P 5 ILC Review Americas Region Report Americas

  • Slides: 21
Download presentation
P 5 ILC Review - Americas Region Report Americas • ART Program – FY

P 5 ILC Review - Americas Region Report Americas • ART Program – FY 08 status – FY 09 proposal • ILC Construction Project Scenarios – – P 5 Review Fermilab Feb 1 Total Cost in a US Metric Timelines & Critical Decisions US Host, non-host scenarios Funding profiles 1

Americas Region FY 08 status Americas Recent omnibus spending bill capped US FY 08

Americas Region FY 08 status Americas Recent omnibus spending bill capped US FY 08 ILC funding at $15 M. Since we were 3 months into the fiscal year with a $60 M guidance this was tantamount to a ‘cease work’ for the balance of FY 08. All spending was halted ~ 1 Jan and a count of funds remaining at the labs indicated an unobligated balance of ~ $2. 5 M under the cap. FY 08 priorities then became: – – – P 5 Review Fermilab Feb 1 GDE common fund ($400 K) GDE core support (Barish, Harrison, Ross, Carwardine) CESR TA (electron cloud R&D) + MDI (? ) + ……. . 2

Americas Region - History Americas The chart shows the time evolution of ART funding

Americas Region - History Americas The chart shows the time evolution of ART funding - actuals + projected. Since Aug of last year the projected FY 09 funding has fallen from $95 M -> $60 M -> ~$30 M. This tends to make detailed planning difficult. P 5 Review Fermilab Feb 1 3

Americas Region FY 09 planning Americas • • After discussions with OHEP it was

Americas Region FY 09 planning Americas • • After discussions with OHEP it was decided to present an FY 09 budget at roughly 50% of the former one. Should be ‘robust’ and thus easily defensible. Given the FY 08 situation then only top down planning possible for the near term. No detailed ART multi-year program yet but it is conceptually compatible with the new GDE plan. Strategic goals: Preserve collaborative commitment to the GDE Provide contributions to the ILC R&D program which are unique to the US Support the value engineering effort in the medium term Maintain US presence in ILC SRF R&D P 5 Review Fermilab Feb 1 4

Americas • ART/GDE Collaboration - Management & Conceptual Engineering FY 09 reduction of effort

Americas • ART/GDE Collaboration - Management & Conceptual Engineering FY 09 reduction of effort ~50% i. e. scaling with program size though not linearly. Mid level management pushed back into the technical programs. – Preserves international and national management & engineering roles, travel, contingency, etc. . – Management/Engineering (GDE) Barish, Harrison, Ross, Carwardine + travel etc. – GDE common fund - $400 K – Management ART/GDE (Garbincius, Kerby) + travel etc. – System integration - (Paterson) – Communications - (~ 50% of an FTE) – Contingency ~ $2 M P 5 Review Fermilab Feb 1 5

ART ILC Systems - FY 09 Impact Americas • Electrons – 20% reduction •

ART ILC Systems - FY 09 Impact Americas • Electrons – 20% reduction • Positrons – US efforts eliminated • Damping Rings – All effort eliminated except e-cloud R&D at CESR-TA (with NSF) • RF systems – All hardware deliverables eliminated (40% reduction) - preserve R&D at SLAC in HLRF • Beam Delivery System – 10% reduction • Accelerator physics/Global systems – 50% reduction • Conventional Facilities – No bid to host or site categorisation – Maintain value engineering P 5 Review Fermilab Feb 1 6

ART ILC Systems - Cavities & Cryomodules Americas • Reduction of ~50% – Maintain

ART ILC Systems - Cavities & Cryomodules Americas • Reduction of ~50% – Maintain US presence in the GDE SRF program but no lead role. No industrialization. No systems tests. The effective reduction is much larger due to the loss of the so-called generic infrastructure support. Here we ‘play the global’ card relying on work in Asia and the EU to provide the majority of the ILC SRF technology development. String test in KEK 2011 at the same time the XFEL is producing 1 cryomodule per week. – Minimal gradient program at JLAB & Cornell – Cryomodule prototyping at Fermilab (cryomodule engineering, cryomodule parts, testing etc…. . $20 M over 4 yrs) – Note: cryomodule development assumes some Fermilab infrastructure (horizontal test stand, cryomodule assembly facilities, cryomodule test stand) P 5 Review Fermilab Feb 1 7

ART Program Summary Americas • • Stop work for the balance of FY 08

ART Program Summary Americas • • Stop work for the balance of FY 08 Reduction of ~ 50% in FY 09 (with the tacit assumption of constant effort for the out years) • Effort more focused – – – • P 5 Review Fermilab Feb 1 GDE collaboration/management CESR TA Beam Delivery & MDI HLRF R&D Cryomodule development Value engineering Pull back on SRF technology - gradient & full system string tests 8

Americas ILC Construction Project Scenarios - conversion to a US metric Start with the

Americas ILC Construction Project Scenarios - conversion to a US metric Start with the RDR “Value” Costs Total Value Cost (FY 07) $4. 80 B $FY 07 Shared + $1. 82 B $FY 07 Site Specific + 14. 1 K person-years (“explicit” labor = 24. 0 M person-hrs @ 1, 700 hrs/yr) (Assume $100 K/yr = $1. 4 B) CFS is ~ $2. 4 B Direct Labour ~ $1. 4 B Balance ($4. 22 B) is what we call materials & services (M&S) US style estimates include R&D, contingency, escalation, design, and base salaries (SWF). Note ILC CFS costs were estimated in the same way as we would in the US but only for what we would term the ‘construction phase’. Correct translation to US metric requires a bottoms-up. In lieu of that look at ITER & RHIC Caveat - what follows is obviously not an official GDE based (or DOE for that matters) costing or scheduling exercise. It should be taken by P 5 in the spirit in which it is offered P 5 Review Fermilab Feb 1 9

Americas P 5 Review Fermilab Feb 1 ILC Construction costs - Value estimate to

Americas P 5 Review Fermilab Feb 1 ILC Construction costs - Value estimate to US style, example of ITER 10

Americas P 5 Review Fermilab Feb 1 ILC Construction costs - Value estimate to

Americas P 5 Review Fermilab Feb 1 ILC Construction costs - Value estimate to US style, example of ITER 11

Americas ILC Construction costs - Value estimate to US style, example of ITER Total

Americas ILC Construction costs - Value estimate to US style, example of ITER Total - escalation = $925 M / Value $503 M = Multiplier of 1. 84 for value -> US Note no conventional facilities & contingency only 15%. We assume 30% thus multiplier is 2. 12 P 5 Review Fermilab Feb 1 12

Americas ILC Construction costs - Value estimate to US style, example of RHIC The

Americas ILC Construction costs - Value estimate to US style, example of RHIC The total RHIC machine costs were $371 M in $AY -> (~ $750 M in FY 07 ). Note no CFS, thanks to Isabelle. Break down M&S 59% SWF 32% Direct Labour 5% Indirects 4% Thus a value estimate would have included 64% of the RHIC costs. Hence a multiplier based on RHIC would suggest 1. 56 + 30% contingency => 2. 03 P 5 Review Fermilab Feb 1 13

ILC Construction costs - Conventional Facilities Americas US style estimate but only for the

ILC Construction costs - Conventional Facilities Americas US style estimate but only for the construction costs thus we need to add in the PED phase scope (Title I & II) - A/E of 10% While the estimate includes the standard construction contingency like items such as errors & omissions it is a so-called 50% estimate. DOE likes a 90% estimate. This adds an additional 20% P 5 Review Fermilab Feb 1 14

ILC Construction costs - US Estimate Americas So the ILC costs in a US

ILC Construction costs - US Estimate Americas So the ILC costs in a US metric (constant dollars) is given by: CFS -> 1. 1 * 1. 2 * Value Accelerator Systems -> 2. 07 * Value Hence total is $2. 4 B * 1. 1 * 1. 2 + $5. 62 B * 2. 07 = $14. 9 B (TEC, $FY 07) P 5 Review Fermilab Feb 1 15

Americas ILC Construction costs - Strawman Project timeline The US system (413. 3 A)

Americas ILC Construction costs - Strawman Project timeline The US system (413. 3 A) requires critical decisions: CD 0 - Mission need - a. k. a. LHC physics results ~ 2011 CD 1 - Cost Range - a. k. a. Site selection (Host or not) ~ 2013 CD 2 - Performance baseline - a. k. a. International scope agreement ~ 2014 CD 3 - Construction Start - ~ 2016 CD 4 - Start of Operations - ~2023 Again the caveat this does not represent any official GDE planning scenario P 5 Review Fermilab Feb 1 16

Americas P 5 Review Fermilab Feb 1 ILC Construction Funding Profile - RDR 2007

Americas P 5 Review Fermilab Feb 1 ILC Construction Funding Profile - RDR 2007 Value costs only 17

ILC Project - US Role & R&D phase Americas The concept of the requirements

ILC Project - US Role & R&D phase Americas The concept of the requirements for an ILC host has been relatively stable for the past few years. The host would be expected to provide ~50% of the total cost. This is made up of the site specific costs together with contributions summing to 33% of the remaining value costs. The host would also be expected to donate any land needed by the Project. In order to construct and operate the machine successfully the host would need to have wide ranging involvement in all the various technical elements of the program; with the SRF systems prominent. As a Non-Host then depending on the number of collaborating countries the contribution would probably lie in the range of 10 -25%. Technical involvement does not need to be across the board and targeting specific sub-systems for contributions will be necessary. A program at the anticipated level of FY 09 lacks the resources to provide a broad-based R&D program consistent with a host scenario. In defining the R&D phase I have assumed that it will cover the programmatic funding phase i. e. up to and including FY 12. I assume that it starts at ~$30 M in FY 09 and ends up in FY 12 at a level needed to avoid funding discontinuities defined as a year on year increase of > factor of 2. This is evidently a highly top down approach. P 5 Review Fermilab Feb 1 18

ILC Construction costs (TEC) Americas With the long lever arm we are sensitive to

ILC Construction costs (TEC) Americas With the long lever arm we are sensitive to assumptions on inflation. A change of 0. 5% = $1. 2 B AY Totals do not include programmatic funding P 5 Review Fermilab Feb 1 19

Near-term ART R&D Program Americas Assume FY 09 $30 M – Host scenario would

Near-term ART R&D Program Americas Assume FY 09 $30 M – Host scenario would suggest FY 11 $86 M, FY 12 $148 M hence FY 10 ~$60 M thus we need starting in FY 08 15 ->30 ->60 ->86 ->148. – Total R&D costs $339 M out of ~$10 B; low compared to the typical 6 -8%. – Non Host scenario would suggest FY 11 $34 M, FY 12 $59 hence FY 10 $32 M thus we need 15 ->30 ->32 ->34 ->59. – Total R&D $160 M out of $4 B would indicate that we are still low compared to a 20% non-host contribution but O. K. for 10 -15% one. P 5 Review Fermilab Feb 1 20

ILC Construction Project - Conclusions Americas Conclusions: – on any relevant time scale we

ILC Construction Project - Conclusions Americas Conclusions: – on any relevant time scale we can’t get from ‘here to there’ with a $30 M-ish program if ‘there’ for the US is hosting an ILC in the foreseeable future. – we are (just) consistent with a non-host role (15± 5%) at this funding level for the next couple of years. The elements of the ART program may not be the correct ones since a non-host role will have specific technical contributions. – A little stability in the funding (actuals & projected) would help to get the most from the available resources. P 5 Review Fermilab Feb 1 21