Presentation to Select Committee on Economic Development Eskoms

  • Slides: 16
Download presentation
Presentation to Select Committee on Economic Development Eskom’s Solar Water Heating Programme 28 February

Presentation to Select Committee on Economic Development Eskom’s Solar Water Heating Programme 28 February 2012 12/13/2021 1

Introduction • Government target of 1 million systems installed by end 2014 • Approximately

Introduction • Government target of 1 million systems installed by end 2014 • Approximately 230, 000 systems installed through Eskom rebate programme and DORA funded Dx 443. • Balance of 800, 000 systems requires roll-out of 22, 000 systems per month (approx. ) • Programme will be overseen by Inter-ministerial Project Steering Committee chaired by Director General for Economic Development

Low pressure installations 12/13/2021 3

Low pressure installations 12/13/2021 3

High pressure installations 12/13/2021 4

High pressure installations 12/13/2021 4

Installations to date 12/13/2021 5

Installations to date 12/13/2021 5

Programme to date installations Programme yearly growth 140000 130000 120000 1100000 90000 80000 70000

Programme to date installations Programme yearly growth 140000 130000 120000 1100000 90000 80000 70000 60000 50000 40000 30000 20000 10000 0 2008 12/13/2021 2009 2010 2011 6

Installations to date Above graph represents total installations to date, including installations received but

Installations to date Above graph represents total installations to date, including installations received but not yet processed. This includes Eskom funded (rebate and contracts) and Do. E funded (Tshwane, Sol Plaatje and Naledi). 12/13/2021 7

Lessons Learnt 1. Electricity savings are low in relation to cost – SWH is

Lessons Learnt 1. Electricity savings are low in relation to cost – SWH is for job creation and service delivery 2. Quality of installations not always up to standard – re-work was required in many instances 3. Rigorous process controls are required 4. Contracts for on-going maintenance of low pressure systems are required 5. Safety is non-negotiable *SWH – solar water heating 8

Way forward 12/13/2021 9

Way forward 12/13/2021 9

The low pressure rebate programme is to be replaced by a contracting approach 1.

The low pressure rebate programme is to be replaced by a contracting approach 1. Government 1. 2. 3. 4. 5. 6. 7. Job creation and sustainability BBBEE Supplier Development &Localisation Equitable share per province Set aside for co-ops Support for disadvantaged groups/communities Certainty that targets will be met 2. Market Participants 1. 2. Predictability and certainty Finance 3. Implementing Agent 1. 2. 3. 4. Rigorous controls and governance Ensure quality installations System sustainability Safety

Roll-out targets 12/13/2021 11

Roll-out targets 12/13/2021 11

Key parameters of future Roll-Out 1. 2. 3. Contracting options 1. Turnkey contracts 2.

Key parameters of future Roll-Out 1. 2. 3. Contracting options 1. Turnkey contracts 2. Separate contracts for the manufacturers and installers 3. Contract with Co-ops Methodology for contract allocation 1. Open tender 2. Conversion of municipal MOU’s into contracts Allocation of systems 1. Completely ‘open’ subject to equitable share across provinces 2. Designated communities / co-ops 3. Allocation process based on local authority submission

Key Parameters Of Future Roll-Out 4. Localisation 1. No local content specification 2. Minimum

Key Parameters Of Future Roll-Out 4. Localisation 1. No local content specification 2. Minimum level of local content in systems (Gate Keeper) 3. Weighting in tender evaluation 5. Sustainability of systems 1. Retention of payments for 3 -5 years 2. Guarantees / provisions required 3. Contract for system maintenance in place for installers 4. ‘Carbon’ revenues to be leveraged

System specification and installation requirements • Safety - Full compliance to OSHACT and Eskom

System specification and installation requirements • Safety - Full compliance to OSHACT and Eskom safety requirements • Compliance with National standards, SANS standards • Installations only on lower LSM (Iiving standards measure) houses • Maximum size 150 L • SWH systems to carry SABS mark approval • If required, roofs to be re-enforced • Permanent Water connection at the dwelling • Water quality within acceptable parameters

Scope of work for installers • Installation and maintenance of Solar Water Heaters •

Scope of work for installers • Installation and maintenance of Solar Water Heaters • Development and execution of a 5 year maintenance plan • Development of installers and execution of training plan • Installer training and skills development by approved accredited solar trainer and SETA approved • Minimum of 70% of local community labour to be trained and employed for the installation. • Quality assurance Management and auditing of SWH System • Call centre establishment and operation • Progress reporting • Database collection and form administration

THANK YOU Website: www. eskomidm. co. za

THANK YOU Website: www. eskomidm. co. za