OTTR 7 Upgrade Project Plan Dan Miller OTTR

  • Slides: 16
Download presentation
OTTR 7 Upgrade Project Plan Dan Miller, OTTR PM OUI 2016

OTTR 7 Upgrade Project Plan Dan Miller, OTTR PM OUI 2016

OTTR 7 Project Upgrade Plan Welcome Glad You Are Here Upgrade: raise (something) to

OTTR 7 Project Upgrade Plan Welcome Glad You Are Here Upgrade: raise (something) to a higher standard, in particular improve by adding or replacing components. 2

OTTR 7 Project Upgrade Plan Outline What changed ‘Typical’ Project Plan Detailed by-the-hour transition

OTTR 7 Project Upgrade Plan Outline What changed ‘Typical’ Project Plan Detailed by-the-hour transition timeline Lessons learned Questions 3

Changes in OTTR 7 The change: Look and feel Update to the presentation layer

Changes in OTTR 7 The change: Look and feel Update to the presentation layer ◦ Web-browser based (Chrome or IE 11) ◦ Adds a web server to the architecture OTTR Platform Guide provides required specs Min 2 core CPU, 8 GB RAM (<25 concurrent users) Same database (minor schema updates) Same interfaces 4

OTTR 7 Implementation Status KEY: New Site Implementations Beta Sites 5

OTTR 7 Implementation Status KEY: New Site Implementations Beta Sites 5

‘Typical’ Project Plan Your mileage will vary Each site has unique clinical/IT processes Test

‘Typical’ Project Plan Your mileage will vary Each site has unique clinical/IT processes Test approach and training approach vary ◦ Formal test plans and workflow documents ◦ Less formal, take a patient through the process ◦ On-site training vs. Train-the-trainer Nominal duration: 6 weeks start to Go-live Test Train Go-live 6

‘Typical’ Project Plan-Site Variations Examples Driving Timelines IT Process Drivers ◦ IT Security and

‘Typical’ Project Plan-Site Variations Examples Driving Timelines IT Process Drivers ◦ IT Security and Architecture Review (weeks) ◦ Hardware Migrations/Server Upgrades (weeks) ◦ IT Change Control Process (could be months) Baseline freezes or competing projects Clinical Needs ◦ Workflow changes to implement ‘best practices’ ◦ Size of program and number of organs Test Approach 7

‘Typical’ Project Plan-Site Variations Test Approach-Audit Tool 8

‘Typical’ Project Plan-Site Variations Test Approach-Audit Tool 8

‘Typical’ Project Plan-Site Variations Test Approach-Audit Tool • • • Patient Review Window, Labs,

‘Typical’ Project Plan-Site Variations Test Approach-Audit Tool • • • Patient Review Window, Labs, Awaiting Review Phases: Referral, Evaluation, Listing, Transplant Event, Post Encounter Donors Reports ETC. 9

‘Typical’ Project Plan-Continued High-level Schedule 10

‘Typical’ Project Plan-Continued High-level Schedule 10

‘Typical’ Project Plan-Continued Detailed tasks: Set up test environment Task Name Duration Upgrade To

‘Typical’ Project Plan-Continued Detailed tasks: Set up test environment Task Name Duration Upgrade To OTTR 7 Start Finish 48. 5 d Tue 6/28/16 Mon 9/5/16 8 d Tue 6/28/16 Fri 7/8/16 Configure Hardware for Test and Prod 5 d Tue 6/28/16 Tue 7/5/16 Assign URLs for Test and Prod 1 d Wed 7/6/16 Send HW Information to OTTR 1 d Thu 7/7/16 Review hardware specifications and access info 0 d Thu 7/7/16 Discuss change control during testing 1 d Fri 7/8/16 Sign/off Specifications Complete 0 d Fri 7/8/16 5 d Fri 7/8/16 Fri 7/15/16 Meet w/client to review procedures during install 0 d Fri 7/8/16 Refresh Test Database 1 d Mon 7/11/16 Upgrade OTTRFeed in Test 1 d Tue 7/12/16 Upgrade Test DB 1 d Wed 7/13/16 Install Calendar. D in Test 0 d Wed 7/13/16 Internal QA on Test 2 d Thu 7/14/16 Fri 7/15/16 PRE UPGRADE NOTIFICATION AND SIGNOFF UPGRADE CLIENT TEST ENVIRONMENT 11

‘Typical’ Project Plan-Continued Detailed tasks: test, train & Go-live Task Name Duration Start Finish

‘Typical’ Project Plan-Continued Detailed tasks: test, train & Go-live Task Name Duration Start Finish SITE TESTING 25 d Mon 7/18/16 Fri 8/19/16 Site Testing 15 d Mon 7/18/16 Fri 8/5/16 Weekly client testing review 1 0 d Fri 7/22/16 Weekly client testing review 2 0 d Fri 7/29/16 Final client testing review 0 d Fri 8/5/16 On-site training 4 d Mon 8/8/16 Thu 8/11/16 Resolve negotiated issues 15 d Mon 7/25/16 Fri 8/12/16 QA issue resolution fixes 4 d Mon 8/15/16 Thu 8/18/16 Client Upgrade Testing and QA Complete 1 d Fri 8/19/16 10 d Fri 8/19/16 Fri 9/2/16 0 d Fri 8/19/16 1 ed Fri 8/19/16 Sat 8/20/16 Go-live on OTTR 7 0 d Mon 8/22/16 OTTR On-site Go-live support 4 d Mon 8/22/16 Thu 8/25/16 Capture any outstanding issues 0 d Thu 8/25/16 Post Go Live 6 d Fri 8/26/16 Fri 9/2/16 Monitor Users for Product Performance 5 d Fri 8/26/16 Thu 9/1/16 Document post-upgrade Lessons Learned 1 d Fri 9/2/16 PRODUCTION UPGRADE Review Prod upgrade steps detailed timeline Configure OTTR 7 in production 12

Getting to production: step-by-step The timeline: communication, steps, roles Task ID Phase Date Start

Getting to production: step-by-step The timeline: communication, steps, roles Task ID Phase Date Start Time Duration (CT) 1 Pre Upgrade 8/16/16 Day of 2 Pre Upgrade 8/16/16 5: 00 PM 3 Upgrade 8/16/16 4 Upgrade 5 Task Team Person(s) Send final downtime notification to users SITE 5 min Team Notification for final Go Ahead (via teleconference) All 5: 05 PM 5 min Disable Calendar D and Interfaces OTTR Aaron 8/16/16 5: 10 PM 5 min Notify Site DBA ready for backup of production DB via email OTTR Aaron Upgrade 8/16/16 5: 10 PM 4 hrs Upgrade user desktops to Chrome or IE 11 (in parallel with db update) SITE-IT 6 Upgrade 8/16/16 5: 15 PM 30 min Back up prod DB - Notify Aaron when underway via email SITE-DBA 9 Upgrade 8/16/16 5: 40 PM 5 min Notify Aaron DB back up complete and ready for install via email SITE-DBA 10 Upgrade 8/16/16 5: 45 PM 4 hrs Additional Config/DB Conversion Steps; restart cal. D OTTR Aaron 11 Upgrade 8/16/16 9: 45 PM 5 min Notify Users System Ready for Site Validation OTTR Aaron 12 Post Upgrade 8/17/16 8: 00 AM 1 hr Site Validation-Team check-in teleconference at 9: 00 AM SITE 13 Post Upgrade 8/17/16 9: 00 AM 30 min Restore interfaces and respool messages in queue OTTR Aaron 14 Post Upgrade 8/17/16 9: 30 AM email to users noting that work is complete and system is ready OTTR Aaron 13

Lessons Learned Communication is KEY to success Test your workflow…Clinical and IT testing important

Lessons Learned Communication is KEY to success Test your workflow…Clinical and IT testing important ◦ Check Crystal Reports-several known issues Have everyone ready to support verification testing ◦ Team effort: OTTR, Clinical, Site IT, DBA ◦ Getting users logged in can be a challenge (icon pushes fail, etc) ◦ Browser security settings in IE must be correct Have a good plan to capture and communicate issues ◦ OTTR will help track and keep an issue list-still need coordination at site Provide feedback-we’re here to help OTTR 7 can make life easier! 14

Questions What else would you like to know? 15

Questions What else would you like to know? 15

Next up… Xyn. Management: 16

Next up… Xyn. Management: 16