Planning and Installation LIU Project Team meeting LIU

  • Slides: 11
Download presentation
Planning and Installation LIU Project Team meeting

Planning and Installation LIU Project Team meeting

LIU activities follow-up EYETS 2016 -2017 LIU-IONS Title Beam Position Monitors in LEIR ITE

LIU activities follow-up EYETS 2016 -2017 LIU-IONS Title Beam Position Monitors in LEIR ITE and EI Lines Group BE-BI ECR LEI-BPM-EC-0001 LIU-PSB Title Relocation of BT. BTV 30 in the PS Booster Installation of a Wideband Pickup in the BTP Transfer Line New Rotatable Beam Wire Scanner Prototype Installation in the PS Booster New BLMs (32 FIC detectors) PSB BCER Switchboard and Containment Installation Enlargement of the shaft to transport the BT. BHZ 10 and BTM. BHZ 10 New KSW magnet in 16 L 1 of the PS Booster New Alcove Construction for PSB Injection BSW Power Converter’s Pulse Transformers BSW Chicane Stripping Foil Magnet Power Converter Installation Group BE-BI EN-EL EN-HE TE-ABT TE-EPC ECR PSB-LJ-EC-0003 PSB-BPUWB-EC-0001 PSB-BWSRA-EC-0001 PSB-BLM-EC-0002 PSB-D-EC-0001 PSB-K-EC-0003 PSB-MKKSW-EC-0001 PSB-K-EC-0002 PSB-R-EC-0002 LIU-PS Title New BLMs (100 New ionization BLMs (2 New racks) and 17 New diamonds BLMs) Installation of Beam Gas Ionisation (BGI) Beam Profile Monitor for the PS Ring An additional Wideband Electrostatic PU in the PS New 80 MHz fast tuner prototype in SS 08 TT 2 transfer line (F 16. QFO 215) Low Energy Quadrupoles (QSK) Power Converters Low Energy Dipoles (DVT) Power Converters Low Energy Dipoles (DHZ) Power Converters New magnets for the horizontal BGI in SS 82 New PS Ring MU 41 and MU 42 Group BE-BI BE-RF TE-EPC ECR PS-BLM-EC-0001 PS-BGI-EC-0001 PS-BPUWA-EC-0001 PS-AC-EC-0001 PS-R-EC-0002 TE-EPC PS-R-EC-0003 TE-EPC TE-MSC TE-VSC / TE-MSC PS-R-EC-0004 PS-MDBCC-EC-0001 PS-VC-EC-0001 Title New Diamonds BLMs in LSS 1 New fast BCTs in LSS 5 Civil engineering for the new beam dump in LSS 5 Flange impedance reduction New vacuum valves a. C coating Group BE-BI SMB TE-VSC ECR SPS-BLMD-EC-0001 SPS-BCTW-EC-0002 SPS-JHCAA-EC-0001 SPS-VF-EC-0001 SPS-V-EC-0005 SPS-VC-EC-0001 LIU-SPS 09 March 2017 LIU PT meeting - J. Coupard

YETS 2017 -2018 schedule Version 3. 0 Machines From beam OFF to Hardware Tests

YETS 2017 -2018 schedule Version 3. 0 Machines From beam OFF to Hardware Tests (not including the xmas break of 2 weeks) PSB 8 PS 8 SPS 8 LHC 9 09 March 2017 LIU PT meeting - J. Coupard

YETS 2017 -2018 schedule Version 3. 1 Version 3. 0 Version 3. 1 Machines

YETS 2017 -2018 schedule Version 3. 1 Version 3. 0 Version 3. 1 Machines From beam OFF to Hardware Tests (not including the xmas break of 2 weeks) Time of machine accessible PSB 8 PSB 7 (-1 week) 6. 5 PS 8 PS 7 (-1 week) 6. 5 SPS 8 (no change) 7. 5 LHC 9 LHC 11 (+2 weeks) 11 09 March 2017 LIU PT meeting - J. Coupard

YETS 2017 -2018 schedule Under study • Upgrade for the new dump in SPS

YETS 2017 -2018 schedule Under study • Upgrade for the new dump in SPS BA 5 YETS 2017 -2018 4 weeks 7 weeks Hardware Commissioning tests Installation of the cables trays between LSS 5 and ECA 5 (EN-EL) Diagnostic tests 4 weeks Cables pulling for MKDH (EN-EL) 2 weeks Xmas closure Infrastructure modifications (SMB) 6 weeks Cables pulling for MKDV (EN-EL) Installation first floor of the kicker platform in ECA 5 8 weeks 4 weeks Installation first floor of the kicker platform in ECA 5 To be scheduled during LS 2 09 March 2017 LIU PT meeting - J. Coupard

09 March 2017 LIU PT meeting - J. Coupard

09 March 2017 LIU PT meeting - J. Coupard

PLAN version 2 timeline Issues on contribution resource availability from version 1 information sent

PLAN version 2 timeline Issues on contribution resource availability from version 1 information sent to all the activity responsible on 21/02 Initialization 30/1/2017 - 31/3/2017 Prioritization 1/4/2017 - 8/4/2017 Resource allocation 9/4/2017 - 2/6/2017 Final approval janvier février mars avril mai Aujourd'hui Milestones All activities are in PLAN All activities are approved by the contributing groups To be approved in PLAN version 2 • LIU activities • Consolidations required for LIU (ref. Chamonix 2016) 09 March 2017 LIU PT meeting - J. Coupard juin 3/6/2017 - 30/6/2017

Consolidation activities required for LIU-IONS Status from Chamonix 2016 System Consolidation item Group When

Consolidation activities required for LIU-IONS Status from Chamonix 2016 System Consolidation item Group When Approved by CONS? Cooling/Ventilations CV of Linac 3 building EN/CV In LS 2 Yes 10392 - Consolidate the Linac 3 HVAC system Beam transfer LEIR SEH 10 Injection septum LEIR TE/ABT 2016 No / Beam transfer LEIR SMH 40 Extraction septum LEIR TE/ABT 2016 No / Beam transfer Magnet KFH 31/32/34 + Generator Extraction kicker LEIR TE/ABT in LS 2 No / Beam transfer KFA 28 spare magnet Injection Kicker PS TE/ABT in LS 2 No / Beam instrumentation LEIR Orbit + Trajectory spare monitors BE/BI No / Magnets LEIR spare magnets coils TE/MSC Ongoing Yes / Magnets Ions lines spare coils TE/MSC Ongoing Partially / in LS 2 Done ? 23 February 2017 LIU PT meeting - J. Coupard PLAN

Consolidation activities required for LIU-PSB Status from Chamonix 2016 System Consolidation item Group When

Consolidation activities required for LIU-PSB Status from Chamonix 2016 System Consolidation item Group When Approved by CONS? Cooling systems Cooling plant replacement / Chilled water plant replacement EN/CV in LS 2 Yes 10427 - Consolidate the PSB chilled water cooling plant 10430 - Consolidate the PSB cooling plant Ventilation systems Renovation of ventilation system EN/CV in LS 2 Yes 10432 - Consolidate the PSB ventilation plant Beam stoppers BI and BTP beam stoppers (under study) EN/STI in LS 2 No 10010 - Renovation of PS complex beam stoppers Vacuum systems Power converters systems Exchange of 12 pumping groups - 4 in BI and BT lines TE/VSC in LS 2 Yes Midi. Discap and Maxi. Discap PCs for LT, LTB and BI lines TE/EPC in LS 2 Yes PLAN 10532 - Consolidation of 2 fixed pumping groups in BI/BT lines 10604 - Consolidation of 3 fixed pumping groups 10691 - Consolidation of 6 fixed pumping groups [LS 2] 11227 - Supply new converters to consolidate LINAC 4 to PS Booster Transfer Line 11224 - Supply new control for the consolidation of the control parts of PS complex converters PC controls renovation (full injectors chain) based on G 64 and MILTE/EPC In progress 1553 Yes Magnet system Spare Coils for Injection and extraction main bends TE/MSC in LS 2 Yes / Magnet system Spare multipoles TE/MSC in LS 2 Yes / 23 February 2017 LIU PT meeting - J. Coupard

Consolidation activities required for LIU-PS Status from Chamonix 2016 Approved by CONS? System Consolidation

Consolidation activities required for LIU-PS Status from Chamonix 2016 Approved by CONS? System Consolidation item Group 40 -80 MHz cavities 40 -80 MHz Power converters replacement TE/EPC In progress Yes 10362 - Supply new converters for PS RF Cavities Vacuum Replacement of enamelled Flanges TE/VSC in LS 2 Yes 10700 - Replacement of 100% enamelled flanges in parallel to 41 magnets consolidation Power converters FTN power converters TE/EPC in LS 2 Yes 10329 - Supply new converters for TT 2 Transfer Line Beam transfer KFA 45 Magnet (modules) Generator TE/ABT in LS 2 Yes 10858 - Prepare PS injection kicker for 2 Ge. V (KFA 45) Beam transfer PS extraction kickers KFA 71 -79 TE/ABT in LS 2 Yes 10860 - Consolidate PS extraction kicker installation FAK (KFA 71 -79) Beam stoppers EN/STI in LS 2 No 10010 - Renovation of PS complex beam stoppers HL-RF 10 MHz system BE/RF in LS 2 Yes 10920 - PS 10 MHz RF Amplifier Upgrade Beam instrumentation TT 2 BLMs BE/BI LS 2 No / Beam instrumentation Injection SEMgrids BE/BI YETS 2015 -16 Yes Magnets TT 2 quadrupoles consolidation TE/MSC in LS 2 Yes 11000 - Rénovation quadrupoles TT 2 Magnets Pole face windings TE/MSC in LS 2 Yes / Yes 10329 - Supply new converters for TT 2 Transfer Line 10424 - Consolidate the cooling plant of the PS main magnet 10430 - Consolidate the PSB cooling plant Cooling systems TT 2 -water cooling station EN/CV When in LS 2 PLAN 10639 - New SEM for PS injection (Septum 42) Done ? Declared under LIU Project WBS 23 February 2017 Declared as preventive maintenance LIU PT meeting - J. Coupard

Consolidation activities required for LIU-SPS Status from Chamonix 2016 System Consolidation item Group When

Consolidation activities required for LIU-SPS Status from Chamonix 2016 System Consolidation item Group When Approved by CONS? 800 MHz Replacement of analogue control with digital BE/RF For Jan 2016 Yes / 800 MHz New 1 -turn feedback and feed-forward (essential for beam control) BE/RF in low level For Jan 2016 Yes / BLM Replace obsolete BLM electronics using new MOPOS fibre BE/BI For LS 2 Pending / MKDV switches Replacement of thyratron/ignitron with GTO switch TE/ABT In LS 2 Yes / ECX 5 crane Refurbishment and upgrade of EXC 5 crane, CONS part EN/HE Completed Partially 10146 - Revamping of crane PR 567 in ECX 5 200 MHz Replacement YL 1530 from Richardson being replaced with TH 335 from Thales BE/RF In LS 2 Yes / Electrical distribution BA 3/BB 3/BF 3 distribution for upgraded 200 MHz EN/EL In LS 2 Yes / Electrical distribution ECA 5/ECX 5 distribution for new LSS 5 beam dump EN/EL In LS 2 Partially / Electrical distribution MOPOS crates to move to UPS EN/EL In LS 2 Partially / De-cabling Various de-cabling activities, especially in LSS 3 and LSS 5, maybe also EN/EL LSS 1 Through LS 2 Yes 11179 - Injector De-cabling SPS BA 3 Declared under LIU Project WBS 23 February 2017 Done ? LIU PT meeting - J. Coupard PLAN