS Project

Gantt Chart With Resources in MS Project

Crashing Projects Accelerating a project by committing more resources than initially planned Principal methods

Crashing Projects Accelerating a project by committing more resources than initially planned Principal methods for crashing Ø Improving existing resources’ productivity Ø Changing work methods Ø Increasing the quantity of resources

Managerial Considerations • Determine activity fixed and variable costs • The crash point is

Managerial Considerations • Determine activity fixed and variable costs • The crash point is the fully expedited activity • Optimize time-cost tradeoffs • Shorten activities on the critical path • Cease crashing when – the target completion time is reached – the crash cost exceeds the penalty cost

What is the lowest cost to complete this project in 53 weeks? Times are

What is the lowest cost to complete this project in 53 weeks? Times are in weeks and costs in dollars. Activity Pred A B C D E F G H -A A B, C D D E, F G Normal Time 14 5 10 8 6 9 7 15 Min Time 9 2 8 5 5 6 4 11 Normal Cost 500 1000 2000 1600 1500 600 1600 Crash Cost 1500 1600 2900 2500 1900 3000 1800 3600

Activity on Arrow Networks ü Activities represented by arrows ü Widely used in construction

Activity on Arrow Networks ü Activities represented by arrows ü Widely used in construction ü Event nodes easy to flag ü Forward and backward pass logic similar to AON ü Two activities may not begin and end at common nodes ü Dummy activities may be required

1. Use AOA to sketch the network that represents the project as described in

1. Use AOA to sketch the network that represents the project as described in the table. 2. Calculate early and late start and finish times for all activities. Activity A B C Time 4 2 10 Pred -A A Activity F G H Time 4 15 7 Pred D D E, F, G D E 3 15 B, C B K 11 G

Controversies in the Use of Networks v Networks can be too complex v Poor

Controversies in the Use of Networks v Networks can be too complex v Poor network construction creates problems v Networks may be used inappropriately v When employing subcontractors – The master network must be available to them – All sub-networks must use common methods v Positive bias exists in PERT networks