Ogden Air Logistics Complex F16 RLCRS Program Update
- Slides: 14
Ogden Air Logistics Complex F-16 RLCRS Program Update Rik Crowther Senior Engineer OO-ALC/EN SME: Rik Crowther OO-ALC/EN DSN: 586 -5361 DISTRIBUTION A. Approved for public release: Distribution Unlimited. HAFB ref# 13 -03 -11_AMXG_041 Built Right. . . Ready to Fight
Overview OGDEN AIR LOGISTICS COMPLEX n Plastic Media Blast n RLCRS process data n Benefits and issues n Planned Improvements n Future Implementations
PMB Process OGDEN AIR LOGISTICS COMPLEX n 2000 lbs. of haz. waste per AC n Multiple operators in PPE n 10 -14 Flow days n 500+ man hrs. (prep, blast, deprep, pre & sand for paint) n Reduces fatigue life of OML skins Built Right. . . Ready to Fight
RLCRS OGDEN AIR LOGISTICS COMPLEX n 10 -12 lbs. of waste n 40 -50% man hrs. reduction n 30% reduction in flow days n Removes worker from PMB environment n No impact to Airworthiness
Process Data Summary OGDEN AIR LOGISTICS COMPLEX 600 500 Man hours 400 Baseline (PMB / Paint Prep) 300 Sanding Laser 200 100 0 85 -1468 86 -0335 90 -0826 91 -0476 89 -2109 89 -2076 88 -0472 Built Right. . . Ready to Fight 87 -0394
RLCRS Average Process Hours OGDEN AIR LOGISTICS COMPLEX n RLCRS prep & operations: 139 hours n RLCRS flow time: 67 hours n RLCRS flow days w/2 shifts: 4 n Sanding: 138 hours n Total Process: 278 hours n Total Process flow: 7 days
RLCRS vs. PMB OGDEN AIR LOGISTICS COMPLEX Reductions: n Total Process hrs: 200 -300 n Flow days: 2 -4 n Hazardous Waste: 2000 lbs.
The “Not So Great” OGDEN AIR LOGISTICS COMPLEX Reductions: n Increase in sanding hours n 40 -80 additional hours of sanding n Mostly bottom of AC n Stress/Strain complaints from AC painters n Increase exposure to sanding dust
RLCRS Improvements OGDEN AIR LOGISTICS COMPLEX n EZP building RLCRS for Testing: n Optimization for multiple AC n Variable coating stack ups n Dem/val future system upgrades n Planned Upgrades for RLCRS: n Reduce robot time 15 -20% (30 -50 hrs) n Evaluating robotic assist sanding technologies n Evaluating improved vacuum systems for sanding equipment Built Right. . . Ready to Fight
RLCRS Future Systems OGDEN AIR LOGISTICS COMPLEX n Repurpose C-130 system for increased F-16 workload at OO-ALC (F-35, F-22, A -10, Off air frame components) n B-1 program n AMARG program Built Right. . . Ready to Fight
Questions? OGDEN AIR LOGISTICS COMPLEX Built Right. . . Ready to Fight
RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX
RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX
RLCRS De-painted AC OGDEN AIR LOGISTICS COMPLEX
- Air logistics complex
- Is an alternative of log based recovery
- F16 net
- F16 mc
- General dynamics f-16cm fighting falcon
- Pill concocter
- Hubungan air dengan tanah
- Simple compound complex and compound-complex sentences quiz
- Ghon complex and ranke complex
- Simple compound complex rules
- Electra complex vs oedipus complex
- Psychodynamic and psychoanalytic theory difference
- Mbti percentages
- Gibbons v ogden decision
- Ogden trece colors