NA 2014 2015 YETS schedule week by week
NA 2014 -2015 YETS: schedule week by week S. Evrard
Week 51 üPainting works in TA 801 by Presiozo • Repair work of TT 84 floor by CE contractor (4/5) üED stop on 19/12 üPR PA 80 maintenance üLight modification H 2 zone 152. üPPE 132 shielding üXEMC. 516 in PPE 124 üOuverture visee geometres H 6 et H 8 üH 6/H 8 alignment campaign (TT 82 & EHN 1)
TA 801 painting
Week 2 üMCWV: • Consignations • Service removal • Plexiglas protection removal • Transport to B. 867 üLight modification (and cabinet relocation, in week 3) H 2 zone 142. üPPE 132 shielding üPR PA 80 maintenance • MNP 22 (Ship) to be moved - CANCELED • Installation XTDV GIF: in progress • EHN 1 gallery cleaning: not started üH 6/H 8 alignment campaign (TT 82)
Week 3 • Remplacement de 4 réducteurs de pression sur T 2 T 4 T 6 et TCSC (F. Moro) S 3, 4, 5 üRepair work of TT 84 floor(last section) üMCWV: üTransport to B. 867 üPR 537 (TCC 2) maintenance üEHN 1 gallery cleaning üLight modification H 2 zone 132. üH 2: zone 142/134 steel beam installation (with QNL 500 & QNL 524 removal/reinstallation) üH 6/H 8 alignment campaign (TT 82&TCC 2) ümagnet MBW. 043089 exchange üStarter exchange on TDC 2 lights. Cubicle exchange in mezzanine (TCC 2 led light control)
TCC 2 led light control
Magnet MBW. 043089 exchange in TCC 2
MCWV transport from TT 84 to B. 867
MCWV repair @ 867
Week 4 üRemplacement de 4 réducteurs de pression sur T 2 T 4 T 6 et TCSC (F. Moro) S 3, 4, 5 üH 6/H 8 alignment campaign (TCC 2) üTarget T 2 T 4 T 6 upgrade (preparation) • Slot for magnet MBW. 043089 exchange(Friday) üOpen survey shielding at the end of TCC 2(by Wednesday) and TT 83 door (by Tuesday) üOverhead crane load test (PA 80 & TCC 2) • MDX magnet installation • MDX service connexion üCovers on DC cable cumbs (Test + implementation) üILS tetra installation
TCC 2 new MDX. 042. 094 S. Girod EM-MEF 11
TCC 2 new MDX. 042. 094 S. Girod EM-MEF 12
Week 5 • MDX magnet installation • MDX service connexion • Target T 2 T 4 T 6 upgrade (target box, monitors and motors) • Water leaks TDC 2 • Réparation des fuites et/ou remplacement des vannes si réparations impossible S 5 (B. Bannister) • Remplacement de 4 réducteurs de pression sur T 2 T 4 T 6 et TCSC (F. Moro) S 3, 4, 5 • H 6/H 8 alignment campaign (TCC 2) • H 6 collimator exchange • Reserve slot for magnet MBW. 043089 reinstallation • MBPL 498 magnet to be installed in H 4_134 • Re-Connexion of vacuum pipes, collars, . . H 6 & H 8.
Week 6 • Contingency week • H 6/H 8 Visual patrol (after survey) • Alignment of new magnets (MDX, MCW, MBPL, collimator H 6) • Closure of all the areas on Friday 6 th at noon • OP patrol on Friday 6 th PM
Week 7 • DSO tests on 09/02 AM • Beam to SPS: 09/02 PM • Scan EHN 1 !! NEXT MEETINGS on FRIDAY at 9. 00 !! Later MCWV repair and reinstallation before MCWV control cable replacement restart of P+ run in April