Progress On TRD Gas System AMS TIM at

  • Slides: 27
Download presentation
Progress On TRD Gas System AMS TIM at CERN TRD Splinter Meeting July 27,

Progress On TRD Gas System AMS TIM at CERN TRD Splinter Meeting July 27, 2005 Martina Green July 27 2005 Martina Green 1

Schematic of the AMS-TRD gas system. All pressures are at 25 C. Box S

Schematic of the AMS-TRD gas system. All pressures are at 25 C. Box S Manifolds Box C Xe 1550 psia Mixing Vessel D 200 psia 17. 6 -20. 4 psia TRD 300 Liters CO 2 940 psia July 27 2005 Martina Green 2

Box S Sub-assemblies July 27 2005 Martina Green 3

Box S Sub-assemblies July 27 2005 Martina Green 3

Box S Pressure Relief Valve July 27 2005 Martina Green 4

Box S Pressure Relief Valve July 27 2005 Martina Green 4

Status of Flight Module • CO 2 and Xe vessels and bosses (Ardé): ready

Status of Flight Module • CO 2 and Xe vessels and bosses (Ardé): ready • Burst disks (BS & B Safety Systems): in hand @ MIT • Relief valves for Box S (Marotta): in hand @ MIT • Flight qualified cables (Glenair): In hand @ MIT • Brackets for Fill/Vent/Tower valves: CERN MIT • Three Sub-assy. pre-assemb. MIT Ardé (05/2005) July 27 2005 Martina Green 5

Preassembled Flight Sub-assemblies 2 -Valve GP 50 July 27 2005 Martina Green 6

Preassembled Flight Sub-assemblies 2 -Valve GP 50 July 27 2005 Martina Green 6

Preassembled Flight Sub-assemblies 2 -Valve Filter July 27 2005 Martina Green 7

Preassembled Flight Sub-assemblies 2 -Valve Filter July 27 2005 Martina Green 7

Preassembled Flight Sub-assemblies 4 -Valve July 27 2005 Martina Green 8

Preassembled Flight Sub-assemblies 4 -Valve July 27 2005 Martina Green 8

Box S Sub-assemblies Box S July 27 2005 Martina Green 9

Box S Sub-assemblies Box S July 27 2005 Martina Green 9

Arde Production Schedule August July 27 2005 Martina Green December 10

Arde Production Schedule August July 27 2005 Martina Green December 10

Box S - Mounting Platform • Completed Arde (07/2005) Box S Mounting Platform Shipping

Box S - Mounting Platform • Completed Arde (07/2005) Box S Mounting Platform Shipping Unit July 27 2005 Martina Green 11

Open Issues with Flight Module • Vessels heaters • Foil or stick : waiting

Open Issues with Flight Module • Vessels heaters • Foil or stick : waiting for Arde’s feedback • Installation: Arde or MIT • Thermostats: Thermostats to be finalized & ordered • TRD heaters: Power? (UB’s details) • Xe/CO 2 vessesl: Fill Location & Procedure • Arde Contract: Subcontract? July 27 2005 Martina Green 12

Box S EM - Previous Status • Passed vibration test at ENSA (12/2003) •

Box S EM - Previous Status • Passed vibration test at ENSA (12/2003) • Reduced 1 st Buffer Vol (10/2004) CO 2: 15 5 c. c. Xe: 30 15 c. c. • Box S + Box C MIT: cabling/manual tests (11/04) • D-Vessel: D-Vessel added a ss tube w/1 -mm holes (11/2004) July 27 2005 Martina Green 13

Mixing Vessel Modification July 27 2005 S. S. Tube: with 1 mm holes Martina

Mixing Vessel Modification July 27 2005 S. S. Tube: with 1 mm holes Martina Green 14

Progress of Box S – EM at MIT • Portable clean room: perform manual

Progress of Box S – EM at MIT • Portable clean room: perform manual tests • Ardé visited MIT: (02/2005) • Visits of INFN-Rome & A. Lebedev @ MIT (03/2005) • updated w/ flight module USCM (Lebedev) • new gas mixing software (Rome & Lebedev) • tested & evaluated software • CO 2 & Xe transfers tests: validate buffer volume July 27 2005 Martina Green 15

CO 2 Fill in Vessel D July 27 2005 Martina Green 16

CO 2 Fill in Vessel D July 27 2005 Martina Green 16

Xe Fill in Vessel D July 27 2005 Martina Green 17

Xe Fill in Vessel D July 27 2005 Martina Green 17

CO 2 – Xe Transfer from Vessel D to Box C July 27 2005

CO 2 – Xe Transfer from Vessel D to Box C July 27 2005 Martina Green 18

EM 10 -day Xe/CO 2 life cycle Study • Xe/CO 2 1% Flight mass

EM 10 -day Xe/CO 2 life cycle Study • Xe/CO 2 1% Flight mass – completed Xe (13. 4 mole/L): 27. 5 L, 48. 5 kg 300 m. L, 500 g CO 2 (9. 9 mole/L): 13. 3 L, 5. 8 kg 150 m. L, 65 g CO 2 July 27 2005 Xe Martina Green 19

High Pressure CO 2 Fill Setup July 27 2005 Martina Green 20

High Pressure CO 2 Fill Setup July 27 2005 Martina Green 20

High Pressure Xe Fill Setup July 27 2005 Martina Green 21

High Pressure Xe Fill Setup July 27 2005 Martina Green 21

10 -Day Life Cycle Study Result July 27 2005 Martina Green 22

10 -Day Life Cycle Study Result July 27 2005 Martina Green 22

Current TRD Progress • EM of Box S + C Rome (electronic integ. 07/2005)

Current TRD Progress • EM of Box S + C Rome (electronic integ. 07/2005) • Xe & CO 2 vessel fill procedure: MIT/Linde • Box C (Flight): being fabricated (G. Rybka) • Rest of Box S components Arde ~08/05) July 27 2005 Martina Green 23

Phase II Safety Data • Pressure System Table: No open issues • Other safety

Phase II Safety Data • Pressure System Table: No open issues • Other safety requests fulfilled: • Fill/Drain of S, C & M - locations & procedures • Vessel fill port seal cap - design/drawing • CO 2 freezing issue – detailed writeup to follow • Radiation Hazard Report request • New monitor tube design & location • Fe 55 loading July 27 2005 Martina Green 24

Monitor Tube Location July 27 2005 Martina Green 25

Monitor Tube Location July 27 2005 Martina Green 25

Monitor Tube – New Design July 27 2005 Martina Green 26

Monitor Tube – New Design July 27 2005 Martina Green 26

Quantity of Fe 55 Loading July 27 2005 Martina Green 27

Quantity of Fe 55 Loading July 27 2005 Martina Green 27