ODOT Fix-It Program
2
Major Fix-It programs Bridge & Seismic Pavements Culverts Safety 3
Fix-It routes 4
Pavement Program components Interstate Maintenance Low volume roads National Highway System Maintenance & Operations 5
State highway pavement conditions Percent fair or better
Gathering pavement data Windshield surveys 7
Gathering pavement data Contractor images and ratings Smoothness and rut depth Friction
Data analysis 9
Data Condition score Pavement age Maintenance history Highway importance Climate Evaluation Considerations in identifying needs Potential fixes Cost Impact on condition rating 10
Bridge Program components Major bridge maintenance Seismic Preservation Rehab/Replacement 11
Fix-It route bridge conditions – percent fair or better 12
Bridges in poor condition on Fix-It priority corridors Blue = bridges built prior to 1970 Red = bridges built between 1970 and 1999 Green = bridges built between 2000 -2016 Bridges Pre 1970 -1999 2000 -2016 13
Bridge inspection
Inspection data collection Slab Deck Bridge Top flange Truss Superstructure Gusset plates Column Substructure Abutment
Project selection from other bridge data sources Maintenance Region bridge crews and MBM engineer provides input Inspectors Bridge inspectors provide input on bridge conditions Preservation Bridge preservation engineer provides list of painting and cathodic protection needs Preliminary needs list
Preliminary bridge needs list review Region staff review list and provide comment Desk scoping list Bridge program manager reviews list 17
Local Bridge Program Large Bridge Deck area of 30, 000 square feet or greater Small Bridge On the Federal. Aid System Small Bridge Not on the Federal-Aid System 18
Culvert Program components Large culverts Major culvert maintenance Priority route Fish passage 19
Culvert conditions Blue = 33% culverts in critical/poor condition Red = 34% culverts in fair condition Green = 33% culverts in good condition Culverts Poor/critical Fair Good 20
Condition assessment Invert condition rating Good Fair Poor Critical 21
Data evaluation 22
Considerations in identifying needs 23
ODOT Safety programs All Roads Transportation Safety Hot spot Systemic 24
Crash data Data are compiled for all reported crashes on all roads.
Safety applications 26
Safety project selection • Evaluate applications. • Validate solution and cost. • Prioritize applications based on benefit cost. • Create 150 -200% list of potential STIP projects. • Verify project details and support with local agencies. 27
Fix-It projects: • Manage the condition of the system. • Collect and analyze data. • Considers program priorities and leadership directives. • Considers available funding. 28