NBCC (India) Limited (A Govt. of India Enterprise) PROGRESS REPORT CRYSTAL HOMES NOVEMBER 2020
Project Name: Construction/Rectification of Balance works / Left Out works of SILICON CITY PHASE -3 (CRYSTAL HOMES). Plot no. GH 01, Sector-76, Noida, Uttar Pradesh.
COMPLETION SCHEDULE Sl. No. Tower No. of Un-finished Flats Completion schedule Completion as on 30. 11. 2020 (%) 1 T 1 108 Jan. - 2023 3% 2 T 2 108 Jan. - 2023 0% 3 T 3 108 Aug. - 2022 5% 4 T 4 108 Aug. - 2022 4. 5% 5 T 5 108 Aug. - 2022 4. 5% 6 T 6 108 Jan. - 2023 0% 7 T 7 108 Jan. - 2023 0% 8 T 8 108 Jan. - 2023 1% 9 T 9 108 Jan. - 2023 2. 5%
COMPLETION SCHEDULE External MEP Works Sl. No Description Completion schedule Completion as on 30. 11. 2020 (%) 1 DGs Oct- 2022 0% 2 Transformers Jan- 2023 0% 3 STP Jan- 2023 0% 4 WTP Jan- 2023 0% 5 Firefighting works Jan- 2023 0% 6 Basement Ventilation Jan- 2023 0% 7 Basements Jan- 2023 0%
COMPLETION SCHEDULE EXTERNAL DEVELOPMENT WORKS Sl. No Description Completion schedule 1 Boundary Wall Jan- 2023 2 Horticulture work Jan- 2023 3 Electrical Work Jan- 2023 4 Pathway/Road Jan- 2023 Completion as on 30. 11. 2020 (%) 0% 0%
PROGRESS PHOTOGRAPHS
Blockwork/Brickwork of Tower 3 (left), 4 & 5 (right) is in progress
Conduit work- Tower 3, 4 & 5
Reinforcement work of Tower -4 is in progress
Fire fighting work of Tower-3, 4 & 5 is in progress
Lower basement shuttering work of Tower-9 is in