PLAN version 1 results Including all status (21 PLAN activities approved if) 01 February 2017 LIU PT meeting - J. Coupard and S. Mataguez
LIU activities in status approved if PS Booster (12 PLAN activities) Respon Facility sible Activity Type Activity Title Group BE-RF New TE-ABT Upgrade Activity Phase Accepted periods 10923 PSB Finemet RF Systems 10274 Preparation Provide high voltage pulsed generators, Installation Electronics & Controls for PSB BI. KSW Supply new converters for Booster Main 10311 Magnets (Dipole & Quadrupole) & Trims Installation [POPS-B] 2016 2017 2018 LS 2 Contribution Group BE-ABP EN-MME EN-EL 2017 -YETS-2018 EN-EL 2018 TE-EPC Upgrade Supply new converters for Booster 10316 Ejection Transfer Bending Magnets Preparation Installation of the new BHZ , main INJ Consolidation 10936 Installation and EXT magnets Installation of new magnets for 2. 0 Ge. V operations ( 14 units), Including the 10942 Installation dismantling of the BTM. BHZ 10 magnet into manageable pieces. New BI. BVT 10 magnets for PS 11017 Preparation BOOSTER PS Booster 11019 TE-MSC Upgrade New BT. BHZ 10 magnet for PS BOOSTER New BTM. BHZ 10 magnet for PS 11023 BOOSTER 01 February 2017 LS 2 -Semester 4 EN-EL Evaluate the impact of the new system on machine impedance. Provide design, machining and procurement of Finemet cavities with vacuum chambers. Provide support for control cables installation and electrical distribution infrastructure. Comments from Contributor Already done Not Available Missing technical information about ENEL contribution Supply and install the power cable for CV installation in bdg 245 Subjected to further evaluation of planning, co-activities and access constraints Missing technical information about ENEL contribution Installation of Control Cables Resources currently not available Installation of Power Cables Missing technical information about ENEL contribution AC Supply Distribution (Power & Cables) Resources currently not available Cabling realization (part 2: B 245 internal and dummy load) LS 2 EN-EL Installation Missing technical information about ENEL contribution LS 2 EN-MME Production and installation of vacuum chambers No information available. LS 2 EN-MME Preparation of spares for BHZ 151 No information available. LS 2 EN-MME Not discussed with TE-VSC. Not clear if it is required or not. Preparation LS 2 EN-MME Cut and weld vacuum chamber if required. Production of vacuum chamber and supports Design and production vacuum chamber for BTM. BHZ 10 if needed Design&Fabrication of vacuum chambers and supports. Modification to be defined by TE-MSC Preparation New BHZ MAIN INJ & EXT magnets for PS BOOSTER Installation 11022 Contribution Groups who answered no resource 11024 New BT/BTP Quadrupoles for PS BOOSTER Preparation LS 2 EN-MME 11025 New BT vertical bending magnets for PS BOOSTER Installation LS 2 EN-MME LIU PT meeting - J. Coupard and S. Mataguez Cut and reweld vacuum chamber No information available. Not discussed with TE-VSC
LIU activities in status approved if PS&TT 2 (4 PLAN activities) Respon Facility sible Activity Type Activity Title Group BE-RF Upgrade PS&TT 2 TE-EPC Upgrade Activity Phase Accepted periods 10921 PS Longitudinal Damper Preparation 10967 Beam control upgrade Installation Supply new converters for PS Injection 10351 PI. BSM 40, 41, 43 & 44 new Bumper Preparation Magnets TE-MSC Consolidation 11009 Injection Bumber for PS (5 magnets) 01 February 2017 Preparation Contribution Groups who answered no resource Contribution Group Comments from Contributor 2016 -Semester 2, 2017 -Semester EN-MME 1 LS 2 -Semester 2 IT-CS Study the system integration and design a movable shielding for the amplifiers. network connections LS 2 EN-EL Installation of Power Cables Missing technical information about ENEL contribution LS 2 EN-MME Design and production of 5 vacuum chambers No information available. LIU PT meeting - J. Coupard and S. Mataguez Not Available
LIU activities in status approved if SPS (5 PLAN activities) Respon Facility sible Activity Type Activity Title Group SPS Contribution Groups who answered no resource Activity Phase Accepted periods Contribution Group Preparation 2016, 2017 BE-ABP design validation Comments from Contributor transfer lines optics and design are not in ABP mandate Missing technical information about ENEL contribution EN-STI Upgrade TCDI SPS to LHC transfer line 10001 collimator renewal for LIU Installation LS 2 EN-EL Cabling for new TCDI collimators BE-BI Wire scanners for LIU in the SPS 10439 (BWSRE) x 5 Preparation 2017, 2018 EN-MME manufacture of instruments and tanks. Not Available 10835 LIU-SPS RF power upgrade BAF 3 Preparation 2016, 2017, 2018 EN-MME Installation 2016, 2017, 2018, TE-VSC 2019 BE-RF New Upgrade 10836 LIU-SPS RF power upgrade LSS 3 EN-MME activities for LIU-SPS RF amplifier upgrade EN-MME activities for LIU-SPS LSS 3 upgrade New control layout Installation of Control Cables TE-EPC Upgrade 01 February 2017 10341 Supply new converters for SPS TCDI Preparation LS 2 EN-EL LIU PT meeting - J. Coupard and S. Mataguez Installation of Power Cables (To Magnets) AC Supply Distribution (Power & Cables) Not Available See 10740 Missing technical information about ENEL contribution
Timeline for PLAN version 2 Initialization 30/1/2017 31/3/2017 Prioritization 1/4/2017 Resource allocation 8/4/2017 9/4/2017 2/6/2017 Final approval janvier 3/6/2017 février mars avril Aujourd'hui 01 February 2017 LIU PT meeting - J. Coupard and S. Mataguez mai 30/6/2017 juin