Pixel Detector ATLAS Prototype Service Quarter Panel and
- Slides: 11
Pixel Detector ATLAS Prototype Service Quarter Panel and Forward Disk Section update ID Week February 2006 System Test DAQ E. Anderssen LBNL
Pixel Detector PQSP Status and Plan ATLAS • Work at LBL is complete and it’s being packed up. • Expect to ship from LBL this Friday (Feb. 17) to arrive at Bat. 154 in about one week • LBL personnel( tech, student, senior citizen) arrive about Feb. 27 to set up Cirris tester and do reception testing of electrical connectivity • Loading of fibers and opto-boards and subsequent testing, checking interface with cooling parts is next critical step (and should happen in parallel) • Need validation of design/fabrication of PQSP optical items by end March to maintain schedule for production quarter service panels • Goal is to deliver first production SQP in April. HEX will be limiting factor unless something found in optical mounting. February 2006 System Test DAQ E. Anderssen LBNL 2
ATLAS Pixel Detector Vvdc at PP 1 • • First 4 harnesses made before pinout was finalized (affects 16 lemo power connectors) Terminal Blocks for Vvdc Replaced – Vvdc and Vvdc Sense routed thru 1 of two Lemo connectors • Jumpers are designed and will be fabricated which remap these to ‘Production’ PP 1 pinout – Should be delivered ~ April • QA Testing likely needs to be done with old pinout due to schedule constraints February 2006 System Test DAQ E. Anderssen LBNL 3
ATLAS Pixel Detector PSQP PP 1 as completed • This will be the shipping configuration of the PSQP • For Acceptance Testing, the PP 1 B panels are welded to the base, but will be held at R 450 in the test • This fixture may be used in system test, but will require some modifications for gas seal February 2006 System Test DAQ E. Anderssen LBNL 4
ATLAS Pixel Detector Optical Service loading configuration • • All SQP’s held inverted to allow population of PP 1 penetration with Ribbons Previous slide shows backbone reinforcement required to flip panels Opto-heat exchanger shown installed underneath backbone (on top in this picture) ENV feedthru removed for this operation February 2006 System Test DAQ E. Anderssen LBNL 5
Pixel Detector Environmental Sensors ATLAS • • • Env connectors (4 lemo’s worth) wired in thru ISP slot Internal locations all terminated with 2 -pin connectors—blue pads in foreground of right pic Do not have NTC’s or Humidity sensors at LBNL—will need to install of them here – May need some E-tech (someone who can really solder) time from an institute to facilitate this February 2006 System Test DAQ E. Anderssen LBNL 6
Pixel Detector Use of Spares ATLAS • Spares in the production SQP’s are fully wired ‘PP 0 Boards’ (serves up to 6/7 modules)—all connected at PP 0 and PP 1 electrically • Spares used in event of broken internal SQP components/connectors/pins etc • Only work if fully serviced with appropriate flavor of Optoboard, and if they are fully servicable externally • Discussion of what level of external infrastructure needs to be present to use Internal Spares might be an appropriate exercise for this group • Infrastructure is of course both physical services, but can also affect software/DB modularity as use of internal spares changes external mapping/modularity February 2006 System Test DAQ E. Anderssen LBNL 7
Pixel Detector Disk Status ATLAS • This is not my responsibility—so this represents only my limited understanding of the status • Defer to Gil for scheduled completion • Preparation for electrical QA testing underway in recently occupied clean room • As of yesterday—all disks populated with sectors, preparation of auxiliary tooling underway to mount U-tubes —first U-tube mounted, but need to align sector tubes to install remaining • Delivery of PEEK fasteners allowed mounting of all strain reliefs (tube and cable) to all disks • Should be mounting and inserting first disk in End frame this week—only a test as no capillaries are available • Believe we are on schedule for April delivery, but capillary is on CP (Gil? ) February 2006 System Test DAQ E. Anderssen LBNL 8
ATLAS Pixel Detector Disk assembly on fixture February 2006 System Test DAQ E. Anderssen LBNL 9
ATLAS Pixel Detector U-Tube installed February 2006 System Test DAQ E. Anderssen LBNL 10
ATLAS Pixel Detector Cable and Tube strain Reliefs (SLA) February 2006 System Test DAQ E. Anderssen LBNL 11