Production and Operations Management The Sharon Construction Corporation

  • Slides: 18
Download presentation
Production and Operations Management The Sharon Construction Corporation Case

Production and Operations Management The Sharon Construction Corporation Case

TEAM 07 Christina Danver Ben Gumpert Adan Montoya Gurinder Virdi

TEAM 07 Christina Danver Ben Gumpert Adan Montoya Gurinder Virdi

Problem • Overhead cost of $500 per week for any delay after 48 weeks

Problem • Overhead cost of $500 per week for any delay after 48 weeks • Penalty of $15, 000 per week if project takes more than 52 weeks • Possible Labor Strike (12/01/04) • Possible Cold December

Alternatives 1. Expedite seat gallery supports 2. Expedite seat gallery supports and filling of

Alternatives 1. Expedite seat gallery supports 2. Expedite seat gallery supports and filling of the field 3. Expedite the roofing 4. Do nothing until December 1 st. If the cold is indeed extreme, postpone concrete pouring or heat when necessary; if a strike occurs, expedite all activities after resolution 5. Do nothing

Analysis of Baseline & A 5 • Do nothing (Tcp = 48+x weeks)

Analysis of Baseline & A 5 • Do nothing (Tcp = 48+x weeks)

Analysis of A 1 • Expedite pouring concrete for seat gallery supports ($20, 000)

Analysis of A 1 • Expedite pouring concrete for seat gallery supports ($20, 000) (activity G from 12 to 6 weeks) (Tcp=42+x)

Analysis of A 2 • Expedite pouring concrete for seat gallery supports ($20, 000)

Analysis of A 2 • Expedite pouring concrete for seat gallery supports ($20, 000) (G from 12 to 6 weeks) and filling of the field ($10, 000) (C from 14 to 9 weeks) (Tcp = 42+x)

Analysis of A 3 • Expedite the roofing ($9, 000) (activity K from 8

Analysis of A 3 • Expedite the roofing ($9, 000) (activity K from 8 to 2 weeks) (Tcp = 48+x)

Analysis of A 4 with 8 w strike • Do nothing until December 1

Analysis of A 4 with 8 w strike • Do nothing until December 1 st. If the cold is indeed extreme, postpone concrete pouring or heat when necessary; if a strike occurs, expedite all activities after resolution ($3, 000 per week cut) (Tcp = 52)

Analysis of A 4 with 12 w strike • Do nothing until December 1

Analysis of A 4 with 12 w strike • Do nothing until December 1 st. If the cold is indeed extreme, postpone concrete pouring or heat when necessary; if a strike occurs, expedite all activities after resolution ($3, 000 per week cut) (Tcp = 56)

Time analysis

Time analysis

Cost analysis

Cost analysis

Risk Analysis

Risk Analysis

Risk Analysis

Risk Analysis

Risk Profiles

Risk Profiles

Risk Profiles

Risk Profiles

Recommendation 1. A 4: Do nothing until December 1 st. If the cold is

Recommendation 1. A 4: Do nothing until December 1 st. If the cold is indeed extreme, postpone concrete pouring; if a strike occurs, expedite all activities after resolution (lowest E(x)) 2. A 1: Expedite seat gallery supports (second lowest E(x))

Conclusion • • • A 1 is better than A 2 and A 3

Conclusion • • • A 1 is better than A 2 and A 3 if the probability/risk of a strike is considered. A 4 provides the option of speeding up the remaining tasks in case of a strike and doing nothing otherwise. This option is powerful. A 4 has a lower E(x), but a higher uncertainty SD(x) (broad range of losses from $0 to $76, 000) than A 1. The analysis of the risk profiles will help management to select the alternative which fits the corporation’s risk strategy. If the corporation is adverse to risk, it could select A 1 (losses are spread out from $20, 000 to $53, 000). A 1 has a lower uncertainty (SD(x)) than A 4. The project duration could be a factor for the decision, if there are projects on hold due to lack of resources.