Mountain Ridge Project winter presentation The making of
- Slides: 55
Mountain Ridge Project - winter presentation - The making of Ridge University Engineering Building Owner Architect Engineer Construction Manager APPrentice Regina Pau, Sunnyvale, CA Katrin Wender, Weimar, Germany Martha Del Campo, Stanford, CA Kris Grotelueschen, Stanford, CA Grace Yamamoto, Stanford, CA AEC
Site conditions AEC
Functional spaces and relationship AEC
Gravity Loads • Dead Loads – Lightweight Concrete Slab: 55 psf – Steel Deck: 5 psf – Partition Walls: 20 psf – Finishes, Lights: 10 psf – Ducts, Pipes: 5 psf – Roofing System: 25 psf • Live Loads – – – Offices: 50 psf Classrooms: 40 psf Auditorium: 50 psf Corridors: 100 psf Snow: 50 psf (Altitude~2500 ft. ) AEC
Sample Gravity Load Path AEC
Lateral Loads • Wind – Exposure B – V 33 = 70 mph • Earthquake – Zone 3 – Type B Fault Zone AEC
Sample Lateral Load Path AEC
Foundation Considerations • Soil – – Stiff Sand Bearing Capacity: 5 ksf Low settlement Frost Depth: 4 ft. • Foundation – Wall footings at perimeter – Column footings under interior columns – Slab on Grade AEC
Construction • Budget is reduced for 4% inflation over the next 14 years. (2015 Budget = 2001 Budget x 0. 9614) • The money available for the building is further reduced by overhead and profit. AEC
Redesign - design concept “soft fluid among stones – water among stones“ AEC
Redesign - schematic layout AEC
Redesign - schematic layout AEC
Redesign - schematic layout AEC
Redesign - circulation AEC
Redesign - Structure AEC
Redesign - Structure Original Design Redesign Perimeter frame with staggered truss Retain Exterior bracing Retain King-post truss over Auditorium Retain Shear Wall core Propose braced frame core Add basement for gymnasium AEC
Redesign - Structure • Eccentrically Braced Frame – Efficient, ductile system – Eliminates need to coordinate concrete and steel workers • Shear Wall – Ductile in combination with frame system – Traditional, widely used – Less expensive in general AEC
Redesign - Construction Foundations Complete 7/1/15 Superstructure Complete 10/14/15 Finishes Complete 5/25/16 Building Closed In 1/6/16 AEC
Redesign - Construction Total Budget: $2, 842, 260 Breakdown of Costs: AEC
Redesign - Construction Equipment • Largest crane pick is a 3 kip column • Hydraulic excavator for basement • Concrete will be placed with a pump AEC
Redesign Site Parking - Construction Material Laydown Site Office Sub Trailers Site Entrance Moving Crane Additional Material Area Direction of Progression AEC
Alternative 2 - design concept “water among stone – water on the mountain” AEC
Alternative 2 1 – schematic layout 2 3 AEC
Alternative 2 1 2 - circulation 3 AEC
Alternative 2 – exterior and interior AEC
Alternative 2 - Structure AEC
Alternative 2 - Structure • Concept – Maximize floor-toceiling height • Thin slab on columns • Eliminate internal beams – Reduce finishing costs – Allow large windows APP C E AEC
Alternative 2 - Structure • Gravity System – Flat Slab System • Minimum allowable depth: 7 in. (probably greater) – Post-tensioned slab • Approximate depth: 8 in. Slab Drop panel Column – Waffle slab over Auditorium • Approximate total depth: 24. 5 in. (4. 5 in. top slab) • 30” x 30” voids, 6”ribs @ 36” AEC
Alternative 2 - Structure • Lateral Load Systems – Concrete Cast in Place SMRF – Precast Concrete SMRF – Shear Wall for redundancy Typical Member Sizes: Ext. Beam: 18 x 24 in. Ext. Column: 18 x 18 in. Int. Column: 12 x 12 in. AEC
Alternative 2 - Structure • Sample Connection Details – Cast in Place SMRF – Precast s. MRF post-tensioning mild steel bars (from pankow. com) AEC
Alternative 2 - Structure • Exterior Cladding – Finished concrete (CIP or Precast) • Saves material cost • Concrete must be designed for thermal effects – Precast stone cladding • Adds cost for material and installation • Lightweight materials • Lower life-cycle costs (i. e. insulation) AEC
Alternative 2 - Structure • Roofing System and Skylight Wood truss with steel tension members AEC
Alternative 2 Foundations Complete 6/24/15 Superstructure Complete 9/23/15 - Construction Building Closed in 12/16/15 Finishes Complete 6/1/16 AEC
Alternative 2 - Construction Total Budget: $2, 732, 912 Breakdown of Costs: AEC
Alternative 2 - Construction Equipment • Largest crane pick for bucket of concrete • Hydraulic excavator foundations • Concrete will be placed with a bucket AEC
Alternative 2 Site Entrance Sub Trailers - Construction Material Laydown Site Office Direction of Progress Moving Crane Additional Material Area Site Parking AEC
Alternative 3 - design concept “water among stones – waterfall and rocks“ AEC
Alternative 3 – schematic layout AEC
Alternative 3 – schematic layout AEC
Alternative 3 – schematic layout AEC
Alternative 3 - circulation AEC
Alternative 3 - Structure AEC
Alternative 3 - Interaction • A/E Interaction A Proposal E Proposal A Feedback E Change Concept Design AEC
Alternative 3 - Structure • Lateral Load Systems – Steel EBF Core – Concrete Shear Wall Core • Gravity Load Systems – Concrete Frame – Steel Frame – Composite floor slab Steel: Concrete: Typical Column: W 14 x 74 18” x 18” Worst-Case Beam: W 18 x 60 18” x 30” AEC
Alternative 3 - Structure • Details Steel: Concrete: AEC
Alternative 3 - Construction Foundations Complete 6/18/15 Finishes Complete 5/12/16 Superstructure Complete 9/11/15 Building Closed In 12/10/15 AEC
Alternative 3 - Construction Total Budget: $3, 447, 825 Breakdown of Costs: AEC
Alternative 3 - Construction Equipment • Largest crane pick for 3. 5 kip steel column • Hydraulic excavator foundations • Concrete will be placed with a pump at the foundations, and shotcrete for the shear walls AEC
Alternative 3 Site Parking - Construction Material Laydown Site Office Sub Trailers Site Entrance Moving Crane Direction of Progress Additional Material Area AEC
Construction AEC
Final Decision Matrix A E C $2. 8 Million 5/25/16 $2. 7 Million 6/01/16 $3. 4 Million 5/12/16 • Owner’s choice • No extended footprint • Fun spiral stairs • 2 Entrances Benefits • Efficient structural • Concrete frame & slab • Privacy/security req. good • Concrete shear core • better MEP & floor depth • Concrete system • Straightforward structure Drawbacks • Design like last years • Public space areas • Lack of daylight • Only one entrance • Extended footprint • Not risky for A • Roof truss & MEP intake • Deep floor beams & MEP • Lack of vertical • Stream threats mechanical path space • Skylight leaking
Design Process timeline Week 1 -3 Week 4 -6 Week 7 -8 Week 9 -10 A Understand program, discussion Redesign, consult E Initial Alt 3 concepts, form idea Completion A proposal E Collecting general information Redesign & A Alt 2, consulting mentors & C Alt 3 & talking with A C Collecting general information & mentors Quantities, m Schedule & Quantities & aterials (AE), Equipment & materials schedule & mentors APP confusion Decide on Alt 2 Archit. Consult A Design basics and consult AEC Asking and adjusting
Team Interaction- Clerestory Windows E C $$$ EC APP A A Concept! C E OK APP Narrow Hallways AEC
Lessons Learned/ Future Improvements Lessons: Improvements: • Skill recognition • More efficient presentation of ideas • Clarified discipline goals and roles in design, how disciplines respond to information • Clear, straightforward, proactive synchronous and asynchronous communication • More thorough use of communication resources (i. e, Recall) • Better online documentation of information and process • Organizing information for documentation (i. e. , web site) • Working with technology AEC
Final choice - challenges architecture: construction manager: some interesting questions still open Reduce budget through continued value engineering - facades ? - roof garden ? - spiral stairs engineer: Concrete system Atrium skylight MEP space team interaction: Value enginering for budget Integration of mechanical systems into current architecture Use of shotcrete for shear walls System for glass roof area AEC
- Type line in fingerprint
- Projecting mountain ridge
- Winter kommt winter kommt flocken fallen nieder
- Winter kommt winter kommt flocken fallen nieder
- Winter kommt winter kommt flocken fallen nieder
- Winter driving safety presentation
- Defensive driving presentation
- Mountains biome
- Is making inference simply making a guess
- War making and state making as organized crime summary
- Hình ảnh bộ gõ cơ thể búng tay
- Frameset trong html5
- Bổ thể
- Tỉ lệ cơ thể trẻ em
- Voi kéo gỗ như thế nào
- Tư thế worms-breton
- Chúa sống lại
- Các môn thể thao bắt đầu bằng tiếng bóng
- Thế nào là hệ số cao nhất
- Các châu lục và đại dương trên thế giới
- Cong thức tính động năng
- Trời xanh đây là của chúng ta thể thơ
- Mật thư anh em như thể tay chân
- Phép trừ bù
- Phản ứng thế ankan
- Các châu lục và đại dương trên thế giới
- Thể thơ truyền thống
- Quá trình desamine hóa có thể tạo ra
- Một số thể thơ truyền thống
- Cái miệng bé xinh thế chỉ nói điều hay thôi
- Vẽ hình chiếu vuông góc của vật thể sau
- Thế nào là sự mỏi cơ
- đặc điểm cơ thể của người tối cổ
- Thế nào là giọng cùng tên? *
- Vẽ hình chiếu đứng bằng cạnh của vật thể
- Phối cảnh
- Thẻ vin
- đại từ thay thế
- điện thế nghỉ
- Tư thế ngồi viết
- Diễn thế sinh thái là
- Dot
- So nguyen to
- Tư thế ngồi viết
- Lời thề hippocrates
- Thiếu nhi thế giới liên hoan
- ưu thế lai là gì
- Hổ đẻ mỗi lứa mấy con
- Sự nuôi và dạy con của hươu
- Hệ hô hấp
- Từ ngữ thể hiện lòng nhân hậu
- Thế nào là mạng điện lắp đặt kiểu nổi
- Occipital brow presentation
- 4 maneuvers of leopold
- Font sans
- Final project presentation template