PERT The Program Evaluation and Review Technique Methods

  • Slides: 17
Download presentation
PERT - The Program Evaluation and Review Technique Methods and techniques of MBP

PERT - The Program Evaluation and Review Technique Methods and techniques of MBP

PERT Definition: ü The Program Evaluation and Review Technique (PERT) ü a technique (mean)

PERT Definition: ü The Program Evaluation and Review Technique (PERT) ü a technique (mean) that analyzes all tasks involved in completing a given project, ü especially to analyze the time needed to complete each task, and identifying the minimum time needed to complete the total project (the critical path). ü PERT was developed in the 1950’s, primarily to simplify the planning and scheduling of large and complex projects. http: //en. wikipedia. org

PERT Definition: ü An arrow-node diagram – a task network for a project made

PERT Definition: ü An arrow-node diagram – a task network for a project made with arrows and small circles. ü A precedence diagram – a task network for a project made with boxes and realtionship lines. http: //en. wikipedia. org

PERT Nomenclature (key terms): event - end point that represents the completion of major

PERT Nomenclature (key terms): event - end point that represents the completion of major activity The event number The latest possible finish time of the event The earliest possible start time of the event The slack time

PERT Nomenclature (key terms): Activity – time required to progress from one event to

PERT Nomenclature (key terms): Activity – time required to progress from one event to another Critical Activity – activity with zero slack time Links – neither time nor activity relationship

PERT Nomenclature (key terms): 0 2 0 0 4 3 0 5 ü events

PERT Nomenclature (key terms): 0 2 0 0 4 3 0 5 ü events - end points that represent the completion of major activities ü activities - time or resources required to progress from one event to another ü slack time - amount of time an activity can be delayed without delaying the entire project ü critical path - the most time-consuming sequence of events and activities in a PERT network ü delays on critical path will delay completion of the entire project (zero slack time) © Prentice Hall, 2002

PERT Nomenclature (key terms): milestone – a strategic event that end certain group of

PERT Nomenclature (key terms): milestone – a strategic event that end certain group of activities 9 14 14 0 7 4 14 14 0 5 14 14 0 6 14 14 0 8 14 14 0 10 14 14 0

PERT - methodology Procedure „step-by-step”: Step 1: Create a table – activity / duration

PERT - methodology Procedure „step-by-step”: Step 1: Create a table – activity / duration Step 2: Name events accordingly to the table Step 3: Link all the events with planned activities Step 4: Add duration time for each activity Step 5: Enter The earliest possible start time for every event Step 6: Enter the latest possible finish time for every event Step 7: Evaluate the slack time for every event Step 8: Underline (in red) the critical path of the entire project Step 9: Select milestones for the project

PERT - methodology Step 1: Create a table – activity / duration Activity: Duration:

PERT - methodology Step 1: Create a table – activity / duration Activity: Duration: A. Activity a 2 B. Activity b 4 C. Activity c 4 D. Activity d 3 E. Activity e 5 F. Activity f 3 G. Activity g 2 H. Activity h 4 I. Activity i 2 J. Activity j 3

PERT - methodology Step 2: name events accordingly to the table 0 4 1

PERT - methodology Step 2: name events accordingly to the table 0 4 1 2 5 8 3 6 9 7 10

PERT - methodology Step 3: Link all the events with planned activities 5 f

PERT - methodology Step 3: Link all the events with planned activities 5 f e 1 6 k 0 a 2 4 b d 8 h c j i 3 7 g 9 10 l

PERT - methodology Step 4: Add duration time for each activity 5 1 2

PERT - methodology Step 4: Add duration time for each activity 5 1 2 0 3 f 5 e 6 k a 4 b 2 3 d c 4 2 h 4 8 4 i 3 2 g 7 2 j 9 6 3 l 10

PERT - methodology Step 5: Enter The earliest possible start time for every event

PERT - methodology Step 5: Enter The earliest possible start time for every event 2 2 0 0 a 1 4 b 7 5 e 5 3 f 10 6 k 4 2 3 d c 7 4 2 h 4 14 8 4 i 8 3 7 2 10 g 2 j 16 9 6 3 l 10 19

PERT - methodology Step 6: Enter the latest possible finish time for every event

PERT - methodology Step 6: Enter the latest possible finish time for every event 2 2 0 0 0 a 1 4 b 7 5 e 5 3 f 10 6 10 13 5 k 4 2 3 d 4 c 7 4 4 12 8 2 h 14 14 4 i 8 3 8 7 2 10 10 g 2 j 9 6 16 16 3 l 10 19 19

PERT - methodology Step 7: Evaluate the slack time for every event 2 2

PERT - methodology Step 7: Evaluate the slack time for every event 2 2 0 0 a 1 3 4 b 7 5 e 5 3 3 f 10 6 10 13 3 5 k 4 2 0 3 d 4 c 7 4 4 5 12 8 2 h 14 14 0 4 i 8 3 0 8 7 2 10 10 g 0 2 j 9 6 16 16 0 3 l 10 19 19 0

PERT - methodology Step 8: Underline (in red) the critical path of the entire

PERT - methodology Step 8: Underline (in red) the critical path of the entire project 2 2 0 0 a 1 3 4 b 5 7 5 e 3 3 f 10 6 10 13 3 5 k 4 2 0 3 d 4 c 7 4 5 12 8 2 h 4 14 14 0 4 i 8 3 0 8 2 g 7 10 10 0 2 j 9 6 16 16 0 3 l 10 19 19 0

PERT - methodology Step 9: Select milestones for the project 2 2 0 0

PERT - methodology Step 9: Select milestones for the project 2 2 0 0 a 1 3 4 b 5 7 5 e 3 3 f 10 6 10 13 3 5 k 4 2 0 3 d 4 c 7 4 5 12 8 2 h 4 14 14 0 4 i 8 3 0 8 2 g 7 10 10 0 2 j 9 6 16 16 0 3 l 10 19 19 0