Pacific Team 2001 TEAM INTRODUCTION Crystal Lang ARCHITECT
- Slides: 66
Pacific Team 2001
TEAM INTRODUCTION Crystal Lang ARCHITECT Robert Wright ENGINEER Robert Alvarado OWNER Edgar Leenen Will Clift CONSTRUCTION MANAGER APPRENTICE Pacific 2001
GENERAL INFORMATION Site: Univ. of the Pacific, Forest Grove, Oregon Year: 2015 Surroundings: • Atop a cliff looking out on Pacific Ocean • Small pond on inland side Pacific 2001
GENERAL INFORMATION • Geologic Information: The site lies on top of bedrock. • Precipitation: 65”-90” annually • Flooding occurs occasionally • Wind: Strong winds up to 85 mph can exist Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER BUDGET Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER ROCK • Light • Functional space
ARCHITECTENGINEERCONSTRUCTIONMANAGER
ARCHITECTENGINEERCONSTRUCTIONMANAGER LOADING Live Loads • Atrium, Terrace, Storage • Corridors • Lobby, Auditorium • Classrooms, Offices • Roof 100 psf 80 psf 60 psf 50 psf 20 psf Seismic Requirements • Zone III Seismic Activity • Occupancy Category, I = 1. 0 Wind Requirements • Design Wind Speed 85 mph Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER M. E. P CONSIDERATIONS • Cooling capacity • Boiler room & chilled water • Space for cooling towers • Cooling air volume • Main supply or return ducts area • Branch supply or return ducts • Area of fan rooms • Area of fresh air louvers • Area of exhaust air louvers • Central mechanical room area 70 tons 450 ft 2 80 ft 2 27000 CFM 16 ft 2 27 ft 2 750 ft 2 65 ft 2 50 ft 2 1200 ft 2 Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER ROCK Structural Solution I Lateral System Gravity System Lateral System • Steel Moment Resistant Frames (N – S) • Reinforced Concrete Shearwalls (E – W) Gravity System • Composite Steel/Concrete Deck Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER ROCK First Floor E E+A TYPICAL SIZES Second Floor Gravity Beams W 18 X 55 Columns W 12 X 45 Slab t = 4. 5” Lateral Beams W 18 X 40 Columns W 18 X 35 Shearwall h = 10” Third Floor Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER STEEL CONNECTIONS Steel Beam-Shearwall Connection Beam-Girder Connection Moment Connection Girder-Column Connection Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER ROCK Structural Solution II Lateral System Gravity System Lateral System • Post-Tensioned Moment Resistant Frames (N – S) • Reinforced Concrete Shearwalls (E – W) Gravity System • Two-Way Post-Tensioned Slab • Reinforced Concrete Columns and Beams Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER ROCK First Floor E E+A TYPICAL SIZES Second Floor Gravity Beams 7”X 10” Columns 12”X 12” Slab h = 9” Lateral Shearwall h = 10” Third Floor Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONCRETE POST-TENSIONED DETAILS Tendon Support Post-Tensioned Slab Moment Connection Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER EQUIPMENT
ARCHITECTENGINEERCONSTRUCTIONMANAGER SITE PLAN ROCK & EARTH Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SCHEDULE ROCK 1 Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SCHEDULE ROCK 1 (steel) ROCK 2 (reinforced concrete/post-tensioned concrete) Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE ROCK Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER • Dynamic WAVE • Explore
1 2 3
ARCHITECTENGINEERCONSTRUCTIONMANAGER
ARCHITECTENGINEERCONSTRUCTIONMANAGER WAVE Structural Solution I Lateral System Gravity System Lateral System • Shear. Walls • Concrete Moment Frames • Two Separate Buildings Gravity System • Two-Way Slabs • Reinforced Concrete Columns and Beams Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER WAVE First Floor E E+A TYPICAL SIZES Second Floor Gravity Beams Columns Slab 10”X 12”X 12” h = 10” Lateral Beams 18”X 18” Columns 16”X 14” Shearwall h = 10” Third Floor Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER REINFORCED CONCRETE CONNECTIONS Column Reinforcement Beam-Column Shear Reinforcement Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER WAVE Structural Solution II Lateral System Gravity System Lateral System • Shear. Walls • Steel Moment Resistant Frames Gravity System • Composite Steel/Concrete Deck • Steel Beams and Columns with Simple Shear Connections Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER WAVE First Floor E E+A TYPICAL SIZES Second Floor Gravity Beams W 16 X 36 Columns W 12 X 40 Slab h = 4. 5” Lateral Beams W 16 X 40 Columns W 16 X 31 Shearwall h = 8” Third Floor Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER SHEARWALL DETAILS Shearwall Reinforcement Wall-Footing Elevation Shearwall Corner Reinforcement Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER SITE PLAN WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SCHEDULE WAVE 1 (reinforced concrete) WAVE 2 (steel) Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE WAVE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER • Functional EARTH • Flexible
ARCHITECTENGINEERCONSTRUCTIONMANAGER
ARCHITECTENGINEERCONSTRUCTIONMANAGER EARTH Structural Solution I Lateral System Gravity System Lateral System • Shear. Walls (N – S) • Shear. Walls (E – W) Gravity System • Post-Tensioned Two-Way Slabs • Reinforced Concrete Beams and Columns Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER EARTH First Floor E E+A TYPICAL SIZES Gravity Beams 7”X 12” Columns 12”X 12” Slab h = 9” Second Floor b Lateral Shearwall N h = 10” Shearwall E h = 8” Third Floor Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER EARTH Structural Solution II Lateral System Gravity System Lateral System • Shear. Walls (N – S) • Shear. Walls (E – W) Gravity System • Composite Steel/Concrete Deck • Steel Beams and Columns with Simple Shear Connections Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER EARTH First Floor E E+A TYPICAL SIZES Gravity Beams W 18 X 55 Columns W 12 X 45 Slab h = 9” Second Floor b Lateral Shearwall N h = 10” Shearwall E h = 8” Third Floor Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER FOUNDATION SYSTEM • Spread for interior columns • Typical Size 4’ X 2’ • Strip for perimeter columns and shearwalls • Typical Size 4’ X 2” Typical Steel Column-Footing Typical Concrete Column-Footing Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SCHEDULE EARTH 1 (reinforced concrete/post-tensioned concrete) EARTH 2 (steel) Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER CONSTRUCTION SEQUENCE Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER COST COMPARISON BUDGET Pacific 2001
ARCHITECTENGINEERCONSTRUCTIONMANAGER COST COMPARISON WAVE 2 Beams Columns Moment frames Slab Roof COSTS Steel Composite Steel Structural system Total $ 178. 000 $ 3. 700. 000 BUDGET Structural system Total $ 296. 000 $ 3. 620. 000 Pacific 2001
TEAM INTERACTIONS SAMPLE DESIGN ITERATION A A+E+C A+E E+C 1 Time C
DECISION MATRIX
PACIFIC 2001 CHOICE WAVE!
LESSONS LEARNED AND GOALS • Utilize available technology more effectively • Improve communication • Coordinate media we work in • More interactions: • Between team members • With mentors • With owner Pacific 2001
QUESTIONS ? Pacific 2001
- Edgar leenen
- Lominger leadership architect
- Pacific strike team
- Learning task 2 im an architect
- Architect act 1967
- Enterprise architect deployment diagram
- Sarah mocke
- Risc os
- Enterprise architect requirements management
- Platform architect synopsys
- Rational software architect
- Rational software architect
- Prosessikartta malli
- The great wave off kanagawa elements of art
- Dpm architect
- Chief network architect
- Xbrl taxonomy editor
- Akta arkitek 1967
- American architect canada
- The architect of french absolutism was
- Activity diagram in enterprise architect
- Vikram goyal architect
- Zaki yasin architect
- Diagonālšķēlums piramīda
- Life transformation church
- Architect of the concept of number system
- Rational software architect
- Enterprise architect subversion
- Architect big ben
- The vertex form
- Stone age architect
- Schroder house architect
- Johan rutgeerts
- How to read 1/8 scale
- Icss bms
- Keith burns architect
- Grady booch uml
- Architect meaning in english
- Digital signage architect
- David olson architect
- Duty of architect
- Contract
- Bill thomas architect
- David lee architect
- Rsa uml
- Webench power architect
- Kenneth turner architect
- Blackboard design pattern
- Angela s. became a famous architect
- Rob sherwood architect
- The architect or “father of american public health” was
- Hina sharma architect
- Enterprise architect import database schema
- John crawford intel
- Dpm architecture
- Aswathy mohan architect
- Chris jordan architect
- Qpr enterprise architect
- Peter sullivan architect
- Thu thiem architect
- "schaefer" labor or wms or wes or wcs or lrm
- Dax davis
- Volcano network architect
- Mel reynolds architect
- Team spirit becomes team infatuation
- Team spirit becomes team infatuation
- The white team cheers for the blue team, just like