Ogden Air Logistics Complex F16 RLCRS Program Update

  • Slides: 14
Download presentation
Ogden Air Logistics Complex F-16 RLCRS Program Update Rik Crowther Senior Engineer OO-ALC/EN SME:

Ogden Air Logistics Complex F-16 RLCRS Program Update Rik Crowther Senior Engineer OO-ALC/EN SME: Rik Crowther OO-ALC/EN DSN: 586 -5361 DISTRIBUTION A. Approved for public release: Distribution Unlimited. HAFB ref# 13 -03 -11_AMXG_041 Built Right. . . Ready to Fight

Overview OGDEN AIR LOGISTICS COMPLEX n Plastic Media Blast n RLCRS process data n

Overview OGDEN AIR LOGISTICS COMPLEX n Plastic Media Blast n RLCRS process data n Benefits and issues n Planned Improvements n Future Implementations

PMB Process OGDEN AIR LOGISTICS COMPLEX n 2000 lbs. of haz. waste per AC

PMB Process OGDEN AIR LOGISTICS COMPLEX n 2000 lbs. of haz. waste per AC n Multiple operators in PPE n 10 -14 Flow days n 500+ man hrs. (prep, blast, deprep, pre & sand for paint) n Reduces fatigue life of OML skins Built Right. . . Ready to Fight

RLCRS OGDEN AIR LOGISTICS COMPLEX n 10 -12 lbs. of waste n 40 -50%

RLCRS OGDEN AIR LOGISTICS COMPLEX n 10 -12 lbs. of waste n 40 -50% man hrs. reduction n 30% reduction in flow days n Removes worker from PMB environment n No impact to Airworthiness

Process Data Summary OGDEN AIR LOGISTICS COMPLEX 600 500 Man hours 400 Baseline (PMB

Process Data Summary OGDEN AIR LOGISTICS COMPLEX 600 500 Man hours 400 Baseline (PMB / Paint Prep) 300 Sanding Laser 200 100 0 85 -1468 86 -0335 90 -0826 91 -0476 89 -2109 89 -2076 88 -0472 Built Right. . . Ready to Fight 87 -0394

RLCRS Average Process Hours OGDEN AIR LOGISTICS COMPLEX n RLCRS prep & operations: 139

RLCRS Average Process Hours OGDEN AIR LOGISTICS COMPLEX n RLCRS prep & operations: 139 hours n RLCRS flow time: 67 hours n RLCRS flow days w/2 shifts: 4 n Sanding: 138 hours n Total Process: 278 hours n Total Process flow: 7 days

RLCRS vs. PMB OGDEN AIR LOGISTICS COMPLEX Reductions: n Total Process hrs: 200 -300

RLCRS vs. PMB OGDEN AIR LOGISTICS COMPLEX Reductions: n Total Process hrs: 200 -300 n Flow days: 2 -4 n Hazardous Waste: 2000 lbs.

The “Not So Great” OGDEN AIR LOGISTICS COMPLEX Reductions: n Increase in sanding hours

The “Not So Great” OGDEN AIR LOGISTICS COMPLEX Reductions: n Increase in sanding hours n 40 -80 additional hours of sanding n Mostly bottom of AC n Stress/Strain complaints from AC painters n Increase exposure to sanding dust

RLCRS Improvements OGDEN AIR LOGISTICS COMPLEX n EZP building RLCRS for Testing: n Optimization

RLCRS Improvements OGDEN AIR LOGISTICS COMPLEX n EZP building RLCRS for Testing: n Optimization for multiple AC n Variable coating stack ups n Dem/val future system upgrades n Planned Upgrades for RLCRS: n Reduce robot time 15 -20% (30 -50 hrs) n Evaluating robotic assist sanding technologies n Evaluating improved vacuum systems for sanding equipment Built Right. . . Ready to Fight

RLCRS Future Systems OGDEN AIR LOGISTICS COMPLEX n Repurpose C-130 system for increased F-16

RLCRS Future Systems OGDEN AIR LOGISTICS COMPLEX n Repurpose C-130 system for increased F-16 workload at OO-ALC (F-35, F-22, A -10, Off air frame components) n B-1 program n AMARG program Built Right. . . Ready to Fight

Questions? OGDEN AIR LOGISTICS COMPLEX Built Right. . . Ready to Fight

Questions? OGDEN AIR LOGISTICS COMPLEX Built Right. . . Ready to Fight

RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX

RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX

RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX

RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX

RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX

RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX