Project Management Life Cycle The Project Management Life
- Slides: 25
Project Management Life Cycle The Project Management Life Cycle SD OV # - 1 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Management Life Cycle Progression of Risk SD OV # - 2 Copyright © 2000 Element K Content LLC. All rights reserved.
Setting Up for Success Three Factors of Success SD OV # - 3 Copyright © 2000 Element K Content LLC. All rights reserved.
Setting Up for Success Initiation Phase of the Project Management Life Cycle SD OV # - 4 Copyright © 2000 Element K Content LLC. All rights reserved.
The Project Team Membership during Project Management Life Cycle SD OV # - 5 Copyright © 2000 Element K Content LLC. All rights reserved.
The Project Team Matrixed Organization Chart SD OV # - 6 Copyright © 2000 Element K Content LLC. All rights reserved.
The Project Team Building Flow Chart SD OV # - 7 Copyright © 2000 Element K Content LLC. All rights reserved.
Risk Management Sources of Risk SD OV # - 8 Copyright © 2000 Element K Content LLC. All rights reserved.
Risk Management Risk Prioritization Chart SD OV # - 9 Copyright © 2000 Element K Content LLC. All rights reserved.
Risk Management Approaches • Avoid It – work around so risk never occurs • Accept It – live with the consequences • Transfer It – share the risk • Mitigate It SD – prepare through contingency planning OV # - 10 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Plans Vocabulary Moment – Work Breakdown Structure (WBS): • Chart breakdown of milestones and tasks that must be accomplished in a project – Work Packages: • Detailed tasks, used in assigning, estimating, scheduling, and controlling project work SD OV # - 11 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Plans Work Breakdown Structure (Hierarchy Format) SD OV # - 12 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Plans Vocabulary Moment – Network Logic Diagram: • Scheduling tool that displays interrelationships among project work packages SD OV # - 13 Copyright © 2000 Element K Content LLC. All rights reserved.
The Project Schedule Network Logic Diagram SD OV # - 14 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Bar Chart of Actual versus Estimated Costs SD OV # - 15 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Variables in Earned Value Analysis – Budgeted Cost for Work Scheduled (BCWS): • The amount you budget for a task between its start date and today Example: • You expected a task to take 10 days and cost $1, 000 • Today is day 3 • The BCWS on day 3 = $300 SD OV # - 16 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Variables in Earned Value Analysis – Budgeted Cost for Work Performed (BCWP): • The percentage of the task budget that corresponds to the task’s completion status • Also known as Earned Value Example: • The $1, 000 task is only 10% complete on day 3 • The BCWP = $100 SD OV # - 17 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Variables in Earned Value Analysis – Actual Cost for Work Performed (ACWP): • The actual cost of the task so far Example: • You have spent $500 of your $1, 000 by day 3 • The ACWP = $500 SD OV # - 18 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Earned Value Calculations – To calculate variances that show the interrelation between cost and schedule: Acronym Variance Calculations CV Cost Variance BCWP — ACWP SV Schedule Variance BCWP — BCWS SD OV # - 19 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Earned Value Calculations – To calculate both cost and schedule variances in terms of percentages: Acronym Variance Calculations CVP Cost Variance Percentage CV BCWP • divides cost variance by budgeted cost • negative value means a cost overrun SVP SD Schedule Variance Percentage SV BCWS • divides schedule variance by budgeted cost to date • negative value means the work is behind schedule OV # - 20 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Tracking and Control Earned Value Calculations – To calculate the result of variance trends over time: Acronym Variance Calculations EAC Estimate at Completion (Original Cost ACWP) ÷ BCWP • Recalculates the cost or completion date based on performance to date SD OV # - 21 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Reports Reporting Format: Bar Chart • Visually summarizes and highlights key points • Can be used to show progress to-date • Can be used to display simple variance data SD OV # - 22 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Reports Reporting Format: Table • Itemizes information • Allows readers to pick out specific data points easily SD OV # - 23 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Reports Reporting Format: S-Curves • Visually displays interrelationships between 2 different types of data (for example, cost and time) • Useful for showing cumulative data and forecasting trends SD OV # - 24 Copyright © 2000 Element K Content LLC. All rights reserved.
Project Close-Out Phase of the Project Management Life Cycle SD OV # - 25 Copyright © 2000 Element K Content LLC. All rights reserved.
- Life cycle phases in software project management
- Traditional project management vs modern project management
- Life cycle of a small to medium star
- Project cycle management ngo
- Plc project management
- Capital project life cycle
- Investment phase of project development cycle
- E governance project life cycle
- Organizational influences and project life cycle
- Adaptive project life cycle
- In the refrigerator
- Project audit life cycle
- Project termination steps
- Objective of project audit
- Frog life cycle project
- Project life cycle
- Diagram of project life cycle
- Nasa project life-cycle process flow poster
- What is the life cycle of a star
- Hát kết hợp bộ gõ cơ thể
- Ng-html
- Bổ thể
- Tỉ lệ cơ thể trẻ em
- Voi kéo gỗ như thế nào
- Chụp phim tư thế worms-breton
- Chúa yêu trần thế alleluia