Project Name Testing Iteration 1 UAT Kickoff Contents
- Slides: 18
Project Name - Testing Iteration 1 UAT Kick-off
Contents 2 § Iteration 1 Overview § Testing Plan § Defect Management Process § SAP Functionality Overview § Iteration 1 UAT Logistics Copyright © 2014 Deloitte Development LLC. All rights reserved.
Iteration 1 Overview § Iteration 1 consists of 43 user stories § Out of 43, 17 are functional & 23 are data user stories § Campaign type “Auto Pay” would be run as part of the campaign execution process 3 Copyright © 2014 Deloitte Development LLC. All rights reserved.
CCM Test Metrics / Communications Weekly View For the foundational release, there are two proposed types of testing communications: 4 § Defect Management Meetings (Daily at TBD) § Internal Deloitte team meeting § Defect Management Reports (Daily at TBD ) § Published externally to our clients Copyright © 2014 Deloitte Development LLC. All rights reserved.
Defect Management Meetings Purpose • Review new defects • Identify appropriate developer for triage • Receive status update on defects in development and defects that failed re-test • Identify next steps to achieve a fix • Determine estimated fix date based on priority / severity • Identify items that are being handed back and forth, requiring escalation to testing leadership • Determine if escalation is needed for high severity or high aging defects, and subsequently work with Test Governance Lead to address Meeting Format • Facilitator to walk through open defect export from CCM Test project in Quality Center • Defect ID • Severity • Developer Assigned • Status • Summary • Comments • Developers to make real-time updates to defects in Quality Center Required Fields When Opening a Defect Proposed Facilitator • Defect Managers Proposed Attendees • Developers • Defect Manager • Test Managers • Test Data Manager • Test Governance Lead (optional) Proposed Timing • Daily • 1 hour 5 Copyright © 2014 Deloitte Development LLC. All rights reserved.
Test Execution Process 6 Actor Involved 1 Approved test cases and steps uploaded to Quality Center through upload template Test Managers Test Governance Lead 2 Test cases are assigned a planned execution date and responsible tester in the test execution schedule Test Managers 3 Testers determine which test cases are assigned to them based on the execution schedule Testers 4 Testers work with Test Manager to get any necessary data, preconditions, etc. prior to running the tests 5 Testers execute tests 6 Test Manager pulls test execution reports at the end of each day 7 Test Governance Lead compiles and publishes reports Testers Test Managers Test Governance Leads Copyright © 2014 Deloitte Development LLC. All rights reserved.
Roles and Responsibilities Role Type Name Governance Test Managers Test Authors Testers Defect Manager Environment Manager Test Data Manager 7 Copyright © 2014 Deloitte Development LLC. All rights reserved.
Defect Management Process The defect management process is as follows: Defect Management Process Tester Defect Manager Developer 8 Executes test case Test Case Passes? Yes Indicates step as passed No Logs a defect with supporting details Executes retest group Assigns it to Appropriate person Assigns back to tester Test Case Passes? Yes Closes defect No Assigns defect back to developer Receives defect assignment Developer fixes the code and assigns it back to defect manager Copyright © 2014 Deloitte Development LLC. All rights reserved.
Iteration 1 UAT Logistics 9 § All test cases should be executed directly into Quality Center § Test cases should not be executed in offline tools and later “mass updated” in Quality Center, as all metrics / reporting will be based real-time out of Quality Center § If you have issues accessing Quality Center, please reach out to Name/Email to determine an alternate testing approach § Defects should be created directly from failed test steps within test cases and linked accordingly § This will show the correlation between failed test cases and defects § If a test step is Blocked, it should also be linked back to a defect § This will show the correlation between blocked test cases and defects § If there is an environment outage preventing testing, please notify Name / Email immediately § Testing resources should follow the guidelines listed in this presentation when it comes to Defect Severity, Test Case Status, processes, etc. § For any issues with accessing and setting up Quality Center, please contact Name / Email § If there are questions about specific processes within Quality Center (what a mandatory / optional field means and how /when it should be used, etc. ) testing resources will contact the Testing Lead, Name / Email Copyright © 2014 Deloitte Development LLC. All rights reserved.
Defect Severity Guidelines Defects will be categorized as follows: Severity 5. Urgent Definition Very severe § § § Entire application, component, or function will not work Client, system or environment is unavailable. No work-around available Severe data loss or corruption Data integrity issue related to security, confidentiality, legal, or regulatory non-compliance Client X definition: Major functionality not working or blocking defect Intermittent defects that result in any of the above are also classified as Urgent. 4. Very High Significant § § Entire application, component or function will not work. A work-around is available Corruption of a critical component Loss of a non-critical component Client X definition: Major functionality not working but there is a workaround or normal functionality not working and the user is unable to proceed with this feature Intermittent defects that result in any of the above are also classified as Very High. 3. High Result is not as expected § Corruption of a non-critical component. A work-around is available § Low impact to the end user or application § Client X definition: Non-essential functionality not working but with correct inputs the user is still able to proceed. Intermittent defects that result in any of the above are also classified as High. 2. Medium Minor defect § Some of the application operations are unexpected § Client X definition: Minor functionality not working - usually cosmetic or screen display Intermittent defects with low impact to the business operations or end users. 1. Low 10 Cosmetic issues or some functionality unavailable but has a simple workaround. Copyright © 2014 Deloitte Development LLC. All rights reserved.
Defect Priority Guidelines Defects will be categorized as follows: Priority 11 Definition Acknowledgement Time 5. Urgent § § Must be fixed immediately Requires notification of responsible executive Requires customer notification and daily follow-up Does not meet Definition of Done if any Critical defect is open 30 minutes 4. Very High Must be included in the next Iteration Requires notification of manager Requires customer notification and weekly follow-up Does not meet Definition of Done if any Serious defect is open 1 hour 3. High § § 2. Medium § Must be scheduled in the next 2 -3 Iterations 2 hours 1. Low § Schedule when time is available 4 hours Copyright © 2014 Deloitte Development LLC. All rights reserved.
Defect and Re-test Assignment Work stream SAP CRM Testers Primary Developer(s) TBD TBD TBD ADT 12 TBD Copyright © 2014 Deloitte Development LLC. All rights reserved.
Test Case Status Definitions Status No Run Test has not undergone its first run and is not blocked Passed Actual results match expected results for each step in the test case Failed Actual results deviate from expected results for at least one step in the test case Blocked Not Complete N/A 13 Definition At least one step is unable to be run due to an existing open defect(s) Test is in progress but not all steps have been executed Test has been descoped Copyright © 2014 Deloitte Development LLC. All rights reserved.
Test Ground Rules § All test cases should be executed directly into Quality Center § Test cases should not be executed in offline tools and later “mass updated” in Quality Center, as all metrics / reporting will be based real-time out of Quality Center § If you have issues accessing Quality Center, please reach out to Name / Email to determine an alternate testing approach § Defects should be created directly from failed test steps within test cases and linked accordingly § This will show the correlation between failed test cases and defects § If a test step is Blocked, it should also be linked back to a defect § This will show the correlation between blocked test cases and defects § If there is an environment outage preventing testing, please notify Name / Email immediately § Testing resources should follow the guidelines listed in this presentation when it comes to Defect Severity, Test Case Status, processes, etc. § § For any issues with accessing and setting up Quality Center, please contact Name / Email If there are questions about CCM specific processes within Quality Center (what a mandatory / optional field means and how /when it should be used, etc. ) testing resources will contact the Testing Lead, Name / Email 14 Copyright © 2014 Deloitte Development LLC. All rights reserved.
Test Progress Example Overall Testing Progress Summary Statement 15 Test Planning - Summary Test Planning - Progress Test Execution - Summary Test Execution - Progress Copyright © 2014 Deloitte Development LLC. All rights reserved.
Defects Summary Example Defects Summary Statement Defects - Progress Defects - Summary Defects Pending SAP CRM RTOM 164 16 Sev 1 Sev 2 Sev 3 Sev 4 16 Copyright © 2014 Deloitte Development LLC. All rights reserved.
Priority 1 Outstanding Defects Priority 1 Defects Summary Statement Defect ID 17 Defect Summary Defect Severity Team Assigned Rationale Days Open Copyright © 2014 Deloitte Development LLC. All rights reserved.
Use Cases Execution Example Use Cases (Requirements) Summary Statement Use Cases - Summary Use Cases - Progress Considerations and Issues 18 Copyright © 2014 Deloitte Development LLC. All rights reserved.
- Uat kickoff
- Kick off meeting script
- Qa vs uat testing
- "original software" uat or "user acceptance testing"
- Project kickoff presentation
- Modern project profiles in spm
- Name
- Table of contents in project proposal
- Agile inception planning
- Meeting objective
- Circle k #45067
- Kickoff o que é
- Kickoff drills
- Proposal kickoff meeting agenda
- Design kickoff meeting
- Fast kickoff training code
- Kickoff meting
- Kickoff projet
- Circle k #45067