PILE TESTING Mike Turner Applied Geotechnical Engineering August
- Slides: 18
PILE TESTING Mike Turner (Applied Geotechnical Engineering) August 2004 Pile Testing
Types of load testing n Static load testing Maintained Load (ML) Constant Rate of Penetration (CRP) n Dynamic load testing August 2004 Pile Testing 2
Static load tests on micropiles Features: n High slenderness ratio (=Aspect Ratio) n Relatively high elastic shortening Implies: n Long piles = large pile head settlement August 2004 Pile Testing 3
Pile length vs Pile head settlement at working load: Micropiles in soils August 2004 Pile Testing 4
Pile length vs settlement at working load Micropiles in soils (2) 0. 5 mm/m 0. 25 mm/m 0. 1 mm/m August 2004 Pile Testing 5
Pile length vs Gross pile head settlement at working load – Micropiles into rock August 2004 Pile Testing 6
Pile length vs settlement at working load Micropiles into rock (2) 0. 4 mm/m 0. 35 mm/m 0. 2 mm/m August 2004 Pile Testing 7
Summary (1) For a wide variety of soils: Gross pile settlement at working load is n Proportional to pile length n Around 0. 25 mm/metre, on average n (As high as 0. 5 mm/metre) n (As low as 0. 1 mm/metre) n Independent of diameter (and load) August 2004 Pile Testing
Summary (2) For a wide variety of rocks: Gross pile settlement at working load is n Proportional to pile length n Around 0. 35 mm/metre, on average n (As high as 0. 4 mm/metre) n (As low as 0. 2 mm/metre) n Independent of diameter (and load) August 2004 Pile Testing
Spooky! August 2004 Pile Testing
Pile head settlement vs working load: Micropiles in soils August 2004 Pile Testing 11
Pile head settlement vs working load: Micropiles in soils (2) 0. 005 mm/k. N 0. 012 mm/k. N 0. 035 mm/k. N August 2004 Pile Testing 12
Pile head settlement vs working load: Micropiles into rock August 2004 Pile Testing 13
Pile head settlement vs working load: Micropiles into rock (2) 0. 004 mm/k. N 0. 01 mm/k. N 0. 02 mm/k. N (variable) August 2004 Pile Testing 14
Summary (1) For a wide variety of soils: Gross pile head settlement at working load is: n Around 0. 012 mm/k. N (0. 1 mm/tonne [metric]) n [As high as 0. 035 mm/k. N (0. 35 mm/tonne)] n [As low as 0. 005 mm/k. N (0. 05 mm/tonne)] n (Fairly) independent of length and actual load! August 2004 Pile Testing
Summary (2) For a wide variety of rocks: Gross pile head settlement at working load is: n Around 0. 01 mm/k. N (0. 1 mm/tonne [metric]) (for most practical purposes) n May be as high as 0. 02 mm/k. N (0. 2 mm/tonne) n May be as low as 0. 004 mm/k. N (0. 04 mm/tonne) n Still fairly independent of length and load! August 2004 Pile Testing
Even spookier! August 2004 Pile Testing 17
Conclusion/discussion Apparent similarities of relationships? n n Bearing stratum generally stronger than overburden Piles designed on shaft friction alone Grout-to-ground design conservative Structural design essentially identical August 2004 Pile Testing
- Applied geotechnical engineering
- Cven4102
- Unconsolidated undrained triaxial test mohr circle
- Consistency limits in geotechnical engineering
- Geotechnical
- Geotechnical earthquake engineering kramer
- Finite element method in geotechnical engineering
- Geotechnical engineering swinburne
- Mike cohn user stories
- Mike applied 10 n
- Geotechnical data management
- Geotechnical data management
- Principles of applied engineering
- Fu foundation school of engineering
- Uc college of engineering and applied science
- Gerling applied engineering
- Achan pile of rocks
- Pile worms teeth
- Pythagoras pile up