Project Execution Plan PEP for the SKA Preconstruction

  • Slides: 24
Download presentation
Project Execution Plan (PEP) for the SKA Pre-construction Phase Aus-NZ Networking workshop Perth, 25

Project Execution Plan (PEP) for the SKA Pre-construction Phase Aus-NZ Networking workshop Perth, 25 Nov 2011 Dr Carole Jackson, CSIRO Astronomy and Space Science

From today. . . ASKAP = one SKA Precursor 36 dish array; 6 km

From today. . . ASKAP = one SKA Precursor 36 dish array; 6 km extent Single receiver technology (PAF) $150 M Build (2010)

From today. . . to the SKA 1000’s dish array; 1000’s km extent Multiple

From today. . . to the SKA 1000’s dish array; 1000’s km extent Multiple receiver technologies & receptor arrays EUR 1. 5 B start build 2016 ASKAP = one SKA Precursor 36 dish array; 6 km extent Single receiver technology (PAF) $150 M Build (2010)

SKA Schedule Technical 2008 -12 2013 -15 2016 -19 2018 -23 2020 2024 Telescope

SKA Schedule Technical 2008 -12 2013 -15 2016 -19 2018 -23 2020 2024 Telescope system design and cost (Prep. SKA/precursors) detailed design in the pre-construction phase (PEP) Phase 1 construction Phase 2 construction Science operations with Phase 1 Science operations with Phase 2 Programmatic 2011 Approve funding for pre-construction (PEP) phase - DONE Establish SKA organisation as a legal entity – December 2011 Select location for SKA Project Office -> JBO DONE, build progressing! 2012 Site selection (29 Feb 2012) 2014 Approve construction funding for Phase 1 (350 M€, 2007) 2018 Approve construction funding for Phase 2 (1. 2 B€, 2007) CSIRO Confidential

What’s happening now? Between now and January 2012: -> The SPDO will become the

What’s happening now? Between now and January 2012: -> The SPDO will become the (legal) SKA Project Office (SPO) • Interim Director-General (Michiel van Haarlem ex-ASTRON) • SPO has management & system authority for the whole project • SPO will oversee the global effort – largely via Work Package Consortia (i. e. Participating Organisations + Industry) • The baseline plan for the Pre-construction phase is the PEP (2012 – end 2015 -> ready to build) • Funding for the PEP is essentially ‘national’ – with some contracts possibly emanating from the SPO

SKA Ltd

SKA Ltd

Goals of the Pre-Construction Phase Jan 2012 – Dec 2015 1. Get the SKA

Goals of the Pre-Construction Phase Jan 2012 – Dec 2015 1. Get the SKA design to Production Readiness Review stage and let contracts for construction of major sub-systems 2. Progress infrastructure roll-out on the selected site to allow subsystems to be deployed 3. Mature the SKA legal entity into an organisation capable of carrying out the construction, verification, and operation of the telescope Preconstruction phase; build on work in Prep. SKA and Precursors Phase end = ‘ready to build’ the SKA CSIRO Confidential

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Concept Designs

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Concept Designs & SKA Precursors CSIRO Confidential 2012 -2015 SKA build Phase I SKA build Phase 2 2016 2018

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Concept designs

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Concept designs & SKA Precursors 2012 -2015 Plan for PEP Stage 1 CSIRO Confidential Jun 12 – June 13 Jun 13 - Dec 15 PEP Stage 1 work delivery PEP WP Stage 2 delivery Contracts SKA build Phase I SKA build Phase 2 2016 2018

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs.

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs. . . . SKA Precursors 2012 -2015 Jun 12 – June 13 Plan for PEP Stage 1 work delivery SPDO-led working groups all SKA-interested parties Institutes, industry. . . can be involved; Nov 11 – Mar 12 CSIRO Confidential SKA build Phase I SKA build Phase 2 2016 2018

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs.

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs. . . . SKA Precursors 2012 -2015 SKA build Phase I SKA build Phase 2 2016 2018 Jun 12 – June 13 Plan for PEP Stage 1 work delivery SPDO-led working groups all SKA-interested parties Institutes, industry. . . can be involved; Nov 11 – Mar 12 Stage 1 work packages will be awarded via ‘bids’ from Consortia (bid process ~May 2012, award of Stage 1 work ~July 2012) Aus-NZ partners form consortia ready for Stage 1 bidding CSIRO Confidential

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs.

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs. . . . SKA Precursors 2012 -2015 SKA build Phase I SKA build Phase 2 2016 2018 Jun 13 - Dec 15 Plan for PEP Stage 1 work delivery PEP WP Stage 2 delivery Contracts Stage 1 PEP work includes planning for Stage 2 (the major prototyping work phase) CSIRO Confidential Stage 2 PEP work contracts awarded second half of 2013

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs.

SKA Pre-construction Phase Pre-Construction PEP NOW 2011 SKA R&D foundation Studies -> Co. DRs. . . . SKA Precursors 2012 -2015 SKA build Phase I SKA build Phase 2 2016 2018 Jun 13 - Dec 15 Plan for PEP Stage 1 work delivery PEP WP Stage 2 delivery Contracts End of Stage 2 = ‘ready to build SKA Phase I CSIRO Confidential

SKA PEP Phase Work Packages 1. 2. 3. 4. Management (SPO) System Science Maintenance

SKA PEP Phase Work Packages 1. 2. 3. 4. Management (SPO) System Science Maintenance and support /Operations Plan 5. Dish Array 6. Aperture arrays 7. Signal transport & networks 8. (Digital) Signal processing 9. Computing & software 10. Power 11. Site preparation CSIRO Confidential

Work Package Allocation CSIRO Confidential

Work Package Allocation CSIRO Confidential

Aus-NZ Networking workshop 0915 – 0930 ASKAP and SKA infrastructure (Shaun Amy, CSIRO) 0930

Aus-NZ Networking workshop 0915 – 0930 ASKAP and SKA infrastructure (Shaun Amy, CSIRO) 0930 – 0945 Networking for SKA: the scope of the system (Charles Smith/ Peter Elford, Cisco & CSIRO) 0945 – 1000 Networking work package – setting the SKA baselines (Neil Marston, CSIRO) 1000 – 1020 Coffee 1020 – 1145 Discussion; baseline issues; Chair Peter Elford (Cisco) 1145 – 1200 Workshop summary (Sarah Pearce, CSIRO)

Dr Carole Jackson carole. jackson@csiro. au CSIRO Astronomy & Space Science Web: www. atnf.

Dr Carole Jackson carole. jackson@csiro. au CSIRO Astronomy & Space Science Web: www. atnf. csiro. au www. csiro. au/org/CASS. html Thank you Contact Us Phone: 1300 363 400 or +61 3 9545 2176 Email: enquiries@csiro. au Web: www. csiro. au

CSIRO Confidential

CSIRO Confidential

Context of Pre-Construction Phase

Context of Pre-Construction Phase

SKA sub-system overview All SKA sub-systems are to progress through this process 2011 2012

SKA sub-system overview All SKA sub-systems are to progress through this process 2011 2012 2014 With a narrowing of # options during development of SKA 1 ready SKA 2 ready

CSIRO Confidential

CSIRO Confidential

WP 7. 1 – Engineering and Management Within the SPO both management and engineering

WP 7. 1 – Engineering and Management Within the SPO both management and engineering resources are allocated to this task. The SPO team comprises a Technical Project Manager, System Engineer and Engineers. WP 7. 2 – Preliminary Design For all the subsystems: Complete SKA 1 preliminary design phase Conduct SKA 1 preliminary design review Completion and auditing of documentation Subsystems for review in this phase include: Dish cabling Digital data back haul LO and timing M+C network Fibre Network Infrastructure connection schematic delivered CSIRO Confidential

WP 7. 3 – Network Infrastructure This work will include leadership and coordination of

WP 7. 3 – Network Infrastructure This work will include leadership and coordination of the network infrastructure task, including review of plans and designs. The integration of site information and network infrastructure designs are included in this task as well as the preparation of the procurement datapacks. There will be some preparatory work on plans to manage the ‘as built’ network and test results. WP 7. 4 – Digital Data Backhaul This work will include the detailed definition and monitoring of interfaces, review of designs and the completion of procurement ready datapacks. Prototype systems will be constructed and test software/firmware developed, if applicable. CSIRO Confidential

WP 7. 5 – Synchronisation This work will include the detailed definition and monitoring

WP 7. 5 – Synchronisation This work will include the detailed definition and monitoring of interfaces, review of designs and the completion of procurement ready datapacks. Prototype systems will be constructed and test software/firmware developed, if applicable. WP 7. 6 – M&C Networks (Physical Layer) This work will include the detailed definition and monitoring of interfaces, review of designs and the completion of procurement ready datapacks. Prototype systems will be constructed and test software/firmware developed, if applicable. WP 7. 7 – Antenna Networks This work will include the detailed definition and monitoring of interfaces, review of designs and the completion of procurement ready datapacks. Prototype systems will be constructed and test software/firmware developed, if applicable. WP 7. 8 – Central Facility Interconnects In this task a central facilities fibre network cabling and routing plan will be developed. Work will include the detailed definition and monitoring of interfaces, review of designs and the completion of procurement ready datapacks. WP 7. 9 – Imaging Distribution This work will include the detailed definition and monitoring of interfaces, review of designs and the completion of procurement ready datapacks. Prototype systems will be constructed and test software/firmware developed, if applicable. CSIRO Confidential