Norfund Anniversary Conference Raymond Carlsen, CEO Scatec Solar Oslo, September 7, 2017 Our values

Norfund Anniversary Conference Raymond Carlsen, CEO Scatec Solar Oslo, September 7, 2017 Our values Predictable Driving results Changemakers Working together Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com

An independent solar power producer IN OPERATION 322 MW FY 2016 PRODUCTIO N 791

An independent solar power producer IN OPERATION 322 MW FY 2016 PRODUCTIO N 791 GWh OPERATING PLANTS 5 COUNTRIES PROJECTS UNDER DEVELOPME NT 23 COUNTRIES Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com 2

Plants in operation South Africa Kalkbult • Capacity: 75 MW • Grid connection: Q

Plants in operation South Africa Kalkbult • Capacity: 75 MW • Grid connection: Q 3 2013 • Energy production: 150, 000 MWh per year Linde • Capacity: 40 MW • Grid connection: Q 3 2014 • Energy production: 94, 000 MWh per year Dreunberg • Capacity: 75 MW • Grid connection: Q 3 2014 • Energy production: 178, 000 MWh per year Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com 36

Plants in operation Rwanda and Honduras ASYV, Rwanda • Capacity: 8. 5 MW •

Plants in operation Rwanda and Honduras ASYV, Rwanda • Capacity: 8. 5 MW • Grid connection: Q 3 2014 • Energy production: 15, 500 MWh per year Agua Fria, Honduras • Capacity: 60 MW • Grid connection: Q 3 2015 • Energy production: 103, 000 MWh per year Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com 46

Plants in backlog Egypt and South Africa Round 4, South Africa • Capacity: 258

Plants in backlog Egypt and South Africa Round 4, South Africa • Capacity: 258 MW • Expected grid connection: 2018/2019 • Energy production: 645 GWh per year Egypt • Capacity: 400 MW • Expected grid connection: 2018/2019 • Energy production: 870 GWh per year Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com 56

Plants in backlog Mozambique and Honduras Mocuba, Mozambique • Capacity: 40 MW • Expected

Plants in backlog Mozambique and Honduras Mocuba, Mozambique • Capacity: 40 MW • Expected grid connection: 2018 • Energy production: 77, 000 MWh per year Los Prados, Honduras • Capacity: 53 MW • Expected grid connection: 2018 • Energy production: 110, 000 MWh per year Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com 66

Key challenges • Political risk / predictability • Land acquisition and possible resettlement •

Key challenges • Political risk / predictability • Land acquisition and possible resettlement • Currency risk / convertibility • Stake holder management • Security • Changing market conditions Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com 7

Thank you Our values • Predictable • Driving results • Changemakers • Working together

Thank you Our values • Predictable • Driving results • Changemakers • Working together Copyright: Scatec Solar ASA www. scatecsolar. com • post@scatecsolar. com